Job Info for 6443-84-001

County: BELL Highway: US0190 Date: 02/01/2024 (9 months ago) Engineer's Estimate: $1,510,250 Control Number: 6443-84-001
Project: MMC - 644384001 District: WACO Time: 183 CALENDAR DAYS Type: HOT MIX
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,510,250.00
BIG CREEK CONSTRUCTION, LTD.   $1,467,750.00 1
-2.81% | -$42,500.00
TEXAS MATERIALS GROUP, INC.   $1,566,582.50 2
3.73% | $56,332.50
6.73% | $98,832.50
KNIFE RIVER CORPORATION - SOUTH   $1,660,000.00 3
9.92% | $149,750.00
13.1% | $192,250.00
5.96% | $93,417.50

Bid Items

Items: 4, 0 filtered
BELL US0190  |  WACO  |  6443-84-001  |  02/01/2024  |  $1,510,250  |  MMC - 644384001  |  HOT MIX  |  183 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate BIG CREEK CONSTRUCTION, LTD. TEXAS MATERIALS GROUP, INC. KNIFE RIVER CORPORATION - SOUTH
8011 6001 D-GR HMA(SQ) TY D PG 64-22 (PICKUP) TON 1,750.000 $73.000 $65.000 $76.350 $76.000
8011 6002 D-GR HMA(SQ) TY D PG 64-22 (DELIVERY) TON 12,000.000 $90.000 $88.000 $93.910 $98.000
8011 6014 D-GR HMA(SQ)TY B PG 64-22 (PICKUP) TON 1,500.000 $65.000 $62.000 $66.350 $74.000
8011 6015 D-GR HMA(SQ)TY B PG 64-22(DELIVERY) TON 2,500.000 $82.000 $82.000 $82.610 $96.000
Totals: $1,510,250.00 $1,467,750.00 $1,566,582.50 $1,660,000.00