Job Info for 0366-04-027

County: WILSON Highway: SH 123 Date: 01/05/2024 (10 months ago) Engineer's Estimate: $42,571,905 Control Number: 0366-04-027
Project: F 2024(696) District: SAN ANTONIO Time: 646 WORKING DAYS Type: SURFACING/ROADWAY RESTORATION
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $42,571,905.35
HUNTER INDUSTRIES, LTD.   $39,483,857.69 1
-7.25% | -$3,088,047.66
TEXAS MATERIALS GROUP, INC.   $43,877,776.99 2
3.07% | $1,305,871.64
11.13% | $4,393,919.30
CK NEWBERRY, LLC   $46,964,574.77 3
10.32% | $4,392,669.42
18.95% | $7,480,717.08
7.03% | $3,086,797.78
Subcontractor Percentage Amount
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED 7.61% $3,004,721.57
TRP CONSTRUCTION GROUP, LLC 1.93% $762,038.45
DEPENDABLE FENCE 1.54% $608,051.41
LONE STAR EROSION CONTROL 0.61% $240,851.53
MURRAY CONSTRUCTION 0.26% $102,658.03
EGGEMEYER LAND CLEARING, LLC 0.13% $51,329.02
TITAN MILLING INC. 0.12% $47,380.63
PROFESSIONAL TRAFFIC CONTROL LLC 0.05% $19,741.93
THE LEVY COMPANY, INC. 0.04% $15,793.54
Total: 12.29% $4,852,566.11

Bid Items

Items: 164, 0 filtered
WILSON SH 123  |  SAN ANTONIO  |  0366-04-027  |  01/05/2024  |  $42,571,905  |  F 2024(696)  |  SURF/ROADWAY RESTOR  |  646 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HUNTER INDUSTRIES, LTD. TEXAS MATERIALS GROUP, INC. CK NEWBERRY, LLC
100 6002 PREPARING ROW STA 523.180 $2,250.000 $789.200 $175.000 $250.000
104 6001 REMOVING CONC (PAV) SY 116,289.000 $18.250 $5.800 $10.250 $15.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 385.000 $22.400 $17.500 $35.000 $35.000
104 6028 REMOVING CONC (MISC) SY 2,723.000 $45.000 $7.000 $15.000 $40.000
105 6026 REMOVE STAB BASE & ASPH PAV (13"-18") SY 141,604.000 $12.000 $6.180 $9.700 $15.000
105 6046 REMOVING STAB BASE & ASPH PAV (0"-10") SY 116,289.000 $10.000 $3.600 $4.100 $8.000
110 6001 EXCAVATION (ROADWAY) CY 28,580.000 $25.000 $17.500 $22.000 $16.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 16,849.000 $22.000 $17.500 $25.000 $15.000
150 6002 BLADING HR 192.000 $163.000 $108.000 $175.000 $150.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 87,162.000 $4.200 $1.770 $1.550 $1.200
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 43,581.000 $0.320 $0.170 $0.160 $0.200
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 43,581.000 $0.280 $0.180 $0.170 $0.200
164 6041 DRILL SEEDING (TEMP) (WARM) SY 43,581.000 $0.220 $0.130 $0.120 $0.130
164 6043 DRILL SEEDING (TEMP) (COOL) SY 43,581.000 $0.220 $0.130 $0.120 $0.130
168 6001 VEGETATIVE WATERING MG 2,722.000 $40.000 $21.000 $24.000 $14.000
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 87,162.000 $1.580 $0.860 $0.820 $1.250
216 6001 PROOF ROLLING HR 192.000 $115.500 $96.000 $135.000 $65.000
247 6475 FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS CY 94,458.000 $53.000 $62.140 $96.000 $80.000
310 6027 PRIME COAT(MC-30 OR AE-P) GAL 61,838.000 $4.830 $4.960 $4.500 $5.000
316 6410 ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR) GAL 124,488.000 $4.160 $4.470 $4.250 $4.500
316 6431 AGGR (TY-PB GR-4) CY 3,458.000 $165.000 $143.150 $140.000 $135.000
401 6001 FLOWABLE BACKFILL CY 677.000 $287.500 $275.400 $255.000 $300.000
403 6001 TEMPORARY SPL SHORING SF 13,596.000 $24.290 $4.940 $15.000 $20.000
432 6001 RIPRAP (CONC)(4 IN) CY 11.800 $1,260.000 $604.800 $560.000 $650.000
432 6002 RIPRAP (CONC)(5 IN) CY 42.000 $845.000 $604.800 $560.000 $650.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 450.600 $988.000 $669.600 $620.000 $725.000
459 6007 GABION MATTRESSES (GALV)(12 IN) SY 377.000 $120.000 $82.770 $62.000 $175.000
462 6001 CONC BOX CULV (3 FT X 2 FT) LF 114.000 $432.360 $568.080 $526.000 $625.000
462 6003 CONC BOX CULV (4 FT X 2 FT) LF 31.000 $489.950 $636.120 $589.000 $650.000
462 6006 CONC BOX CULV (5 FT X 2 FT) LF 43.000 $535.690 $842.400 $780.000 $975.000
462 6045 CONC BOX CULV (3 FT X 2 FT)(EXTEND) LF 29.000 $700.000 $617.760 $572.000 $650.000
462 6046 CONC BOX CULV (3 FT X 3 FT)(EXTEND) LF 121.000 $900.000 $542.160 $502.000 $575.000
462 6048 CONC BOX CULV (4 FT X 3 FT)(EXTEND) LF 43.000 $715.000 $718.200 $665.000 $775.000
462 6049 CONC BOX CULV (4 FT X 4 FT)(EXTEND) LF 152.000 $790.000 $696.600 $645.000 $750.000
462 6052 CONC BOX CULV (5 FT X 4 FT)(EXTEND) LF 22.000 $950.000 $756.000 $700.000 $825.000
462 6053 CONC BOX CULV (5 FT X 5 FT)(EXTEND) LF 222.000 $569.250 $783.000 $725.000 $850.000
462 6067 CONC BOX CULV (8 FT X 8 FT)(EXTEND) LF 270.000 $1,350.000 $1,177.200 $1,090.000 $1,250.000
462 6147 CONC BOX CULV (4 FT X 2.5 FT) (EXTEND) LF 30.000 $1,350.000 $810.000 $750.000 $875.000
464 6005 RC PIPE (CL III)(24 IN) LF 154.000 $110.000 $113.400 $105.000 $130.000
464 6017 RC PIPE (CL IV)(18 IN) LF 293.000 $115.000 $113.400 $105.000 $135.000
464 6030 RC PIPE (ARCH)(CL III)(DES 1) LF 474.000 $237.000 $300.240 $278.000 $335.000
464 6046 RC PIPE (ARCH)(CL IV)(DES 3) LF 134.000 $305.000 $373.680 $346.000 $410.000
466 6171 WINGWALL (PW - 1) (HW=10 FT) EA 1.000 $49,293.370 $62,936.780 $58,275.000 $65,000.000
466 6179 WINGWALL (PW - 1) (HW=4 FT) EA 6.000 $16,503.550 $10,470.560 $9,695.000 $12,000.000
466 6180 WINGWALL (PW - 1) (HW=5 FT) EA 7.000 $38,000.000 $12,052.760 $11,160.000 $13,000.000
466 6181 WINGWALL (PW - 1) (HW=6 FT) EA 4.000 $24,028.060 $17,945.220 $16,616.000 $20,000.000
466 6182 WINGWALL (PW - 1) (HW=7 FT) EA 3.000 $32,946.290 $23,889.520 $22,120.000 $25,000.000
466 6183 WINGWALL (PW - 1) (HW=8 FT) EA 1.000 $30,800.000 $27,215.910 $25,200.000 $29,000.000
466 6184 WINGWALL (PW - 1) (HW=9 FT) EA 4.000 $63,512.000 $39,065.620 $36,172.000 $40,000.000
467 6111 SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C) EA 4.000 $17,930.000 $6,695.980 $6,200.000 $7,000.000
467 6116 SET (TY I)(S=3 FT)(HW= 4 FT)(6:1)(P) EA 9.000 $5,000.000 $6,793.180 $6,290.000 $7,250.000
467 6142 SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P) EA 4.000 $7,015.900 $7,127.980 $6,600.000 $7,500.000
467 6148 SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C) EA 6.000 $7,595.000 $7,451.970 $5,900.000 $8,000.000
467 6174 SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (P) EA 4.000 $12,423.260 $8,099.970 $7,500.000 $8,500.000
467 6181 SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C) EA 1.000 $20,570.000 $8,747.970 $8,100.000 $9,000.000
467 6185 SET (TY I)(S= 5 FT)(HW= 6 FT)(3:1) (C) EA 6.000 $21,832.310 $10,205.960 $9,450.000 $11,000.000
467 6288 SET (TY I)(S= 8 FT)(HW= 9 FT)(3:1) (C) EA 3.000 $20,887.210 $22,679.920 $21,000.000 $24,000.000
467 6357 SET (TY II) (18 IN) (RCP) (3: 1) (P) EA 1.000 $1,250.000 $1,296.000 $1,200.000 $1,600.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 15.000 $2,157.870 $1,684.790 $1,560.000 $2,000.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 10.000 $2,543.000 $1,943.990 $1,800.000 $2,250.000
467 6519 SET (TY II) (DES 1) (RCP) (6: 1) (P) EA 30.000 $2,800.000 $2,807.990 $2,600.000 $3,250.000
467 6545 SET (TY II) (DES 3) (RCP) (6: 1) (P) EA 6.000 $3,718.800 $5,831.980 $5,400.000 $6,000.000
479 6001 ADJUSTING MANHOLES EA 5.000 $1,580.000 $3,499.620 $2,100.000 $2,500.000
480 6001 CLEAN EXIST CULVERTS EA 19.000 $3,110.000 $2,699.990 $2,500.000 $3,000.000
496 6004 REMOV STR (SET) EA 16.000 $660.100 $972.000 $900.000 $1,000.000
496 6005 REMOV STR (WINGWALL) EA 33.000 $1,982.920 $1,350.000 $1,250.000 $1,500.000
496 6007 REMOV STR (PIPE) LF 347.000 $22.000 $31.320 $29.000 $35.000
500 6001 MOBILIZATION LS 1.000 $3,870,167.400 $3,922,753.650 $3,786,000.000 $4,500,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 40.000 $4,640.000 $3,861.490 $7,700.000 $25,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 975.000 $37.750 $26.040 $24.000 $26.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 508.000 $40.000 $30.070 $24.750 $30.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 349.000 $108.000 $73.250 $28.550 $75.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 1,832.000 $10.000 $15.800 $12.000 $15.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 480.000 $28.000 $23.160 $22.000 $10.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 480.000 $4.750 $15.800 $12.000 $5.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 21,246.000 $3.500 $2.360 $2.250 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 21,246.000 $0.530 $1.370 $1.500 $2.000
508 6001 CONSTRUCTING DETOURS SY 3,045.000 $69.000 $79.810 $68.000 $100.000
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 9,220.000 $24.000 $70.000 $32.000 $60.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 85,240.000 $7.000 $10.000 $12.000 $12.000
512 6037 PORT CTB (STKPL)(SGL SLP)(TY 1) LF 11,820.000 $40.000 $10.000 $12.000 $15.000
512 6049 PORT CTB (REMOVE)(SGL SLP)(TY 1) LF 9,220.000 $13.000 $12.000 $17.000 $16.000
529 6002 CONC CURB (TY II) LF 73.000 $32.000 $59.400 $55.000 $60.000
530 6002 INTERSECTIONS (ACP) SY 3,510.000 $55.200 $75.000 $110.000 $100.000
530 6004 DRIVEWAYS (CONC) SY 537.000 $98.770 $113.400 $123.000 $125.000
530 6005 DRIVEWAYS (ACP) SY 4,635.000 $50.910 $69.000 $108.000 $90.000
530 6008 TURNOUTS (ACP) SY 198.000 $72.400 $71.200 $210.000 $90.000
531 6001 CONC SIDEWALKS (4") SY 30.000 $63.850 $86.400 $80.000 $93.200
531 6010 CURB RAMPS (TY 7) EA 1.000 $2,160.410 $2,699.990 $2,500.000 $2,700.000
531 6017 CURB RAMPS (TY 22) EA 1.000 $2,800.000 $3,239.990 $3,000.000 $3,200.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 96,413.000 $3.000 $0.080 $0.160 $0.200
533 6004 RUMBLE STRIPS (CENTERLINE) ASPHALT LF 38,685.000 $3.000 $0.080 $0.200 $0.250
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 2,419.000 $26.440 $23.900 $21.550 $30.000
540 6014 SHORT RADIUS LF 100.000 $39.030 $29.100 $33.500 $40.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 1.000 $1,480.000 $1,975.000 $1,410.000 $2,000.000
540 6017 MTL BM GD FEN (LONG SPAN SYSTEM) LF 300.000 $22.750 $26.550 $20.750 $32.000
540 6020 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 442.000 $75.100 $96.600 $83.000 $100.000
540 6035 MTL BM GD FEN TRANS (31"-28") EA 1.000 $1,250.000 $731.000 $835.000 $1,700.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 5,519.000 $2.000 $3.750 $1.950 $2.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 6.000 $230.630 $225.000 $224.000 $225.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 55.000 $3,175.000 $3,195.000 $2,662.000 $3,250.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 48.000 $215.000 $225.000 $187.000 $225.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 141.000 $975.000 $725.000 $870.000 $1,000.000
545 6004 CRASH CUSH ATTEN (STKPL) EA 32.000 $500.000 $725.000 $525.000 $1,000.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 18.000 $750.000 $850.000 $490.000 $1,000.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 18.000 $8,100.000 $8,150.000 $8,450.000 $10,000.000
552 6002 WIRE FENCE (TY B) LF 33.000 $25.000 $40.720 $75.000 $125.000
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 26.000 $338.350 $200.000 $200.000 $225.000
560 6012 MAILBOX INSTALL-D (TWW-POST) TY 4 EA 3.000 $375.180 $240.000 $240.000 $275.000
560 6013 MAILBOX INSTALL-M (TWW-POST) TY 4 EA 1.000 $651.500 $575.000 $575.000 $650.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 83.000 $715.000 $575.000 $575.000 $650.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 45.000 $860.000 $700.000 $700.000 $800.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 1.000 $1,052.000 $875.000 $875.000 $1,000.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 4.000 $1,050.000 $975.000 $975.000 $1,100.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 1.000 $1,255.000 $1,100.000 $1,100.000 $1,200.000
644 6076 REMOVE SM RD SN SUP&AM EA 124.000 $102.500 $75.000 $75.000 $100.000
658 6047 INSTL OM ASSM (OM-2Y)(WC)GND EA 21.000 $81.060 $55.000 $55.000 $60.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 82.000 $33.500 $30.000 $34.000 $33.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 6.000 $36.290 $32.000 $52.000 $35.000
662 6005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 770.000 $0.400 $0.500 $0.500 $0.650
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 212,059.000 $0.370 $0.400 $0.400 $0.500
662 6030 WK ZN PAV MRK NON-REMOV(W)18"(YLD TRI) EA 92.000 $23.000 $80.000 $80.000 $35.000
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 224,675.000 $0.370 $0.400 $0.400 $0.500
662 6064 WK ZN PAV MRK REMOV (W)6"(BRK) LF 9,027.000 $1.700 $1.350 $1.350 $2.150
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 104,197.000 $1.500 $0.900 $0.900 $0.850
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 108,892.000 $1.500 $0.900 $0.900 $0.850
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 6,772.000 $1.630 $1.630 $1.500 $0.750
666 6018 REFL PAV MRK TY I (W)6"(DOT)(100MIL) LF 1,296.000 $1.500 $1.600 $1.600 $1.050
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 4,760.000 $1.200 $1.000 $1.000 $1.250
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 853.000 $10.800 $8.000 $8.000 $10.000
666 6054 REFL PAV MRK TY I (W)(ARROW)(100MIL) EA 22.000 $188.500 $130.000 $130.000 $200.000
666 6072 REFL PAV MRK TY I(W)(LNDP ARW)(100MIL) EA 6.000 $410.000 $250.000 $250.000 $525.000
666 6078 REFL PAV MRK TY I (W)(WORD)(100MIL) EA 20.000 $207.500 $150.000 $150.000 $225.000
666 6099 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) EA 10.000 $65.000 $55.000 $55.000 $65.000
666 6156 REFL PAV MRK TY I(Y)(MED NOSE)(100MIL) EA 4.000 $395.700 $175.000 $175.000 $300.000
666 6225 PAVEMENT SEALER 6" LF 240,393.000 $0.480 $0.200 $0.250 $0.320
666 6226 PAVEMENT SEALER 8" LF 4,760.000 $1.000 $0.250 $0.250 $0.800
666 6230 PAVEMENT SEALER 24" LF 811.000 $6.000 $1.250 $1.250 $3.500
666 6231 PAVEMENT SEALER (ARROW) EA 18.000 $88.000 $25.000 $25.000 $75.000
666 6232 PAVEMENT SEALER (WORD) EA 16.000 $90.500 $30.000 $30.000 $90.000
666 6233 PAVEMENT SEALER (MED NOSE) EA 4.000 $193.000 $35.000 $35.000 $120.000
666 6237 PAVEMENT SEALER (LNDP ARROW) EA 6.000 $68.500 $50.000 $50.000 $170.000
666 6243 PAVEMENT SEALER (YLD TRI) EA 10.000 $20.750 $10.000 $10.000 $13.000
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 7,122.000 $0.690 $0.700 $0.700 $1.050
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 105,011.000 $0.630 $0.650 $0.650 $0.800
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 3,807.000 $0.650 $0.700 $0.700 $1.050
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 123,156.000 $0.740 $0.650 $0.650 $0.800
672 6007 REFL PAV MRKR TY I-C EA 603.000 $4.800 $4.500 $4.500 $4.750
672 6009 REFL PAV MRKR TY II-A-A EA 3,204.000 $4.650 $4.500 $4.500 $4.750
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 120,144.000 $0.760 $0.350 $0.450 $0.750
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 4.000 $94.000 $50.000 $50.000 $110.000
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 4.000 $94.000 $50.000 $50.000 $115.000
730 6107 FULL - WIDTH MOWING CYC 14.000 $2,100.000 $9,000.000 $5,000.000 $7,000.000
738 6010 CLEANING / SWEEPING (SPOT) MI 30.000 $192.500 $238.280 $240.000 $1,000.000
3076 6001 D-GR HMA TY-B PG64-22 TON 123,712.000 $84.000 $94.400 $92.000 $95.000
3076 6003 D-GR HMA TY-B PG64-22 (EXEMPT) TON 1,326.000 $120.000 $96.800 $107.000 $125.000
3076 6043 D-GR HMA TY-D PG70-22 (LEVEL-UP) TON 11,968.000 $97.000 $105.400 $127.000 $120.000
3076 6066 TACK COAT GAL 63,290.000 $4.000 $3.100 $3.500 $5.000
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 34,097.000 $100.000 $105.400 $111.500 $110.000
4171 6001 INSTALL BRIDGE IDENTIFICATION NUMBERS EA 14.000 $422.370 $305.580 $500.000 $750.000
5003 6006 RETROFIT DET WARN SURF(SURF APP OR CIP) EA 1.000 $600.000 $1,793.320 $1,000.000 $3,000.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $4,600.000 $10,598.120 $20,000.000 $45,000.000
6185 6002 TMA (STATIONARY) DAY 1,212.000 $200.000 $292.710 $250.000 $250.000
6185 6005 TMA (MOBILE OPERATION) DAY 105.000 $550.000 $696.450 $700.000 $550.000
Totals: $42,571,905.35 $39,483,857.70 $43,877,776.99 $46,964,574.77