PREPARING ROW
|
STA
|
394.000
|
$6,000.000
|
$3,500.000
|
$10,000.000
|
$10,000.000
|
$2,600.000
|
$15,080.370
|
$26,650.000
|
$5,488.000
|
|
|
REMOV CONC (PAV)
|
SY
|
76,579.000
|
$10.000
|
$6.850
|
$5.250
|
$6.000
|
$15.000
|
$9.000
|
$6.030
|
$13.000
|
|
|
REMOV CONC (RIPRAP)
|
SY
|
874.000
|
$8.200
|
$12.500
|
$15.000
|
$15.000
|
$15.000
|
$8.000
|
$9.650
|
$30.000
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
3,937.000
|
$18.300
|
$14.500
|
$15.000
|
$7.500
|
$25.000
|
$14.000
|
$8.610
|
$30.000
|
|
|
REMOV CONC (CURB & GUTTER)
|
LF
|
293.000
|
$4.800
|
$12.350
|
$10.000
|
$2.250
|
$10.000
|
$5.000
|
$5.900
|
$30.000
|
|
|
REMOV CONC (FLUME)
|
SY
|
17.000
|
$6.300
|
$40.000
|
$20.000
|
$40.000
|
$25.000
|
$8.000
|
$37.550
|
$100.000
|
|
|
RMV (4"-8") TRT/UNTRT BASE & ASPH PAV
|
SY
|
80,345.000
|
$5.000
|
$4.500
|
$6.000
|
$4.500
|
$3.000
|
$6.000
|
$3.280
|
$8.000
|
|
|
RMV (12"-16") TRT/UNTRT BASE & ASPH PAV
|
SY
|
146,188.000
|
$7.000
|
$6.700
|
$10.750
|
$7.500
|
$6.190
|
$8.000
|
$7.980
|
$12.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
771,996.000
|
$8.000
|
$5.800
|
$6.000
|
$5.000
|
$5.460
|
$7.000
|
$8.560
|
$10.500
|
|
|
EMBANK (FNL)(DC)(TY C)
|
CY
|
243,318.000
|
$11.000
|
$8.000
|
$7.500
|
$6.250
|
$10.000
|
$4.000
|
$6.600
|
$6.250
|
|
|
FURN & PLACE TOPSOIL (4")
|
SY
|
750,353.000
|
$1.500
|
$1.400
|
$1.200
|
$1.500
|
$1.000
|
$1.000
|
$0.690
|
$1.200
|
|
|
BLOCK SODDING
|
SY
|
4,066.000
|
$9.000
|
$5.000
|
$5.000
|
$6.200
|
$5.000
|
$5.700
|
$4.500
|
$5.000
|
|
|
BROADCAST SEED (PERM_RURAL_SAND)
|
SY
|
375,179.000
|
$0.150
|
$0.130
|
$0.130
|
$0.130
|
$0.120
|
$0.110
|
$0.120
|
$0.130
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
750,353.000
|
$0.950
|
$0.550
|
$0.540
|
$0.600
|
$0.500
|
$0.500
|
$0.500
|
$0.530
|
|
|
BOND FBR MTRX SEED (TEMP)(WARM)
|
SY
|
375,179.000
|
$0.410
|
$0.530
|
$0.520
|
$0.600
|
$0.480
|
$0.500
|
$0.480
|
$0.500
|
|
|
BOND FBR MTRX SEED (TEMP)(COOL)
|
SY
|
375,179.000
|
$0.410
|
$0.540
|
$0.530
|
$0.600
|
$0.490
|
$0.500
|
$0.490
|
$0.510
|
|
|
VEGETATIVE WATERING
|
TGL
|
20,680.000
|
$7.000
|
$8.750
|
$8.000
|
$12.500
|
$5.000
|
$8.500
|
$32.000
|
$15.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 1-2) (6")
|
SY
|
888.000
|
$18.000
|
$22.000
|
$22.000
|
$17.500
|
$19.000
|
$54.000
|
$22.220
|
$58.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 1-2) (8")
|
SY
|
368,022.000
|
$24.000
|
$22.000
|
$23.000
|
$21.500
|
$17.500
|
$25.000
|
$21.540
|
$31.000
|
|
|
LIME (QUICKLIME (DRY))
|
TON
|
3,527.000
|
$365.000
|
$335.000
|
$380.000
|
$463.000
|
$330.000
|
$364.000
|
$364.880
|
$330.000
|
|
|
LIME TRT (EXIST MATL)(8")
|
SY
|
195,931.000
|
$5.150
|
$3.750
|
$4.000
|
$2.750
|
$2.770
|
$5.300
|
$8.220
|
$2.700
|
|
|
CEMENT
|
TON
|
3,527.000
|
$210.000
|
$263.000
|
$265.000
|
$322.000
|
$210.000
|
$310.000
|
$268.670
|
$280.000
|
|
|
CEMENT TRT (EXIST MATL)(8")
|
SY
|
195,931.000
|
$3.000
|
$3.750
|
$2.750
|
$2.000
|
$2.770
|
$4.200
|
$2.160
|
$2.700
|
|
|
PRIME COAT & BLOTTER (MC-30)
|
GAL
|
109,674.000
|
$5.000
|
$5.200
|
$5.750
|
$6.500
|
$5.610
|
$6.000
|
$5.000
|
$6.500
|
|
|
EMULS ASPH (EROSN CONT)(CSS-1)
|
GAL
|
8,710.000
|
$8.000
|
$3.850
|
$5.000
|
$4.600
|
$5.000
|
$3.100
|
$4.500
|
$5.700
|
|
|
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
|
GAL
|
125,664.000
|
$4.900
|
$3.850
|
$5.000
|
$4.000
|
$4.500
|
$5.000
|
$4.500
|
$5.300
|
|
|
AGGR (TY-PD OR PL, GR-4)
|
CY
|
2,586.000
|
$220.000
|
$180.000
|
$190.000
|
$235.000
|
$150.000
|
$225.000
|
$180.000
|
$200.000
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
95,363.000
|
$135.000
|
$137.910
|
$145.000
|
$127.000
|
$148.000
|
$128.000
|
$132.000
|
$148.000
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
45,266.000
|
$142.000
|
$145.500
|
$152.000
|
$143.000
|
$157.000
|
$142.000
|
$155.000
|
$155.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
1,688.000
|
$2.000
|
$8.500
|
$12.000
|
$26.000
|
$6.000
|
$26.000
|
$5.160
|
$12.000
|
|
|
CONC PVMT (CRCP) (10")
|
SY
|
15,480.000
|
$120.000
|
$110.000
|
$110.000
|
$103.000
|
$110.000
|
$93.000
|
$112.480
|
$145.000
|
|
|
CONC PVMT (CRCP)(FAST TRK) (13")
|
SY
|
3,652.000
|
$220.000
|
$157.000
|
$145.000
|
$155.000
|
$130.000
|
$121.000
|
$166.410
|
$225.000
|
|
|
CUT & RESTORING PAV
|
SY
|
2,254.000
|
$250.000
|
$90.000
|
$100.000
|
$70.000
|
$250.000
|
$236.000
|
$105.520
|
$190.000
|
|
|
CEM STABIL BKFL
|
CY
|
2,467.000
|
$150.000
|
$195.000
|
$160.000
|
$210.000
|
$250.000
|
$300.000
|
$139.560
|
$250.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
749.000
|
$552.000
|
$190.000
|
$200.000
|
$200.000
|
$250.000
|
$200.000
|
$285.010
|
$250.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
3,891.000
|
$9.000
|
$12.200
|
$10.000
|
$7.000
|
$5.000
|
$3.000
|
$1.100
|
$12.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
7,314.000
|
$59.000
|
$45.000
|
$50.000
|
$25.000
|
$55.000
|
$58.000
|
$25.740
|
$56.000
|
|
|
TEMPORARY SPL SHORING (COFFERDAM)
|
SF
|
2,400.000
|
$29.930
|
$29.000
|
$30.000
|
$50.000
|
$55.000
|
$10.000
|
$114.320
|
$60.000
|
|
|
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
|
EA
|
3.000
|
$22,000.000
|
$30,250.000
|
$30,000.000
|
$31,000.000
|
$30,000.000
|
$43,000.000
|
$27,500.000
|
$38,000.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
310.000
|
$178.000
|
$85.000
|
$70.000
|
$143.000
|
$168.000
|
$230.000
|
$65.350
|
$200.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,280.000
|
$240.000
|
$265.000
|
$250.000
|
$262.000
|
$330.000
|
$355.000
|
$235.740
|
$390.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
1,265.000
|
$400.000
|
$361.400
|
$340.000
|
$395.000
|
$450.000
|
$370.000
|
$322.540
|
$420.000
|
|
|
DRILL SHAFT (60 IN)
|
LF
|
4,599.000
|
$675.000
|
$745.000
|
$705.000
|
$700.000
|
$650.000
|
$670.000
|
$654.360
|
$670.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
126.000
|
$300.000
|
$295.000
|
$290.000
|
$295.000
|
$268.000
|
$290.000
|
$268.000
|
$300.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
28.000
|
$650.000
|
$355.000
|
$345.000
|
$352.000
|
$320.000
|
$337.000
|
$320.000
|
$350.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (48 IN)
|
LF
|
44.000
|
$1,200.000
|
$895.000
|
$875.000
|
$900.000
|
$815.000
|
$860.000
|
$815.000
|
$860.000
|
|
|
CL C CONC (ABUT)
|
CY
|
305.800
|
$1,100.000
|
$1,015.000
|
$1,100.000
|
$980.000
|
$985.000
|
$885.000
|
$1,115.380
|
$1,600.000
|
|
|
CL C CONC (CAP)
|
CY
|
453.400
|
$1,400.000
|
$1,085.000
|
$1,100.000
|
$1,005.000
|
$1,200.000
|
$985.000
|
$1,261.130
|
$2,000.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
1,071.500
|
$1,575.000
|
$900.000
|
$1,075.000
|
$1,070.000
|
$1,100.000
|
$900.000
|
$1,453.580
|
$1,400.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
21.000
|
$500.000
|
$715.000
|
$800.000
|
$970.000
|
$1,500.000
|
$520.000
|
$624.330
|
$910.000
|
|
|
CL C CONC (MISC)
|
CY
|
6.000
|
$1,554.740
|
$1,500.000
|
$1,000.000
|
$2,220.000
|
$1,500.000
|
$1,400.000
|
$1,094.960
|
$1,300.000
|
|
|
CL E CONC (SEAL SLAB)(NON-REINF)
|
CY
|
294.000
|
$400.000
|
$515.000
|
$500.000
|
$405.000
|
$350.000
|
$320.000
|
$501.990
|
$650.000
|
|
|
REINF CONC SLAB
|
SF
|
133,830.000
|
$23.000
|
$25.000
|
$24.000
|
$26.000
|
$22.500
|
$20.000
|
$24.570
|
$34.000
|
|
|
APPROACH SLAB
|
CY
|
763.400
|
$755.000
|
$750.000
|
$800.000
|
$600.000
|
$750.000
|
$705.000
|
$628.500
|
$700.000
|
|
|
PRESTR CONC GIRDER (TX40)
|
LF
|
1,509.600
|
$200.000
|
$230.000
|
$206.000
|
$275.000
|
$256.000
|
$202.000
|
$194.410
|
$280.000
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
3,627.000
|
$223.000
|
$236.000
|
$230.000
|
$275.000
|
$256.000
|
$217.000
|
$205.140
|
$280.000
|
|
|
PRESTR CONC GIRDER (TX70)
|
LF
|
14,377.000
|
$250.000
|
$268.000
|
$280.000
|
$275.000
|
$256.000
|
$240.000
|
$237.860
|
$290.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
305.000
|
$500.000
|
$590.000
|
$600.000
|
$500.000
|
$700.000
|
$488.000
|
$516.180
|
$690.000
|
|
|
RIPRAP (CONC)(CL B)(5 IN)
|
CY
|
615.000
|
$580.000
|
$545.000
|
$600.000
|
$675.000
|
$600.000
|
$502.000
|
$435.100
|
$580.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
56.000
|
$580.000
|
$610.000
|
$600.000
|
$555.000
|
$550.000
|
$515.000
|
$778.530
|
$820.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
572.000
|
$160.000
|
$190.000
|
$195.000
|
$230.000
|
$180.000
|
$160.000
|
$274.040
|
$260.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
53.000
|
$200.000
|
$235.000
|
$195.000
|
$242.000
|
$180.000
|
$140.000
|
$342.920
|
$230.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(24 IN)
|
CY
|
208.000
|
$230.000
|
$190.000
|
$195.000
|
$233.000
|
$180.000
|
$160.000
|
$245.520
|
$260.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
5,160.000
|
$200.000
|
$165.000
|
$202.000
|
$233.000
|
$180.000
|
$160.000
|
$247.820
|
$190.000
|
|
|
STR STEEL (MISC NON-BRIDGE)
|
LB
|
1,228.000
|
$45.000
|
$33.000
|
$40.000
|
$33.000
|
$30.000
|
$18.000
|
$22.080
|
$27.000
|
|
|
RAIL (TY T222)
|
LF
|
2,790.000
|
$100.000
|
$133.000
|
$100.000
|
$103.000
|
$180.000
|
$90.000
|
$69.670
|
$95.000
|
|
|
RAIL (TY SSTR)
|
LF
|
115.000
|
$82.000
|
$125.000
|
$175.000
|
$150.000
|
$210.000
|
$130.000
|
$146.970
|
$200.000
|
|
|
RAIL (TY PR11)
|
LF
|
2,790.000
|
$135.000
|
$134.000
|
$120.000
|
$125.000
|
$180.000
|
$130.000
|
$109.360
|
$210.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
257.000
|
$200.000
|
$229.000
|
$200.000
|
$260.000
|
$250.000
|
$199.000
|
$194.640
|
$320.000
|
|
|
SEALED EXPANSION JOINT (5 IN) (SEJ - M)
|
LF
|
516.000
|
$175.000
|
$229.000
|
$200.000
|
$260.000
|
$250.000
|
$199.000
|
$206.880
|
$320.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)
|
LF
|
353.000
|
$320.000
|
$315.000
|
$300.000
|
$234.000
|
$310.000
|
$330.000
|
$260.050
|
$310.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)
|
LF
|
814.000
|
$440.000
|
$365.650
|
$355.000
|
$286.000
|
$350.000
|
$350.000
|
$302.690
|
$350.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)
|
LF
|
208.000
|
$460.000
|
$430.000
|
$425.000
|
$348.000
|
$450.000
|
$390.000
|
$364.460
|
$410.000
|
|
|
CONC BOX CULV (5 FT X 3 FT)
|
LF
|
176.000
|
$468.000
|
$465.000
|
$465.000
|
$388.000
|
$470.000
|
$450.000
|
$406.820
|
$420.000
|
|
|
CONC BOX CULV (5 FT X 4 FT)
|
LF
|
212.000
|
$525.000
|
$495.000
|
$510.000
|
$420.000
|
$500.000
|
$450.000
|
$427.060
|
$460.000
|
|
|
CONC BOX CULV (5 FT X 5 FT)
|
LF
|
180.000
|
$550.000
|
$525.000
|
$550.000
|
$458.000
|
$520.000
|
$470.000
|
$467.550
|
$470.000
|
|
|
CONC BOX CULV (6 FT X 4 FT)
|
LF
|
342.000
|
$600.000
|
$645.000
|
$700.000
|
$584.000
|
$650.000
|
$540.000
|
$615.510
|
$630.000
|
|
|
CONC BOX CULV (7 FT X 5 FT)
|
LF
|
266.000
|
$750.000
|
$765.000
|
$800.000
|
$667.000
|
$676.000
|
$700.000
|
$690.500
|
$710.000
|
|
|
CONC BOX CULV (8 FT X 5 FT)
|
LF
|
990.000
|
$850.000
|
$850.000
|
$900.000
|
$754.000
|
$800.000
|
$740.000
|
$811.130
|
$780.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
3,747.000
|
$55.000
|
$58.000
|
$55.000
|
$50.000
|
$46.000
|
$55.000
|
$85.760
|
$86.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
3,189.000
|
$75.000
|
$77.000
|
$75.000
|
$70.000
|
$60.000
|
$105.000
|
$92.690
|
$100.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
342.000
|
$98.000
|
$100.000
|
$110.000
|
$96.000
|
$87.000
|
$140.000
|
$121.040
|
$130.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
1,079.000
|
$145.000
|
$145.000
|
$140.000
|
$130.000
|
$110.000
|
$170.000
|
$146.050
|
$155.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
240.000
|
$200.000
|
$180.000
|
$195.000
|
$164.000
|
$206.000
|
$220.000
|
$173.520
|
$195.000
|
|
|
MANH (COMPL)(PRM)(48IN)
|
EA
|
1.000
|
$6,000.000
|
$6,100.000
|
$7,000.000
|
$4,870.000
|
$5,000.000
|
$4,600.000
|
$4,611.370
|
$7,000.000
|
|
|
INLET (COMPL)(PSL)(RC)(4FTX4FT)
|
EA
|
1.000
|
$7,750.000
|
$7,575.000
|
$9,000.000
|
$6,364.000
|
$7,000.000
|
$6,800.000
|
$5,438.500
|
$8,500.000
|
|
|
INLET (COMPL)(PSL)(SH)(3FTX3FT-3FTX3FT)
|
EA
|
1.000
|
$9,000.000
|
$7,900.000
|
$9,000.000
|
$6,200.000
|
$7,000.000
|
$6,200.000
|
$5,971.410
|
$8,500.000
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
11.000
|
$8,000.000
|
$8,500.000
|
$9,500.000
|
$6,500.000
|
$7,000.000
|
$7,600.000
|
$5,696.000
|
$9,000.000
|
|
|
INLET (COMPL)(CCO)(3FT)(BOTH)
|
EA
|
1.000
|
$6,771.000
|
$7,100.000
|
$9,500.000
|
$9,700.000
|
$10,000.000
|
$6,700.000
|
$5,473.420
|
$12,000.000
|
|
|
INLET(COMPL)(PSL)(FG)(4'X4'-4'X4')(MOD)
|
EA
|
6.000
|
$9,500.000
|
$9,200.000
|
$10,000.000
|
$7,000.000
|
$8,000.000
|
$7,700.000
|
$5,213.080
|
$9,500.000
|
|
|
HEADWALL (CH - FW - 30) (DIA= 42 IN)
|
EA
|
2.000
|
$9,600.000
|
$10,500.000
|
$8,500.000
|
$12,235.000
|
$12,000.000
|
$9,200.000
|
$14,689.130
|
$17,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
3.000
|
$14,500.000
|
$10,850.000
|
$5,000.000
|
$12,620.000
|
$9,000.000
|
$11,000.000
|
$13,667.800
|
$20,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 54 IN)
|
EA
|
1.000
|
$15,000.000
|
$19,000.000
|
$13,500.000
|
$25,000.000
|
$15,000.000
|
$20,000.000
|
$29,532.970
|
$34,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 72 IN)
|
EA
|
1.000
|
$23,500.000
|
$20,250.000
|
$10,000.000
|
$32,625.000
|
$18,000.000
|
$20,000.000
|
$39,758.680
|
$42,000.000
|
|
|
WINGWALL (FW - 0) (HW=4 FT)
|
EA
|
6.000
|
$18,500.000
|
$15,200.000
|
$7,500.000
|
$9,425.000
|
$12,000.000
|
$17,000.000
|
$9,383.920
|
$21,000.000
|
|
|
WINGWALL (FW - 0) (HW=5 FT)
|
EA
|
2.000
|
$25,250.000
|
$19,500.000
|
$10,500.000
|
$12,915.000
|
$15,000.000
|
$28,000.000
|
$14,311.700
|
$21,000.000
|
|
|
WINGWALL (FW - 0) (HW=6 FT)
|
EA
|
3.000
|
$24,000.000
|
$18,800.000
|
$14,500.000
|
$16,320.000
|
$18,000.000
|
$23,000.000
|
$15,178.770
|
$28,000.000
|
|
|
WINGWALL (FW - S) (HW=4 FT)
|
EA
|
3.000
|
$12,000.000
|
$16,000.000
|
$9,000.000
|
$12,930.000
|
$12,000.000
|
$22,000.000
|
$13,011.110
|
$21,000.000
|
|
|
WINGWALL (FW - S) (HW=5 FT)
|
EA
|
4.000
|
$25,000.000
|
$15,850.000
|
$10,000.000
|
$12,950.000
|
$15,000.000
|
$27,000.000
|
$13,444.630
|
$21,000.000
|
|
|
WINGWALL (PW - 2) (HW=4 FT)
|
EA
|
1.000
|
$15,000.000
|
$10,500.000
|
$6,000.000
|
$11,565.000
|
$12,000.000
|
$22,000.000
|
$14,197.480
|
$14,000.000
|
|
|
WINGWALL (PW - 2) (HW=8 FT)
|
EA
|
1.000
|
$33,600.000
|
$31,400.000
|
$30,000.000
|
$34,700.000
|
$24,000.000
|
$47,000.000
|
$39,672.800
|
$58,000.000
|
|
|
WINGWALL (SW - 0) (HW=6 FT)
|
EA
|
2.000
|
$15,150.000
|
$31,300.000
|
$17,000.000
|
$19,140.000
|
$18,000.000
|
$32,000.000
|
$19,621.260
|
$35,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
5.000
|
$712.000
|
$1,100.000
|
$715.000
|
$960.000
|
$578.000
|
$2,100.000
|
$1,398.130
|
$1,200.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (C)
|
EA
|
2.000
|
$1,325.000
|
$1,350.000
|
$860.000
|
$1,215.000
|
$686.000
|
$2,300.000
|
$1,544.160
|
$1,300.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
162.000
|
$2,200.000
|
$1,115.000
|
$860.000
|
$1,025.000
|
$686.000
|
$2,300.000
|
$1,514.860
|
$1,300.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
16.000
|
$1,205.000
|
$1,400.000
|
$1,150.000
|
$1,340.000
|
$938.000
|
$2,300.000
|
$2,245.090
|
$1,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
1.000
|
$2,179.280
|
$1,800.000
|
$1,300.000
|
$1,645.000
|
$1,300.000
|
$2,500.000
|
$2,409.790
|
$1,600.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
32.000
|
$1,818.060
|
$1,550.000
|
$1,300.000
|
$1,465.000
|
$1,300.000
|
$2,500.000
|
$2,009.400
|
$1,600.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$2,100.000
|
$2,100.000
|
$2,100.000
|
$1,820.000
|
$2,053.000
|
$2,700.000
|
$2,739.180
|
$2,200.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
11.000
|
$4,500.000
|
$3,200.000
|
$3,600.000
|
$2,900.000
|
$3,500.000
|
$3,700.000
|
$3,710.870
|
$3,600.000
|
|
|
REMOV STR (INLET)
|
EA
|
2.000
|
$1,300.000
|
$800.000
|
$600.000
|
$642.000
|
$1,000.000
|
$1,400.000
|
$797.900
|
$1,800.000
|
|
|
REMOV STR (SET)
|
EA
|
1.000
|
$850.000
|
$800.000
|
$300.000
|
$642.000
|
$500.000
|
$900.000
|
$724.550
|
$1,200.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,508.000
|
$51.040
|
$16.000
|
$20.000
|
$22.000
|
$50.000
|
$27.000
|
$12.310
|
$36.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
1,297.000
|
$200.000
|
$30.000
|
$40.000
|
$43.000
|
$100.000
|
$220.000
|
$49.790
|
$90.000
|
|
|
REMOV STR (BRIDGE 1000 FT OR GREATER)
|
EA
|
1.000
|
$1,000,000.000
|
$110,000.000
|
$200,000.000
|
$400,000.000
|
$150,000.000
|
$340,000.000
|
$365,341.880
|
$750,000.000
|
|
|
REMOVE STR (DRIVEWAY CULVERT)
|
EA
|
96.000
|
$600.000
|
$525.000
|
$350.000
|
$500.000
|
$500.000
|
$710.000
|
$1,015.770
|
$1,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$7,468,904.000
|
$7,000,000.000
|
$5,700,000.000
|
$9,000,000.000
|
$10,100,000.000
|
$9,900,000.000
|
$10,500,000.000
|
$8,500,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
41.000
|
$7,000.000
|
$5,500.000
|
$6,000.000
|
$4,000.000
|
$5,000.000
|
$15,000.000
|
$10,912.730
|
$29,850.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
300.000
|
$100.000
|
$115.000
|
$125.000
|
$135.000
|
$100.000
|
$120.000
|
$71.840
|
$170.000
|
|
|
TMA (STATIONARY)
|
DAY
|
2,030.000
|
$195.000
|
$130.000
|
$25.000
|
$200.000
|
$25.000
|
$245.000
|
$132.970
|
$100.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
220.000
|
$237.000
|
$200.000
|
$200.000
|
$200.000
|
$500.000
|
$730.000
|
$665.870
|
$50.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
4,270.000
|
$45.000
|
$40.000
|
$39.000
|
$29.000
|
$36.000
|
$30.000
|
$36.000
|
$37.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
480.000
|
$62.250
|
$50.000
|
$50.000
|
$30.000
|
$45.000
|
$32.000
|
$45.000
|
$47.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
4,750.000
|
$13.000
|
$8.250
|
$8.000
|
$11.000
|
$7.500
|
$11.000
|
$7.500
|
$8.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
4,008.000
|
$48.000
|
$44.000
|
$20.000
|
$32.000
|
$15.000
|
$30.000
|
$40.000
|
$40.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
4,008.000
|
$11.000
|
$5.500
|
$5.500
|
$11.000
|
$5.000
|
$11.000
|
$5.000
|
$5.000
|
|
|
EXCAV (EROSN & SEDMT CONT, IN VEH)
|
CY
|
5,120.000
|
$37.500
|
$19.700
|
$12.000
|
$19.750
|
$20.000
|
$12.000
|
$20.000
|
$19.000
|
|
|
EMBANK (EROSN & SEDMT CONT, IN VEH)
|
CY
|
5,120.000
|
$50.000
|
$22.250
|
$15.000
|
$19.750
|
$20.000
|
$12.000
|
$20.000
|
$20.000
|
|
|
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
|
CY
|
3,000.000
|
$43.180
|
$20.000
|
$12.000
|
$19.500
|
$20.000
|
$12.000
|
$25.890
|
$18.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
300.000
|
$55.880
|
$50.000
|
$85.000
|
$170.000
|
$100.000
|
$193.000
|
$58.310
|
$120.000
|
|
|
BULLDOZER WORK (EROSION & SEDMT CONT)
|
HR
|
200.000
|
$100.000
|
$95.000
|
$100.000
|
$92.000
|
$100.000
|
$138.000
|
$162.460
|
$190.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
6,744.000
|
$3.500
|
$4.300
|
$4.250
|
$4.200
|
$4.000
|
$4.000
|
$3.890
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
6,744.000
|
$1.200
|
$0.500
|
$0.300
|
$1.000
|
$0.250
|
$0.650
|
$0.250
|
$0.250
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
180.000
|
$1.250
|
$5.000
|
$5.000
|
$4.400
|
$5.000
|
$5.000
|
$4.500
|
$5.500
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
180.000
|
$1.600
|
$1.000
|
$0.700
|
$1.400
|
$1.000
|
$1.300
|
$0.650
|
$1.000
|
|
|
TRACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
300.000
|
$98.000
|
$120.000
|
$100.000
|
$170.000
|
$100.000
|
$216.000
|
$146.510
|
$125.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
51,810.000
|
$137.000
|
$115.000
|
$130.000
|
$123.000
|
$136.000
|
$129.000
|
$112.240
|
$130.000
|
|
|
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
|
LF
|
2,290.000
|
$49.000
|
$11.000
|
$30.000
|
$12.500
|
$25.000
|
$10.000
|
$21.240
|
$60.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
5,720.000
|
$9.500
|
$17.000
|
$8.000
|
$5.500
|
$10.000
|
$9.000
|
$8.190
|
$25.000
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
2,290.000
|
$14.000
|
$10.000
|
$18.000
|
$6.250
|
$25.000
|
$9.000
|
$16.450
|
$50.000
|
|
|
CONC CURB (TY II)
|
LF
|
1,108.000
|
$46.500
|
$30.000
|
$9.000
|
$17.000
|
$35.000
|
$12.000
|
$22.190
|
$20.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
2,611.000
|
$130.000
|
$130.000
|
$105.000
|
$144.000
|
$110.000
|
$128.000
|
$133.530
|
$180.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
13,014.000
|
$80.000
|
$35.000
|
$38.000
|
$32.860
|
$65.000
|
$88.000
|
$72.190
|
$35.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
1,574.000
|
$75.000
|
$75.000
|
$72.000
|
$66.000
|
$75.000
|
$48.000
|
$55.450
|
$110.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
3.000
|
$4,200.000
|
$2,300.000
|
$2,500.000
|
$5,325.000
|
$1,800.000
|
$2,750.000
|
$2,587.510
|
$2,500.000
|
|
|
CURB RAMPS (TY 22)
|
EA
|
2.000
|
$3,000.000
|
$3,100.000
|
$4,000.000
|
$5,565.000
|
$3,500.000
|
$4,100.000
|
$3,143.400
|
$3,000.000
|
|
|
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
|
LF
|
124,850.000
|
$0.210
|
$0.270
|
$0.270
|
$0.150
|
$0.250
|
$0.200
|
$0.060
|
$0.250
|
|
|
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
|
LF
|
7,800.000
|
$0.190
|
$0.270
|
$0.270
|
$1.000
|
$0.250
|
$0.200
|
$0.310
|
$0.250
|
|
|
MILL RUMBLE STRIPS (CONC) (SHLDR)
|
LF
|
3,500.000
|
$0.900
|
$1.100
|
$1.100
|
$1.000
|
$1.000
|
$1.200
|
$0.750
|
$1.000
|
|
|
MILL RUMBLE STRIPS (CONC) (CENTERLINE)
|
LF
|
4,000.000
|
$0.960
|
$1.100
|
$1.100
|
$0.200
|
$1.000
|
$1.200
|
$0.660
|
$1.000
|
|
|
CONC DIRECTIONAL ISLAND
|
SY
|
479.000
|
$180.000
|
$70.000
|
$125.000
|
$112.000
|
$180.000
|
$76.000
|
$128.040
|
$195.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,288.000
|
$30.500
|
$30.250
|
$28.000
|
$29.000
|
$30.000
|
$31.000
|
$26.000
|
$27.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
9.000
|
$2,100.000
|
$2,365.000
|
$2,300.000
|
$2,475.000
|
$2,200.000
|
$2,250.000
|
$2,100.000
|
$2,200.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
683.000
|
$2.600
|
$2.200
|
$2.200
|
$2.200
|
$3.000
|
$4.000
|
$2.000
|
$2.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
14.000
|
$3,200.000
|
$3,410.000
|
$3,250.000
|
$3,300.000
|
$2,950.000
|
$2,960.000
|
$3,000.000
|
$3,200.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$220.000
|
$220.000
|
$220.000
|
$220.000
|
$250.000
|
$260.000
|
$200.000
|
$220.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
27.000
|
$1,100.000
|
$2,200.000
|
$1,650.000
|
$1,650.000
|
$1,000.000
|
$1,200.000
|
$1,500.000
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
7.000
|
$900.000
|
$880.000
|
$900.000
|
$880.000
|
$1,000.000
|
$900.000
|
$800.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
1.000
|
$28,000.000
|
$27,500.000
|
$28,000.000
|
$28,500.000
|
$30,000.000
|
$26,000.000
|
$25,900.000
|
$27,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
7.000
|
$7,600.000
|
$9,240.000
|
$9,100.000
|
$9,250.000
|
$7,500.000
|
$7,700.000
|
$8,400.000
|
$9,300.000
|
|
|
PIPE UNDERDRAINS (TY 8) (6")
|
LF
|
53,870.000
|
$33.500
|
$31.500
|
$28.000
|
$34.000
|
$45.000
|
$38.000
|
$52.170
|
$40.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
3.000
|
$605.000
|
$820.000
|
$830.000
|
$550.000
|
$500.000
|
$310.000
|
$775.000
|
$530.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
50.000
|
$330.000
|
$365.000
|
$350.000
|
$275.000
|
$300.000
|
$260.000
|
$325.000
|
$260.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
13.000
|
$365.000
|
$415.000
|
$425.000
|
$300.000
|
$350.000
|
$290.000
|
$395.000
|
$290.000
|
|
|
IN RD IL (TY SA) 20T-8 (150W EQ) LED
|
EA
|
5.000
|
$5,300.000
|
$3,540.000
|
$3,450.000
|
$3,540.000
|
$3,215.000
|
$3,400.000
|
$3,215.000
|
$3,400.000
|
|
|
IN RD IL(TY SA)15T-4(150W EQ)LED
|
EA
|
16.000
|
$5,000.000
|
$3,550.000
|
$3,450.000
|
$3,550.000
|
$3,225.000
|
$3,400.000
|
$3,225.000
|
$3,400.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
1,555.000
|
$33.660
|
$9.700
|
$9.400
|
$9.650
|
$9.000
|
$10.000
|
$8.750
|
$10.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
690.000
|
$42.000
|
$21.200
|
$20.600
|
$21.200
|
$20.000
|
$21.000
|
$19.250
|
$20.000
|
|
|
CONDT (PVC) (SCH 80) (3")
|
LF
|
150.000
|
$41.630
|
$19.000
|
$18.250
|
$18.700
|
$17.000
|
$18.000
|
$17.000
|
$18.000
|
|
|
CONDT (PVC) (SCH 80) (3") (BORE)
|
LF
|
135.000
|
$46.000
|
$27.000
|
$26.250
|
$26.950
|
$25.000
|
$26.000
|
$24.500
|
$26.000
|
|
|
CONDT (PVC) (SCH 80) (4")
|
LF
|
65.000
|
$31.000
|
$23.000
|
$22.500
|
$23.000
|
$21.000
|
$23.000
|
$21.000
|
$22.000
|
|
|
CONDT (PVC) (SCH 80) (4") (BORE)
|
LF
|
295.000
|
$35.000
|
$34.000
|
$33.000
|
$34.000
|
$31.000
|
$33.000
|
$31.000
|
$33.000
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
2,280.000
|
$2.300
|
$2.500
|
$2.450
|
$2.500
|
$2.000
|
$2.400
|
$2.250
|
$2.400
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
5,350.000
|
$2.500
|
$2.750
|
$2.700
|
$2.750
|
$2.500
|
$2.700
|
$2.500
|
$2.600
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
605.000
|
$3.450
|
$3.300
|
$3.250
|
$3.300
|
$3.000
|
$3.200
|
$3.000
|
$3.200
|
|
|
ELEC CONDR (NO.4) BARE
|
LF
|
30.000
|
$4.500
|
$4.200
|
$4.050
|
$4.150
|
$3.750
|
$4.000
|
$3.750
|
$4.000
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
55.000
|
$5.200
|
$4.750
|
$4.550
|
$4.700
|
$4.250
|
$4.500
|
$4.250
|
$4.500
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
820.000
|
$6.000
|
$3.600
|
$3.500
|
$3.600
|
$3.250
|
$3.500
|
$3.250
|
$3.400
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
3.000
|
$1,900.000
|
$1,300.000
|
$1,260.000
|
$1,300.000
|
$1,175.000
|
$1,250.000
|
$1,175.000
|
$1,250.000
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
5.000
|
$2,900.000
|
$1,540.000
|
$1,500.000
|
$1,540.000
|
$1,400.000
|
$1,480.000
|
$1,400.000
|
$1,500.000
|
|
|
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
|
EA
|
2.000
|
$9,090.000
|
$7,850.000
|
$7,650.000
|
$7,850.000
|
$7,125.000
|
$7,500.000
|
$7,125.000
|
$7,500.000
|
|
|
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
|
EA
|
1.000
|
$8,000.000
|
$7,600.000
|
$7,400.000
|
$7,590.000
|
$6,900.000
|
$7,300.000
|
$6,900.000
|
$7,300.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
57.000
|
$760.000
|
$685.000
|
$680.000
|
$720.000
|
$738.000
|
$650.000
|
$635.000
|
$690.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
135.000
|
$750.000
|
$885.000
|
$800.000
|
$825.000
|
$893.000
|
$760.000
|
$745.000
|
$790.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$1,220.000
|
$1,050.000
|
$1,100.000
|
$910.000
|
$927.000
|
$1,050.000
|
$1,020.000
|
$870.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
4.000
|
$800.000
|
$755.000
|
$885.000
|
$770.000
|
$797.000
|
$840.000
|
$825.000
|
$740.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
9.000
|
$1,000.000
|
$970.000
|
$955.000
|
$900.000
|
$897.000
|
$900.000
|
$890.000
|
$860.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
4.000
|
$1,200.000
|
$1,270.000
|
$1,350.000
|
$1,210.000
|
$997.000
|
$1,280.000
|
$1,255.000
|
$1,200.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
1.000
|
$760.000
|
$585.000
|
$660.000
|
$275.000
|
$475.000
|
$640.000
|
$615.000
|
$260.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
123.000
|
$120.000
|
$95.000
|
$100.000
|
$110.000
|
$50.000
|
$90.000
|
$89.000
|
$110.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
|
EA
|
33.000
|
$21.000
|
$22.000
|
$32.000
|
$16.500
|
$20.000
|
$21.000
|
$15.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
12.000
|
$31.000
|
$28.000
|
$36.000
|
$27.500
|
$25.000
|
$26.000
|
$25.000
|
$35.000
|
|
|
INSTL DEL ASSM (D-DY)SZ 1(YFLX)GND
|
EA
|
28.000
|
$67.000
|
$80.000
|
$65.000
|
$82.500
|
$45.000
|
$46.000
|
$55.000
|
$80.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
19.000
|
$90.000
|
$86.000
|
$60.000
|
$77.000
|
$60.000
|
$61.000
|
$55.000
|
$80.000
|
|
|
INSTL OM SM RD SIGN (1-OM-CON)Y
|
EA
|
4.000
|
$95.000
|
$180.000
|
$27.000
|
$55.000
|
$63.000
|
$121.000
|
$25.000
|
$53.000
|
|
|
INSTL OM SM RD SIGN (1-OM-CON)R
|
EA
|
51.000
|
$84.000
|
$180.000
|
$27.000
|
$56.000
|
$63.000
|
$181.000
|
$25.000
|
$54.000
|
|
|
INSTL OM SM RD SIGN (1-OM-PW)Y
|
EA
|
28.000
|
$49.000
|
$45.000
|
$27.000
|
$13.200
|
$63.000
|
$26.000
|
$25.000
|
$13.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
4,407.000
|
$0.550
|
$0.550
|
$0.550
|
$0.550
|
$0.350
|
$0.520
|
$0.500
|
$0.520
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
120,302.000
|
$0.550
|
$0.280
|
$0.270
|
$0.280
|
$0.600
|
$0.260
|
$0.250
|
$0.260
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
975.000
|
$1.080
|
$1.100
|
$1.100
|
$1.100
|
$0.350
|
$1.050
|
$1.000
|
$1.050
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
291.000
|
$4.860
|
$4.400
|
$4.300
|
$4.400
|
$5.000
|
$4.100
|
$4.000
|
$4.200
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ARROW)
|
EA
|
4.000
|
$175.000
|
$110.000
|
$110.000
|
$110.000
|
$100.000
|
$101.000
|
$100.000
|
$105.000
|
|
|
WK ZN PAV MRK NON-REMOV(W)(WORD)
|
EA
|
4.000
|
$95.000
|
$110.000
|
$110.000
|
$110.000
|
$100.000
|
$101.000
|
$100.000
|
$105.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(DOT)
|
LF
|
42.000
|
$2.000
|
$2.200
|
$2.150
|
$2.200
|
$0.140
|
$2.100
|
$2.000
|
$2.100
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
117,824.000
|
$0.560
|
$0.280
|
$0.270
|
$0.280
|
$0.350
|
$0.260
|
$0.250
|
$0.260
|
|
|
WK ZN PAV MRK REMOV (REFL) TY I-C
|
EA
|
663.000
|
$6.000
|
$5.000
|
$4.850
|
$4.950
|
$4.000
|
$4.600
|
$4.500
|
$4.700
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
377.000
|
$6.000
|
$5.000
|
$4.850
|
$4.950
|
$4.000
|
$4.600
|
$4.500
|
$4.700
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
EA
|
1,443.000
|
$4.150
|
$4.200
|
$4.000
|
$4.150
|
$2.000
|
$4.000
|
$3.750
|
$4.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
EA
|
1,077.000
|
$4.150
|
$4.200
|
$4.000
|
$4.150
|
$2.000
|
$4.000
|
$3.750
|
$4.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
10,744.000
|
$1.300
|
$1.400
|
$1.350
|
$2.000
|
$0.900
|
$1.300
|
$1.250
|
$1.300
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
34,359.000
|
$1.300
|
$1.400
|
$1.350
|
$2.000
|
$0.900
|
$1.300
|
$1.250
|
$1.300
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
8,772.000
|
$2.300
|
$1.750
|
$1.500
|
$2.200
|
$2.000
|
$1.050
|
$1.500
|
$0.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,596.000
|
$2.300
|
$1.750
|
$1.500
|
$2.200
|
$2.000
|
$1.050
|
$1.500
|
$0.550
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
1,619.000
|
$1.250
|
$1.300
|
$1.300
|
$1.320
|
$1.250
|
$1.250
|
$1.200
|
$1.250
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
30,658.000
|
$0.750
|
$1.300
|
$1.300
|
$1.320
|
$1.000
|
$1.250
|
$1.200
|
$1.250
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
371.000
|
$2.370
|
$4.400
|
$4.300
|
$4.400
|
$3.250
|
$4.100
|
$4.000
|
$4.200
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
741.000
|
$5.000
|
$7.000
|
$6.700
|
$6.900
|
$6.500
|
$6.300
|
$6.250
|
$6.600
|
|
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
|
LF
|
49.000
|
$4.000
|
$4.500
|
$4.300
|
$4.400
|
$3.250
|
$4.100
|
$4.000
|
$4.200
|
|
|
PAVEMENT SLER 6"
|
LF
|
17,582.000
|
$0.100
|
$0.350
|
$0.330
|
$0.350
|
$0.300
|
$0.320
|
$0.300
|
$0.320
|
|
|
PAVEMENT SLER 8"
|
LF
|
2,211.000
|
$0.110
|
$0.600
|
$0.540
|
$0.550
|
$0.400
|
$0.520
|
$0.500
|
$0.550
|
|
|
PAVEMENT SLER 12"
|
LF
|
199.000
|
$0.750
|
$2.200
|
$2.150
|
$2.200
|
$1.500
|
$2.100
|
$2.000
|
$2.100
|
|
|
PAVEMENT SLER 24"
|
LF
|
372.000
|
$2.000
|
$3.300
|
$3.220
|
$3.300
|
$3.000
|
$3.100
|
$3.000
|
$3.100
|
|
|
PAVEMENT SLER (ARROW)
|
EA
|
12.000
|
$40.000
|
$110.000
|
$110.000
|
$110.000
|
$50.000
|
$101.000
|
$100.000
|
$110.000
|
|
|
PAVEMENT SLER (WORD)
|
EA
|
7.000
|
$55.000
|
$165.000
|
$165.000
|
$165.000
|
$50.000
|
$152.000
|
$150.000
|
$160.000
|
|
|
PAVEMENT SLER (YLD TRI)
|
EA
|
8.000
|
$16.000
|
$55.000
|
$55.000
|
$55.000
|
$15.000
|
$52.000
|
$50.000
|
$53.000
|
|
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
|
LF
|
18,261.000
|
$0.470
|
$0.830
|
$0.800
|
$1.000
|
$0.650
|
$0.800
|
$0.750
|
$0.800
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
83,148.000
|
$0.460
|
$0.830
|
$0.800
|
$0.850
|
$0.610
|
$0.800
|
$0.750
|
$0.800
|
|
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
|
LF
|
3,078.000
|
$0.440
|
$0.830
|
$0.800
|
$0.850
|
$0.650
|
$0.800
|
$0.750
|
$0.800
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
87,164.000
|
$0.470
|
$0.830
|
$0.800
|
$0.850
|
$0.610
|
$0.800
|
$0.750
|
$0.800
|
|
PREFAB PM TY C (W)(ARROW)
|
EA
|
85.000
|
$225.000
|
$230.000
|
$225.000
|
$230.000
|
$275.000
|
$212.000
|
$210.000
|
$220.000
|
|
PREFAB PM TY C (W)(LN REDUCT ARROW)
|
EA
|
3.000
|
$373.700
|
$315.000
|
$305.000
|
$315.000
|
$400.000
|
$290.000
|
$285.000
|
$300.000
|
|
PREFAB PM TY C (W)(WORD)
|
EA
|
71.000
|
$260.000
|
$260.000
|
$255.000
|
$260.000
|
$325.000
|
$240.000
|
$235.000
|
$250.000
|
|
PREFAB PM TY C (W)(36")(YLD TRI)
|
EA
|
34.000
|
$41.500
|
$66.000
|
$65.000
|
$66.000
|
$35.000
|
$62.000
|
$60.000
|
$65.000
|
|
PREFAB PM TY C (Y)(MED NOSE)
|
EA
|
2.000
|
$292.600
|
$550.000
|
$535.000
|
$550.000
|
$350.000
|
$505.000
|
$500.000
|
$530.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
540.000
|
$4.100
|
$5.500
|
$5.350
|
$5.500
|
$4.500
|
$5.100
|
$5.000
|
$5.250
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
845.000
|
$3.960
|
$5.500
|
$5.350
|
$5.500
|
$4.500
|
$5.100
|
$5.000
|
$5.250
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
1,926.000
|
$4.150
|
$5.500
|
$5.350
|
$5.500
|
$4.500
|
$5.100
|
$5.000
|
$5.250
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
92,888.000
|
$0.850
|
$0.530
|
$0.510
|
$0.550
|
$0.620
|
$0.500
|
$0.480
|
$0.500
|
|
|
ELIM EXT PM & MRKS (8")
|
LF
|
680.000
|
$0.600
|
$1.100
|
$1.100
|
$1.100
|
$1.000
|
$1.050
|
$1.000
|
$1.100
|
|
|
ELIM EXT PM & MRKS (24")
|
LF
|
177.000
|
$6.000
|
$2.750
|
$2.700
|
$2.750
|
$12.000
|
$2.550
|
$2.500
|
$2.700
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
17,582.000
|
$0.100
|
$0.110
|
$0.110
|
$0.110
|
$0.300
|
$0.110
|
$0.100
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
2,211.000
|
$0.100
|
$0.220
|
$0.220
|
$0.220
|
$0.400
|
$0.210
|
$0.200
|
$0.200
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
199.000
|
$0.340
|
$1.100
|
$1.100
|
$1.100
|
$2.000
|
$1.050
|
$1.000
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
372.000
|
$1.330
|
$1.100
|
$1.100
|
$1.100
|
$4.000
|
$1.050
|
$1.000
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
12.000
|
$25.000
|
$55.000
|
$54.000
|
$55.000
|
$50.000
|
$51.000
|
$50.000
|
$52.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
7.000
|
$25.000
|
$55.000
|
$54.000
|
$55.000
|
$50.000
|
$51.000
|
$50.000
|
$52.000
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
8.000
|
$25.000
|
$55.000
|
$54.000
|
$55.000
|
$10.000
|
$51.000
|
$50.000
|
$52.000
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
1.000
|
$63,750.000
|
$31,075.000
|
$30,250.000
|
$31,100.000
|
$28,250.000
|
$30,000.000
|
$28,250.000
|
$30,000.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
1.000
|
$7,500.000
|
$6,410.000
|
$6,250.000
|
$6,400.000
|
$5,825.000
|
$6,200.000
|
$5,825.000
|
$6,200.000
|
|
|
TEMP TRAF SIGNALS
|
EA
|
1.000
|
$128,012.000
|
$126,500.000
|
$123,500.000
|
$126,500.000
|
$115,000.000
|
$121,000.000
|
$115,000.000
|
$122,000.000
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
8.000
|
$450.000
|
$300.000
|
$290.000
|
$300.000
|
$270.000
|
$290.000
|
$269.670
|
$300.000
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
2.000
|
$450.000
|
$305.000
|
$295.000
|
$300.000
|
$275.000
|
$290.000
|
$275.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
8.000
|
$450.000
|
$295.000
|
$290.000
|
$300.000
|
$269.000
|
$290.000
|
$269.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
4.000
|
$450.000
|
$305.000
|
$295.000
|
$300.000
|
$275.000
|
$290.000
|
$275.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
8.000
|
$450.000
|
$275.000
|
$290.000
|
$300.000
|
$269.000
|
$290.000
|
$269.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
2.000
|
$450.000
|
$300.000
|
$295.000
|
$300.000
|
$275.000
|
$290.000
|
$275.000
|
$300.000
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
8.000
|
$475.000
|
$595.000
|
$580.000
|
$600.000
|
$540.000
|
$570.000
|
$540.000
|
$600.000
|
|
|
BACKPLATE W/REFL BRDR(4 SEC)
|
EA
|
2.000
|
$275.000
|
$255.000
|
$250.000
|
$255.000
|
$232.000
|
$245.000
|
$232.000
|
$250.000
|
|
|
BACKPLATE W/REFL BRDR(3 SEC)
|
EA
|
8.000
|
$330.000
|
$187.000
|
$185.000
|
$190.000
|
$190.000
|
$180.000
|
$170.000
|
$180.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
|
LF
|
1,555.000
|
$2.250
|
$2.200
|
$2.150
|
$2.200
|
$2.000
|
$2.200
|
$2.000
|
$2.200
|
|
|
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
|
LF
|
1,595.000
|
$2.850
|
$3.600
|
$3.500
|
$3.600
|
$3.250
|
$3.500
|
$3.250
|
$3.500
|
|
|
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
|
LF
|
1,520.000
|
$7.000
|
$4.500
|
$4.300
|
$4.400
|
$4.000
|
$4.300
|
$4.000
|
$4.500
|
|
|
INS TRF SIG PL AM(S)1 ARM(36')LUM
|
EA
|
2.000
|
$31,000.000
|
$14,800.000
|
$14,400.000
|
$14,795.000
|
$13,450.000
|
$14,500.000
|
$13,450.000
|
$14,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(55')
|
EA
|
1.000
|
$31,350.000
|
$36,300.000
|
$35,300.000
|
$36,300.000
|
$32,970.000
|
$35,000.000
|
$32,970.000
|
$35,000.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(55')LUM
|
EA
|
1.000
|
$38,500.000
|
$38,800.000
|
$37,750.000
|
$38,775.000
|
$35,250.000
|
$38,000.000
|
$35,250.000
|
$38,000.000
|
|
|
PED POLE ASSEMBLY
|
EA
|
6.000
|
$6,600.000
|
$3,165.000
|
$3,080.000
|
$3,200.000
|
$2,875.000
|
$3,100.000
|
$2,875.000
|
$3,000.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
8.000
|
$1,025.000
|
$820.000
|
$800.000
|
$820.000
|
$745.000
|
$790.000
|
$745.000
|
$800.000
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
1.000
|
$4,500.000
|
$3,100.000
|
$3,000.000
|
$3,100.000
|
$2,800.000
|
$3,000.000
|
$2,800.000
|
$3,000.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
14.000
|
$6,300.000
|
$8,250.000
|
$3,000.000
|
$5,300.000
|
$5,000.000
|
$8,100.000
|
$2,500.000
|
$10,000.000
|
|
|
LITTER REMOVAL
|
CYC
|
14.000
|
$4,100.000
|
$5,500.000
|
$2,500.000
|
$3,600.000
|
$1,000.000
|
$4,200.000
|
$910.010
|
$5,000.000
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
6.000
|
$8,100.000
|
$6,600.000
|
$6,500.000
|
$5,500.000
|
$5,000.000
|
$8,800.000
|
$6,000.000
|
$10,000.000
|
|
|
INSTALL FTB
|
LF
|
200.000
|
$54.100
|
$50.000
|
$50.000
|
$27.500
|
$45.000
|
$61.000
|
$43.630
|
$48.000
|
|
|
REMOVE FTB
|
LF
|
200.000
|
$10.760
|
$10.000
|
$10.000
|
$11.000
|
$10.000
|
$8.000
|
$3.770
|
$10.000
|
|
|
AMPHIBIAN/REPTILE EXCLUSION FENCE INST
|
LF
|
2,715.000
|
$3.830
|
$4.500
|
$4.500
|
$5.750
|
$4.000
|
$4.500
|
$4.000
|
$4.500
|
|
|
AMPHIBIAN/REPTILE EXCLUSION FENCE REM
|
LF
|
2,715.000
|
$1.050
|
$1.100
|
$1.000
|
$1.400
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
|
|
RETROFIT DET WARN SURF (SURF APPLIED)
|
SF
|
131.000
|
$59.760
|
$55.000
|
$55.000
|
$71.000
|
$25.000
|
$56.000
|
$46.920
|
$80.000
|
|
|
BBU SYSTEM (EXTERNAL BATTERY CABINET)
|
EA
|
1.000
|
$8,800.000
|
$7,650.000
|
$7,450.000
|
$7,650.000
|
$6,950.000
|
$7,350.000
|
$6,950.000
|
$8,000.000
|
|
|
VDS PROSR SYS
|
EA
|
1.000
|
$17,750.000
|
$11,750.000
|
$11,500.000
|
$11,720.000
|
$10,655.000
|
$12,000.000
|
$10,655.000
|
$12,000.000
|
|
|
VIVDS CAM ASSY VAR LNS
|
EA
|
2.000
|
$5,600.000
|
$6,405.000
|
$6,230.000
|
$6,500.000
|
$5,820.000
|
$6,200.000
|
$5,820.000
|
$6,200.000
|
|
|
HVDS W/VAR LNS
|
EA
|
2.000
|
$8,000.000
|
$6,525.000
|
$6,350.000
|
$6,525.000
|
$5,930.000
|
$6,300.000
|
$5,930.000
|
$6,300.000
|
|
|
VDS CNTRL SOFTWARE
|
EA
|
1.000
|
$390.000
|
$450.000
|
$435.000
|
$450.000
|
$405.000
|
$430.000
|
$405.000
|
$450.000
|
|
|
VDS CABLING
|
LF
|
1,055.000
|
$3.250
|
$3.900
|
$3.750
|
$3.850
|
$3.500
|
$4.000
|
$3.500
|
$4.000
|
|
Totals: |
$99,453,909.950
|
$89,285,640.220
|
$92,528,349.070
|
$92,886,054.520
|
$93,554,962.330
|
$99,220,428.460
|
$105,308,971.262
|
$109,382,476.790
|