Show Job Controls
Bid Cobra

RED RIVER BU 82-J (0046-01-070)

Items: 25

County: RED RIVER
Length: N/A
Highway: BU 82-J
District: PARIS
Control Number: 0046-01-070
DBE Goal: 0.0%
Project: BR 2024(726)
Guaranty: N/A
Time: 74 WORKING DAYS
Engineer's Estimate: $603,306.30
Date: 02/02/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
DANIEL TAYLOR
ZACHARY SMITH
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$603,306.30
$627,372.00
Over/Under Est: 3.99% $24,065.70
Over/Under Est: 6.85% $41,328.70
Amt Left: 2.75% $17,263.00
Over/Under Est: 11.88% $71,674.40
Amt Left: 7.59% $47,608.70
Delta: -4.71% -$30,345.70
Over/Under Est: 14.82% $89,411.70
Amt Left: 10.42% $65,346.00
Delta: -2.63% -$17,737.30
Over/Under Est: 15.95% $96,200.20
Amt Left: 11.5% $72,134.50
Delta: -0.98% -$6,788.50
Over/Under Est: 42.22% $254,742.20
Amt Left: 36.77% $230,676.50
Delta: -22.66% -$158,542.00
Over/Under Est: 65.7% $396,370.70
Amt Left: 59.34% $372,305.00
Delta: -16.51% -$141,628.50
$1,257,802.00
Over/Under Est: 108.48% $654,495.70
Amt Left: 100.49% $630,430.00
Delta: -25.82% -$258,125.00
Subcontractor Percentage Amount
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. 12.29% $77,104.02
DALLAS LITE AND BARRICADE, INC. 3.17% $19,887.69
STRAIGHT LINE SAWING & SEALING, INC. 3.03% $19,009.37
TEXOP CONSTRUCTION 2.47% $15,496.09
SKIDABRADER GROUP LLC 1.20% $7,528.46
Total: 22.16% $139,025.63

Bid Items & Bid Tabulations

25 Total 0 of 25
RED RIVER  |  BU 82-J  |  PARIS  |  0046-01-070  |  02/02/2024  |  $603,306.30  |  BR 2024(726)  |  BRIDGE MAINT  |  74 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AAD CONTRACTING INC.
GARRET SHIELDS INFRASTRUCTURE
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
DCC CONSTRUCTION AND SERVICES, L.L.C.
HIGHWAY 19 CONSTRUCTION LLC
SCR CIVIL CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
PLANE ASPH CONC PAV(0" TO 8")
SY 3,696.000 $5.000 $10.000 $10.000 $10.000 $8.000 $8.500 $11.000 $13.000 $20.000
CEM STABIL BKFL
CY 10.000 $250.000 $250.000 $200.000 $350.000 $400.000 $275.000 $1,615.000 $600.000 $350.000
FLOWABLE BACKFILL
CY 3.000 $300.000 $250.000 $600.000 $650.000 $1,000.000 $395.000 $1,615.000 $600.000 $350.000
CL B CONC (FLUME)
CY 2.000 $638.000 $1,000.000 $1,000.000 $1,200.000 $1,000.000 $650.000 $5,100.000 $2,500.000 $1,000.000
CONC STR REPAIR (EPOXY MORTAR)
SF 4.000 $2,500.000 $175.000 $200.000 $400.000 $3,000.000 $525.000 $550.000 $500.000 $500.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 658.000 $300.000 $200.000 $250.000 $250.000 $175.000 $265.000 $257.000 $350.000 $300.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 132.000 $200.000 $200.000 $230.000 $300.000 $175.000 $180.000 $385.000 $250.000 $185.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 300.000 $200.000 $250.000 $230.000 $300.000 $200.000 $220.000 $235.000 $250.000 $250.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 880.000 $65.000 $30.000 $60.000 $55.000 $75.000 $55.000 $40.000 $65.000 $100.000
CLEANING AND SEALING JOINTS (CL 7)
LF 243.000 $65.000 $85.000 $60.000 $45.000 $35.000 $85.000 $60.000 $70.000 $100.000
SHOT BLASTING
SY 429.000 $6.000 $20.000 $20.000 $10.000 $10.000 $18.500 $8.600 $82.000 $150.000
MOBILIZATION
LS 1.000 $52,573.300 $135,000.000 $60,000.000 $70,000.000 $50,000.000 $63,000.000 $85,800.000 $85,000.000 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $10,000.000 $5,000.000 $3,500.000 $3,000.000 $4,500.000 $9,800.000 $12,500.000 $10,000.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 87.000 $2.000 $3.000 $5.000 $0.100 $1.000 $1.500 $6.000 $6.000 $2.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,584.000 $4.000 $1.500 $5.000 $3.000 $5.000 $5.000 $3.150 $6.000 $1.000
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 200.000 $4.000 $1.500 $5.000 $3.000 $5.000 $5.000 $3.150 $6.000 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 550.000 $4.000 $1.500 $5.000 $3.000 $5.000 $5.000 $3.150 $6.000 $1.000
REFL PAV MRKR TY II-A-A
EA 20.000 $10.000 $5.000 $5.000 $8.000 $10.000 $10.000 $5.750 $12.000 $5.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 5.000 $550.000 $150.000 $200.000 $150.000 $75.000 $85.000 $200.000 $600.000 $100.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 359.000 $160.000 $220.000 $180.000 $255.000 $200.000 $275.000 $245.000 $300.000 $200.000
BONDING COURSE
GAL 163.000 $11.000 $15.000 $10.000 $15.000 $10.000 $4.500 $15.000 $25.000 $8.000
POLYESTER POLYMER CONC OVERLAY (1")
SY 429.000 $125.000 $10.000 $200.000 $140.000 $467.000 $250.000 $297.000 $400.000 $850.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 15.000 $26.000 $350.000 $100.000 $150.000 $300.000 $250.000 $200.000 $300.000 $150.000
TMA (STATIONARY)
DAY 15.000 $300.000 $350.000 $300.000 $275.000 $300.000 $250.000 $700.000 $400.000 $250.000
REML & DISPL DRIFTWOOD & DEBRIS
LS 1.000 $3,000.000 $10,000.000 $5,000.000 $15,000.000 $5,000.000 $7,500.000 $65,000.000 $30,000.000 $85,000.000
Totals: $603,306.300 $627,372.000 $644,635.000 $674,980.700 $692,718.000 $699,506.500 $858,048.500 $999,677.000 $1,257,802.000