Job Info for 0049-01-095

County: MCLENNAN Highway: SH 6 Date: 02/02/2024 (9 months ago) Engineer's Estimate: $29,068,891 Control Number: 0049-01-095
Project: F 2024(764) District: WACO Time: 120 WORKING DAYS Type: SURFACING/ROADWAY RESTORATION
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $29,068,891.09
BIG CREEK CONSTRUCTION, LTD.   $22,852,587.83 1
-21.38% | -$6,216,303.26
TEXAS MATERIALS GROUP, INC.   $26,259,213.67 2
-9.67% | -$2,809,677.42
14.91% | $3,406,625.84
KNIFE RIVER CORPORATION - SOUTH   $26,782,412.37 3
-7.87% | -$2,286,478.72
17.2% | $3,929,824.54
1.99% | $523,198.70
Subcontractor Percentage Amount
KING GEORGE TRAFFIC SOLUTIONS LLC 2.71% $619,305.13
D. I. J. CONSTRUCTION, INC. 2.28% $521,039.00
ROADWAY SPECIALTIES, INC. 1.67% $381,638.22
WILKO INDUSTRIAL, L.L.C. 1.00% $228,525.88
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 0.47% $107,407.16
PRIMATE CONSTRUCTION, LP 0.38% $86,839.83
PROFESSIONAL TRAFFIC CONTROL LLC 0.14% $31,993.62
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.05% $11,426.29
Total: 8.70% $1,988,175.13

Bid Items

Items: 44, 0 filtered
MCLENNAN SH 6  |  WACO  |  0049-01-095  |  02/02/2024  |  $29,068,891  |  F 2024(764)  |  SURF/ROADWAY RESTOR  |  120 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BIG CREEK CONSTRUCTION, LTD. TEXAS MATERIALS GROUP, INC. KNIFE RIVER CORPORATION - SOUTH
104 6054 REMOVING CONCRETE(MOW STRIP) LF 4,750.000 $15.000 $14.000 $8.000 $10.250
134 6001 BACKFILL (TY A) STA 1,932.100 $222.500 $150.000 $160.000 $210.000
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 5,000.000 $95.000 $60.000 $68.000 $88.500
354 6220 PLANE ASPH CONC PAV (0" TO 2" MICRO) SY 932,640.000 $2.000 $1.280 $1.850 $1.810
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 404.100 $621.310 $650.000 $625.000 $645.000
438 6002 CLEANING AND SEALING EXIST JOINTS(CL3) LF 1,124.000 $38.600 $40.000 $27.640 $38.000
438 6004 CLEANING AND SEALING EXIST JOINTS(CL7) LF 1,607.700 $50.350 $40.000 $33.510 $43.000
479 6001 ADJUSTING MANHOLES EA 2.000 $3,000.000 $1,500.000 $1,800.000 $2,300.000
500 6001 MOBILIZATION LS 1.000 $2,600,000.000 $1,625,000.000 $780,000.000 $2,350,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $10,000.000 $3,000.000 $2,560.000 $40,000.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 363,717.000 $0.400 $0.200 $0.180 $0.250
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 4,910.000 $31.290 $35.000 $27.000 $31.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 29.000 $2,560.000 $2,900.000 $2,700.000 $3,000.000
540 6014 SHORT RADIUS LF 65.000 $150.000 $50.000 $24.000 $48.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,400.000 $1,411.000 $1,100.000 $1,400.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 4,750.000 $3.790 $9.000 $3.000 $2.700
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 29.000 $366.670 $340.000 $250.000 $270.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 30.000 $3,312.500 $3,500.000 $2,850.000 $3,100.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 29.000 $452.120 $475.000 $275.000 $270.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 56.000 $62.500 $50.000 $38.000 $45.000
662 6005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 47,760.000 $0.400 $0.220 $0.500 $0.540
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 189,669.000 $0.330 $0.220 $0.220 $0.240
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 30,427.000 $0.570 $0.260 $0.500 $0.540
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 183,008.000 $0.330 $0.220 $0.220 $0.240
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 19,087.000 $1.170 $1.500 $0.930 $1.450
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 4,591.000 $2.070 $1.500 $0.930 $1.450
666 6030 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 7,596.000 $2.030 $1.250 $1.300 $1.400
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 30,427.000 $1.370 $1.250 $1.000 $1.080
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 1,055.000 $17.520 $7.000 $6.250 $6.720
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 47,760.000 $0.660 $0.880 $0.800 $0.860
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 189,669.000 $0.710 $0.920 $0.700 $0.750
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 183,008.000 $0.690 $0.880 $0.700 $0.750
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 127.000 $300.000 $250.000 $205.000 $220.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 100.000 $400.000 $300.000 $240.000 $258.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 863.000 $50.000 $60.000 $40.000 $43.000
672 6007 REFL PAV MRKR TY I-C EA 2,277.000 $4.300 $6.000 $5.000 $5.250
3076 6043 D-GR HMA TY-D PG70-22 (LEVEL-UP) TON 51,297.000 $120.000 $88.000 $102.200 $119.000
3080 6007 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 TON 102,590.000 $131.000 $120.000 $145.000 $134.000
3080 6029 TACK COAT GAL 93,264.000 $3.380 $3.500 $2.950 $0.010
3085 6001 UNDERSEAL COURSE GAL 233,166.000 $7.500 $1.500 $4.850 $0.010
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 6.000 $11,810.000 $7,500.000 $10,000.000 $15,000.000
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 80.000 $25.000 $25.000 $25.000 $26.500
6185 6002 TMA (STATIONARY) DAY 270.000 $628.190 $350.000 $240.000 $250.000
6185 6003 TMA (MOBILE OPERATION) HR 1,800.000 $24.330 $73.000 $40.000 $20.000
Totals: $29,068,891.09 $22,852,587.83 $26,259,213.68 $26,782,412.37