MCLENNAN BU 77-L (0014-10-071)

Items: 41

County: MCLENNAN
Length: N/A
Highway: BU 77-L
District: WACO
Control Number: 0014-10-071
DBE Goal: 300.0%
Project: BR 2024(859)
Guaranty: N/A
Time: 30 WORKING DAYS
Engineer's Estimate: $1,247,631.06
Date: 02/01/2024 (2 years ago)
Contract Number: N/A
Type: REMOVAL AND DISPOSAL OF BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,247,631.06
$1,121,180.80
Over/Under Est: -10.14% -$126,450.26
Over/Under Est: 4.82% $60,075.94
Amt Left: 16.64% $186,526.20
Over/Under Est: 22.79% $284,305.69
Amt Left: 36.64% $410,755.95
Delta: -17.15% -$224,229.75
$1,941,568.00
Over/Under Est: 55.62% $693,936.94
Amt Left: 73.17% $820,387.20
Delta: -26.74% -$409,631.25
Subcontractor Percentage Amount
CND CONTRACTING 26.60% $330,009.83
F & W ELECTRICAL CONTRACTORS, INC. 4.26% $52,851.20
MURRAY CONSTRUCTION 2.81% $34,861.94
WOLFE CONSTRUCTION GROUP, INCORPORATED 2.74% $33,993.49
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.82% $10,173.24
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.77% $9,552.92
WILKO INDUSTRIAL, L.L.C. 0.67% $8,312.28
Total: 38.67% $479,754.90

Bid Items & Bid Tabulations

41 Total 0 of 41
MCLENNAN  |  BU 77-L  |  WACO  |  0014-10-071  |  02/01/2024  |  $1,247,631.06  |  BR 2024(859)  |  RMVL AND DISPOSAL OF BRIDGE  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
JAMES CONSTRUCTION GROUP, LLC
BIG CREEK CONSTRUCTION, LTD.
FNH CONSTRUCTION, LLC
REMOVING CONC (PAV)
SY 10,715.000 $17.500 $15.000 $15.000 $14.500 $20.000
REMOVING CONC (MEDIANS)
SY 1,027.000 $36.000 $22.000 $7.000 $12.000 $20.000
REMOVING CONC (APPR SLAB)
SY 348.000 $50.000 $25.000 $19.000 $60.000 $100.000
EXCAVATION (ROADWAY)
CY 21,514.000 $15.530 $14.000 $16.070 $23.000 $15.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 3,343.000 $20.000 $5.000 $13.920 $20.000 $30.000
FURNISHING AND PLACING TOPSOIL (4")
SY 23,612.000 $1.000 $2.000 $0.320 $3.000 $8.000
ROLL SODDING
SY 2,633.000 $5.500 $6.500 $5.730 $6.000 $10.000
BROADCAST SEED (PERM) (URBAN) (CLAY)
SY 20,979.000 $0.760 $0.200 $0.200 $0.250 $1.000
VEGETATIVE WATERING
MG 190.000 $15.000 $50.000 $31.170 $46.000 $50.000
ADJUSTING INLET (CAP)
EA 3.000 $2,650.000 $3,800.000 $8,325.570 $4,500.000 $2,500.000
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 2.000 $150,000.000 $130,000.000 $139,410.000 $175,000.000 $200,000.000
MOBILIZATION
LS 1.000 $78,191.640 $85,000.000 $131,551.700 $150,000.000 $175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $7,000.000 $3,000.000 $19,227.990 $10,000.000 $15,000.000
SANDBAGS FOR EROSION CONTROL
EA 3.000 $18.250 $100.000 $61.780 $10.000 $50.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,774.000 $4.000 $4.000 $4.260 $3.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,774.000 $2.500 $1.000 $1.140 $1.250 $2.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 120.000 $12.000 $50.000 $28.530 $32.000 $40.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 80.000 $13.900 $50.000 $42.800 $20.000 $40.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 120.000 $12.000 $50.000 $28.530 $32.000 $40.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 80.000 $12.330 $50.000 $42.800 $20.000 $40.000
CONC CURB & GUTTER (TY II)
LF 120.000 $45.000 $78.000 $57.740 $90.000 $65.000
REMOVE METAL BEAM GUARD FENCE
LF 555.000 $4.000 $7.500 $5.000 $6.000 $5.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $172.210 $500.000 $1,000.000 $250.000 $1,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $269.240 $500.000 $1,500.000 $350.000 $2,500.000
REMOVE RD IL ASM (TRANS-BASE)
EA 12.000 $525.000 $1,350.000 $920.000 $1,000.000 $2,500.000
CONDT (PVC) (SCH 40) (2")
LF 23.000 $13.500 $75.000 $65.000 $72.000 $50.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 88.000 $45.000 $95.000 $85.000 $95.000 $100.000
CONDT (RM) (1")
LF 30.000 $32.650 $35.000 $30.000 $35.000 $150.000
ELEC CONDR (NO.8) BARE
LF 156.000 $1.290 $5.500 $2.000 $2.500 $3.000
ELEC CONDR (NO.8) INSULATED
LF 312.000 $1.900 $6.750 $3.000 $3.500 $3.000
GROUND BOX TY A (122311)
EA 2.000 $900.000 $1,250.000 $1,100.000 $1,200.000 $1,500.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 1.000 $7,300.000 $10,000.000 $8,500.000 $9,500.000 $9,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $950.000 $1,025.000 $900.000 $1,000.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 9.000 $525.000 $575.000 $390.000 $550.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 4.000 $585.000 $625.000 $415.000 $600.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 24.000 $132.930 $110.000 $80.000 $110.000 $100.000
REMOVE OVERHD SIGN SUP
EA 2.000 $8,000.000 $6,000.000 $5,000.000 $5,500.000 $2,500.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 380.000 $10.000 $17.000 $16.930 $12.000 $20.000
LEAD CONTAINING COATING MANAGEMENT
SF 120.000 $71.000 $100.000 $743.000 $100.000 $1,150.000
TMA (STATIONARY)
DAY 14.000 $300.000 $250.000 $410.050 $200.000 $250.000
SOLAR POWERED LED SIGN
EA 8.000 $5,500.000 $3,500.000 $4,350.000 $3,150.000 $12,500.000
Totals: $1,247,631.060 $1,121,180.800 $1,307,707.000 $1,531,936.750 $1,941,568.000