Items: 62
County: KAUFMAN
Length: N/A
Highway: FM 1391
District: DALLAS
Control Number: 1396-01-013
DBE Goal: 750.0%
Project: BR 2024(767)
Guaranty: N/A
Time: 123 WORKING DAYS
Engineer's Estimate: $5,890,953.05
Date: 02/02/2024 7:00 PM CST (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,890,953.05 | |||
| $5,443,323.50 |
-7.6%
-$447,629.55
|
|||
| $5,656,473.25 |
-3.98%
-$234,479.80
|
3.92%
$213,149.75
|
||
| $5,796,575.60 |
-1.6%
-$94,377.45
|
6.49%
$353,252.10
|
-2.48%
-$140,102.35
|
|
| $6,409,510.18 |
8.8%
$518,557.13
|
17.75%
$966,186.68
|
-10.57%
-$612,934.58
|
|
| $6,802,263.40 |
15.47%
$911,310.35
|
24.97%
$1,358,939.90
|
-6.13%
-$392,753.22
|
|
| $6,837,424.50 |
16.07%
$946,471.45
|
25.61%
$1,394,101.00
|
-0.52%
-$35,161.10
|
|
| $7,085,239.30 |
20.27%
$1,194,286.25
|
30.16%
$1,641,915.80
|
-3.62%
-$247,814.80
|
|
| $7,297,277.60 |
23.87%
$1,406,324.55
|
34.06%
$1,853,954.10
|
-2.99%
-$212,038.30
|
|
| $7,395,000.00 |
25.53%
$1,504,046.95
|
35.85%
$1,951,676.50
|
-1.34%
-$97,722.40
|
|
| $7,976,078.75 |
35.4%
$2,085,125.70
|
46.53%
$2,532,755.25
|
-7.86%
-$581,078.75
|
E
Engineer's Estimate
$5,890,953.05
1
Awarded
$5,443,323.50
Over/Under Est:
-7.6%
-$447,629.55
$5,656,473.25
Over/Under Est:
-3.98%
-$234,479.80
Amt Left:
3.92%
$213,149.75
$5,796,575.60
Over/Under Est:
-1.6%
-$94,377.45
Amt Left:
6.49%
$353,252.10
Delta:
-2.48%
-$140,102.35
$6,409,510.18
Over/Under Est:
8.8%
$518,557.13
Amt Left:
17.75%
$966,186.68
Delta:
-10.57%
-$612,934.58
$6,802,263.40
Over/Under Est:
15.47%
$911,310.35
Amt Left:
24.97%
$1,358,939.90
Delta:
-6.13%
-$392,753.22
$6,837,424.50
Over/Under Est:
16.07%
$946,471.45
Amt Left:
25.61%
$1,394,101.00
Delta:
-0.52%
-$35,161.10
$7,085,239.30
Over/Under Est:
20.27%
$1,194,286.25
Amt Left:
30.16%
$1,641,915.80
Delta:
-3.62%
-$247,814.80
$7,297,277.60
Over/Under Est:
23.87%
$1,406,324.55
Amt Left:
34.06%
$1,853,954.10
Delta:
-2.99%
-$212,038.30
$7,395,000.00
Over/Under Est:
25.53%
$1,504,046.95
Amt Left:
35.85%
$1,951,676.50
Delta:
-1.34%
-$97,722.40
$7,976,078.75
Over/Under Est:
35.4%
$2,085,125.70
Amt Left:
46.53%
$2,532,755.25
Delta:
-7.86%
-$581,078.75
Bid Items & Bid Tabulations