Job Info for 6462-10-001

County: BURLESON Highway: SH0036 Date: 02/02/2024 (9 months ago) Changed Engineer's Estimate: $333,750 Control Number: 6462-10-001
Project: RMC - 646210001 District: BRYAN Time: 365 CALENDAR DAYS Type: TREE REMOVAL
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $333,750.00
ICOS MANAGEMENT, LLC   $285,360.00 1
-14.5% | -$48,390.00
ABESCAPE LANDSCAPING, LLC   $480,650.00 2
44.01% | $146,900.00
68.44% | $195,290.00
CLAW CONTRACTORS, LLC   $513,165.00 3
53.76% | $179,415.00
79.83% | $227,805.00
6.76% | $32,515.00
RISE UP CONSTRUCTION LLC   $797,200.00 4
138.86% | $463,450.00
179.37% | $511,840.00
55.35% | $284,035.00
Subcontractor Percentage Amount
TEAL ARROW LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items

Items: 12, 0 filtered
BURLESON SH0036  |  BRYAN  |  6462-10-001  |  02/02/2024  |  $333,750  |  RMC - 646210001  |  TREE RMVL  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate ICOS MANAGEMENT, LLC ABESCAPE LANDSCAPING, LLC CLAW CONTRACTORS, LLC RISE UP CONSTRUCTION LLC
500 6033 MOBILIZATION (CALLOUT) EA 5.000 $3,000.000 $4,872.000 $2,000.000 $12,733.000 $5,000.000
752 6005 TREE REMOVAL (4" - 12" DIA) EA 750.000 $85.000 $120.000 $100.000 $50.000 $125.000
752 6006 TREE REMOVAL (12" - 18" DIA) EA 400.000 $85.000 $50.000 $160.000 $75.000 $199.000
752 6007 TREE REMOVAL (18" - 24" DIA) EA 300.000 $120.000 $100.000 $225.000 $140.000 $299.000
752 6008 TREE REMOVAL (24" - 30" DIA) EA 200.000 $210.000 $50.000 $325.000 $400.000 $399.000
752 6009 TREE REMOVAL (30" - 36" DIA) EA 150.000 $250.000 $150.000 $450.000 $550.000 $678.000
752 6010 TREE REMOVAL (36" - 42" DIA) EA 50.000 $425.000 $200.000 $750.000 $600.000 $678.000
752 6011 TREE REMOVAL (42" - 48" DIA) EA 10.000 $500.000 $500.000 $1,000.000 $650.000 $987.000
752 6012 TREE REMOVAL (48" - 60" DIA) EA 10.000 $650.000 $300.000 $1,400.000 $750.000 $988.000
752 6013 TREE REMOVAL (60" - 72" DIA) EA 10.000 $850.000 $300.000 $1,400.000 $850.000 $2,345.000
752 6014 STUMP REMOVAL EA 50.000 $285.000 $50.000 $123.000 $100.000 $321.000
6185 6002 TMA (STATIONARY) DAY 100.000 $500.000 $650.000 $500.000 $1,200.000 $2,345.000
Totals: $333,750.00 $285,360.00 $480,650.00 $513,165.00 $797,200.00