Bid Cobra

WOOD FM 1254 (1390-03-005)

Items: 66

County: WOOD
Length: N/A
Highway: FM 1254
District: TYLER
Control Number: 1390-03-005
DBE Goal: N/A
Project: BR 2018(791)
Guaranty: N/A
Time: 108 WORKING DAYS
Engineer's Estimate: $1,663,511.73
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE & APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,663,511.73
$1,518,305.69
Over/Under Est: -8.73% -$145,206.04
Over/Under Est: -5.63% -$93,667.96
Amt Left: 3.39% $51,538.08
Over/Under Est: -4.03% -$66,979.39
Amt Left: 5.15% $78,226.65
Delta: -1.70% -$26,688.57
Over/Under Est: 1.45% $24,160.02
Amt Left: 11.15% $169,366.06
Delta: -5.71% -$91,139.41
Over/Under Est: 9% $149,702.53
Amt Left: 19.42% $294,908.57
Delta: -7.44% -$125,542.51
$1,863,693.93
Over/Under Est: 12.03% $200,182.20
Amt Left: 22.75% $345,388.24
Delta: -2.78% -$50,479.67
$2,518,797.45
Over/Under Est: 51.41% $855,285.72
Amt Left: 65.9% $1,000,491.76
Delta: -35.15% -$655,103.52

Bid Items & Bid Tabulations

66 Total 0 of 66
WOOD  |  FM 1254  |  TYLER  |  1390-03-005  |  03/06/2019  |  $1,663,511.73  |  BR 2018(791)  |  REPLACE BRIDGE & APPROACHES  |  108 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
HIGHWAY 19 CONSTRUCTION LLC
EAST TEXAS BRIDGE, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PIERCE R & B LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 8.600 $1,500.000 $3,000.000 $2,000.000 $1,500.000 $2,350.000 $3,000.000 $1,750.000 $20,000.000
REMOVING CONC (RIPRAP)
SY 198.000 $15.000 $8.000 $16.000 $25.000 $20.000 $15.000 $19.750 $20.000
REMOVING CONCRETE(MOW STRIP)
LF 774.000 $5.250 $8.000 $13.250 $5.000 $8.000 $5.000 $5.500 $20.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 2,293.000 $6.000 $4.520 $4.750 $10.000 $5.000 $10.000 $6.000 $20.000
EXCAVATION (ROADWAY)
CY 140.000 $9.000 $24.000 $23.500 $10.000 $10.000 $20.000 $20.000 $20.000
EXCAVATION (CHANNEL)
CY 261.000 $15.500 $13.000 $25.000 $15.000 $10.000 $20.000 $25.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 2,661.000 $15.000 $10.000 $11.500 $30.000 $12.000 $15.000 $15.000 $30.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,616.000 $2.000 $4.000 $5.000 $3.000 $2.000 $4.000 $4.000 $6.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 3,232.000 $1.000 $1.050 $1.000 $0.900 $1.000 $1.500 $0.970 $1.000
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 1,616.000 $1.200 $1.050 $1.000 $0.900 $1.000 $0.500 $0.990 $1.000
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 1,616.000 $1.000 $0.100 $0.950 $0.900 $1.000 $0.500 $0.990 $1.000
VEGETATIVE WATERING
MG 142.210 $18.000 $5.000 $1.000 $10.000 $8.000 $1.000 $25.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 200.000 $2.100 $2.250 $2.800 $2.000 $2.850 $4.000 $2.500 $6.500
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 1,169.000 $4.000 $5.500 $5.500 $7.000 $10.000 $8.000 $7.000 $10.000
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 28.000 $175.000 $225.000 $230.000 $500.000 $400.000 $400.000 $400.000 $300.000
D-GR HMA(SQ) TY-D PG64-22
TON 283.000 $170.000 $120.000 $100.000 $144.000 $130.000 $150.000 $148.000 $120.000
SUPERPAVE MIXTURES SP-B PG64-22
TON 690.000 $130.000 $120.000 $100.000 $150.000 $125.000 $150.000 $150.000 $110.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-22
TON 307.000 $130.000 $130.000 $100.000 $160.000 $130.000 $160.000 $160.000 $120.000
PLANE ASPH CONC PAV(0" TO 2")
SY 272.000 $1.500 $19.500 $8.500 $20.000 $25.000 $20.000 $21.250 $10.000
CEM STABIL BKFL
CY 64.000 $300.000 $170.000 $220.000 $180.000 $200.000 $200.000 $200.000 $350.000
DRILL SHAFT (30 IN)
LF 596.000 $110.000 $172.000 $175.000 $199.000 $200.000 $150.000 $195.000 $520.000
CL C CONC (ABUT)
CY 36.400 $1,000.000 $860.000 $875.000 $914.000 $900.000 $1,000.000 $1,000.000 $850.000
CL C CONC (CAP)
CY 30.200 $1,000.000 $940.000 $850.000 $1,100.000 $900.000 $1,000.000 $1,200.000 $850.000
CL C CONC (COLUMN)
CY 12.300 $1,500.000 $1,180.000 $950.000 $1,000.000 $1,000.000 $1,200.000 $1,200.000 $850.000
REINF CONC SLAB (BOX BEAM)
SF 8,280.000 $15.000 $15.100 $14.500 $10.000 $16.000 $16.000 $16.000 $15.000
APPROACH SLAB
CY 70.600 $500.000 $590.000 $475.000 $500.000 $520.000 $600.000 $525.000 $1,000.000
SHEAR KEY
CY 39.600 $400.000 $340.000 $405.000 $350.000 $420.000 $475.000 $395.000 $1,000.000
PRESTR CONC BOX BEAM (4B20)
LF 714.010 $140.000 $179.850 $170.000 $168.000 $169.000 $235.000 $205.000 $165.000
PRESTR CONC BOX BEAM (5B20)
LF 1,071.020 $140.000 $157.850 $170.000 $168.000 $169.000 $235.000 $190.000 $165.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 2,462.000 $140.000 $102.000 $135.000 $90.000 $130.000 $130.000 $140.000 $165.000
RIPRAP (MOW STRIP)(4 IN)
CY 51.000 $425.000 $405.000 $480.000 $400.000 $400.000 $450.000 $475.000 $550.000
RAIL (TY T223)
LF 392.000 $95.000 $95.000 $78.000 $100.000 $90.000 $110.000 $100.000 $135.000
ARMOR JOINT (SEALED)
LF 84.000 $80.000 $90.000 $70.000 $100.000 $90.000 $75.000 $90.000 $30.000
RC PIPE (CL III)(18 IN)
LF 32.000 $50.000 $60.000 $58.000 $35.000 $50.000 $80.000 $60.000 $85.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $700.000 $925.000 $745.000 $550.000 $750.000 $1,600.000 $800.000 $2,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $100,000.000 $16,000.000 $20,000.000 $50,000.000 $40,000.000 $40,000.000 $72,000.000 $150,000.000
MOBILIZATION
LS 1.000 $150,299.090 $150,000.000 $120,000.000 $160,000.000 $170,000.000 $145,000.000 $180,000.000 $240,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $3,000.000 $1,500.000 $2,000.000 $1,000.000 $1,500.000 $1,500.000 $2,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 185.000 $30.000 $31.960 $26.400 $35.000 $27.000 $10.000 $25.500 $30.000
ROCK FILTER DAMS (REMOVE)
LF 185.000 $8.750 $12.000 $13.200 $10.000 $8.000 $1.000 $11.000 $15.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 100.000 $25.000 $20.000 $25.000 $30.000 $40.000 $10.000 $40.000 $30.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $125.000 $40.000 $150.000 $30.000 $40.000 $10.000 $50.000 $150.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,347.000 $2.400 $3.000 $2.500 $2.500 $2.550 $2.000 $2.870 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,347.000 $0.700 $1.000 $0.880 $1.000 $1.000 $1.000 $1.110 $2.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 24.000 $125.000 $65.000 $150.000 $30.000 $40.000 $10.000 $50.000 $200.000
DRIVEWAYS (ACP)
SY 88.000 $30.000 $48.000 $80.000 $40.000 $35.000 $40.000 $60.000 $42.000
MTL W-BEAM GD FEN (TIM POST)
LF 705.000 $20.000 $30.000 $19.800 $18.000 $20.000 $24.000 $19.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $1,800.000 $1,625.000 $1,470.000 $1,600.000 $1,600.000 $1,560.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $2.750 $2.000 $2.200 $2.000 $2.200 $5.000 $2.500 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $200.000 $300.000 $220.000 $200.000 $220.000 $200.000 $228.000 $500.000
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $200.000 $475.000 $165.000 $150.000 $165.000 $300.000 $175.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,400.000 $2,985.000 $2,750.000 $2,500.000 $2,750.000 $2,600.000 $2,652.000 $2,850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $350.000 $770.000 $680.000 $700.000 $700.000 $600.000 $750.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 2.000 $450.000 $900.000 $760.000 $700.000 $770.000 $600.000 $750.000 $650.000
REMOVE SM RD SN SUP&AM
EA 5.000 $90.000 $200.000 $315.000 $100.000 $100.000 $200.000 $150.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $25.000 $16.500 $35.000 $20.000 $30.000 $27.500 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $35.000 $75.000 $27.500 $35.000 $30.000 $50.000 $32.000 $100.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,720.000 $0.250 $0.570 $1.650 $1.500 $1.650 $2.000 $1.620 $2.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 216.000 $0.400 $0.570 $2.200 $2.000 $2.200 $2.000 $2.500 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 861.000 $0.260 $0.570 $2.200 $2.000 $2.200 $2.000 $2.250 $2.000
RE PM W/RET REQ TY II (W) 4" (SLD)
LF 440.000 $0.300 $0.570 $1.100 $1.000 $1.100 $2.000 $1.200 $2.000
RE PM W/RET REQ TY II (Y) 4" (BRK)
LF 55.000 $0.450 $0.570 $1.100 $1.000 $1.100 $4.000 $2.340 $2.000
RE PM W/RET REQ TY II (Y) 4" (SLD)
LF 220.000 $0.300 $0.570 $1.100 $1.000 $1.100 $2.000 $1.370 $2.000
REFL PAV MRKR TY II-A-A
EA 22.000 $3.250 $1.800 $5.500 $5.000 $5.500 $5.000 $8.500 $15.000
PAV SURF PREP FOR MRK (4")
LF 715.000 $0.300 $0.570 $0.550 $0.500 $0.550 $1.000 $0.620 $2.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $3,500.000 $10,000.000 $5,000.000 $10,000.000 $5,000.000 $8,400.000 $8,000.000
Totals: $1,663,511.730 $1,518,305.706 $1,569,843.770 $1,596,532.340 $1,687,671.750 $1,813,214.260 $1,863,693.930 $2,518,797.450