Show Job Controls
Bid Cobra

WISE SH0114 (6388-99-001)

Items: 23

County: WISE
Length: N/A
Highway: SH0114
District: FORT WORTH
Control Number: 6388-99-001
DBE Goal: 0.0%
Project: BPM - 638899001
Guaranty: N/A
Time: 28 W
Engineer's Estimate: $155,637.00
Date: 02/23/2024 (2 years ago) Changed
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
EDREAN CHENG
OSCAR R CHAVEZ
JANA ROBINSON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$155,637.00
$136,896.30
Over/Under Est: -12.04% -$18,740.70
Over/Under Est: -4.91% -$7,640.00
Amt Left: 8.11% $11,100.70
Over/Under Est: -1.22% -$1,904.00
Amt Left: 12.3% $16,836.70
Delta: -3.88% -$5,736.00
Over/Under Est: 44.12% $68,667.60
Amt Left: 63.85% $87,408.30
Delta: -45.91% -$70,571.60
$269,652.00
Over/Under Est: 73.26% $114,015.00
Amt Left: 96.98% $132,755.70
Delta: -20.22% -$45,347.40

Bid Items & Bid Tabulations

23 Total 0 of 23
WISE  |  SH0114  |  FORT WORTH  |  6388-99-001  |  02/23/2024  |  $155,637.00  |  BPM - 638899001  |  BRIDGE PREVENT MAINT  |  28 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCOUT 5 CONSTRUCTION LLC
GARRET SHIELDS INFRASTRUCTURE
RISE UP CONSTRUCTION LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
IBCTX, LLC
PREPARING ROW
AC 0.400 $12,500.000 $0.010 $10,000.000 $5,000.000 $17,454.000 $50,000.000
REMOVING CONC (RIPRAP)
SY 622.000 $30.000 $75.000 $40.000 $37.000 $24.000 $15.000
REMOVING CONC (CURB)
LF 12.000 $15.000 $100.000 $20.000 $37.000 $70.000 $100.000
REMOVING CONC (FLUME)
SY 22.000 $40.000 $200.000 $50.000 $37.000 $112.000 $200.000
REMOVING CONCRETE(MOW STRIP)
LF 14.000 $15.000 $50.000 $50.000 $37.000 $113.000 $100.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 60.000 $100.000 $120.000 $100.000 $55.000 $268.000 $225.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 273.000 $3.000 $0.010 $1.000 $2.000 $4.000 $4.000
VEGETATIVE WATERING
MG 41.000 $40.000 $0.010 $50.000 $123.000 $147.000 $75.000
RIPRAP (CONC)(4 IN)
CY 86.000 $650.000 $500.000 $700.000 $656.000 $749.000 $1,400.000
RIPRAP (CONC)(FLUME)
CY 5.000 $1,300.000 $900.000 $1,000.000 $1,500.000 $3,281.000 $1,400.000
RIPRAP (MOW STRIP)(4 IN)
CY 1.000 $1,000.000 $400.000 $1,000.000 $1,500.000 $10,019.000 $2,000.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 114.000 $55.000 $60.000 $80.000 $45.000 $83.000 $50.000
MOBILIZATION
LS 1.000 $15,000.000 $7,000.000 $10,000.000 $15,000.000 $22,428.000 $26,900.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $5,500.000 $0.010 $5,000.000 $3,454.000 $11,512.000 $15,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $20.000 $0.010 $5.000 $12.000 $51.000 $72.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $5.000 $0.010 $5.000 $12.000 $32.000 $36.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 44.000 $10.000 $0.010 $4.000 $12.000 $11.000 $24.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 44.000 $2.000 $0.010 $2.000 $12.000 $8.000 $12.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $3,000.000 $3,500.000 $5,000.000 $3,000.000 $6,029.000 $4,500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $400.000 $0.010 $500.000 $4,500.000 $1,045.000 $1,000.000
INS DEL ASSM(D-SW)SZ 1(WFLX)GF2
EA 1.000 $100.000 $0.010 $50.000 $56.000 $37.000 $350.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $5,000.000 $1,000.000 $3,400.000 $2,530.000 $1,500.000
TMA (STATIONARY)
DAY 15.000 $250.000 $100.000 $300.000 $500.000 $417.000 $75.000
Totals: $155,637.000 $136,896.304 $147,997.000 $153,733.000 $224,304.600 $269,652.000