Job Info for 6388-99-001

County: WISE Highway: SH0114 Date: 02/23/2024 (9 months ago) Changed Engineer's Estimate: $155,637 Control Number: 6388-99-001
Project: BPM - 638899001 District: FORT WORTH Time: 28 W Type: BRIDGE PREVENTATIVE MAINTENANCE
Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $155,637.00
SCOUT 5 CONSTRUCTION LLC   $136,896.30 1
-12.04% | -$18,740.70
GARRET SHIELDS INFRASTRUCTURE   $147,997.00 2
-4.91% | -$7,640.00
8.11% | $11,100.70
RISE UP CONSTRUCTION LLC   $153,733.00 3
-1.22% | -$1,904.00
12.3% | $16,836.70
3.88% | $5,736.00
SCOTT TUCKER CONSTRUCTION COMPANY, LLC   $224,304.60 4
44.12% | $68,667.60
63.85% | $87,408.30
45.91% | $70,571.60
IBCTX, LLC   $269,652.00 5
73.26% | $114,015.00
96.98% | $132,755.70
20.22% | $45,347.40

Bid Items

Items: 23, 0 filtered
WISE SH0114  |  FORT WORTH  |  6388-99-001  |  02/23/2024  |  $155,637  |  BPM - 638899001  |  BRIDGE PREVENT MAINT  |  28 W
Item code Description Unit Quantity Engineer's Estimate SCOUT 5 CONSTRUCTION LLC GARRET SHIELDS INFRASTRUCTURE RISE UP CONSTRUCTION LLC SCOTT TUCKER CONSTRUCTION COMPANY, LLC IBCTX, LLC
100 6001 PREPARING ROW AC 0.400 $12,500.000 $0.010 $10,000.000 $5,000.000 $17,454.000 $50,000.000
104 6009 REMOVING CONC (RIPRAP) SY 622.000 $30.000 $75.000 $40.000 $37.000 $24.000 $15.000
104 6021 REMOVING CONC (CURB) LF 12.000 $15.000 $100.000 $20.000 $37.000 $70.000 $100.000
104 6044 REMOVING CONC (FLUME) SY 22.000 $40.000 $200.000 $50.000 $37.000 $112.000 $200.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 14.000 $15.000 $50.000 $50.000 $37.000 $113.000 $100.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 60.000 $100.000 $120.000 $100.000 $55.000 $268.000 $225.000
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 273.000 $3.000 $0.010 $1.000 $2.000 $4.000 $4.000
168 6001 VEGETATIVE WATERING MG 41.000 $40.000 $0.010 $50.000 $123.000 $147.000 $75.000
432 6001 RIPRAP (CONC)(4 IN) CY 86.000 $650.000 $500.000 $700.000 $656.000 $749.000 $1,400.000
432 6044 RIPRAP (CONC)(FLUME) CY 5.000 $1,300.000 $900.000 $1,000.000 $1,500.000 $3,281.000 $1,400.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 1.000 $1,000.000 $400.000 $1,000.000 $1,500.000 $10,019.000 $2,000.000
438 6004 CLEANING AND SEALING EXIST JOINTS(CL7) LF 114.000 $55.000 $60.000 $80.000 $45.000 $83.000 $50.000
500 6001 MOBILIZATION LS 1.000 $15,000.000 $7,000.000 $10,000.000 $15,000.000 $22,428.000 $26,900.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $5,500.000 $0.010 $5,000.000 $3,454.000 $11,512.000 $15,000.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 112.000 $20.000 $0.010 $5.000 $12.000 $51.000 $72.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 112.000 $5.000 $0.010 $5.000 $12.000 $32.000 $36.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 44.000 $10.000 $0.010 $4.000 $12.000 $11.000 $24.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 44.000 $2.000 $0.010 $2.000 $12.000 $8.000 $12.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 1.000 $3,000.000 $3,500.000 $5,000.000 $3,000.000 $6,029.000 $4,500.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 1.000 $400.000 $0.010 $500.000 $4,500.000 $1,045.000 $1,000.000
658 6115 INS DEL ASSM(D-SW)SZ 1(WFLX)GF2 EA 1.000 $100.000 $0.010 $50.000 $56.000 $37.000 $350.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $8,000.000 $5,000.000 $1,000.000 $3,400.000 $2,530.000 $1,500.000
6185 6002 TMA (STATIONARY) DAY 15.000 $250.000 $100.000 $300.000 $500.000 $417.000 $75.000
Totals: $155,637.00 $136,896.30 $147,997.00 $153,733.00 $224,304.60 $269,652.00