Show Job Controls
Bid Cobra

WILLIAMSON US 79 (0204-01-074)

Items: 23

County: WILLIAMSON
Length: N/A
Highway: US 79
District: AUSTIN
Control Number: 0204-01-074
DBE Goal: 0.0%
Project: STP 2024(756)HES
Guaranty: N/A
Time: 368 WORKING DAYS
Engineer's Estimate: $4,943,516.45
Date: 02/02/2024 (2 years ago)
Contract Number: N/A
Type: INSTALLATION OF MEDIAN CABLE BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$4,943,516.45
$3,597,980.30
Over/Under Est: -27.22% -$1,345,536.15
Over/Under Est: -19.73% -$975,352.20
Amt Left: 10.29% $370,183.95
$4,312,745.65
Over/Under Est: -12.76% -$630,770.80
Amt Left: 19.87% $714,765.35
Delta: -8.68% -$344,581.40
Over/Under Est: -8.34% -$412,395.45
Amt Left: 25.94% $933,140.70
Delta: -5.06% -$218,375.35
Over/Under Est: 0.87% $43,050.86
Amt Left: 38.59% $1,388,587.01
Delta: -10.05% -$455,446.31
$6,773,700.50
Over/Under Est: 37.02% $1,830,184.05
Amt Left: 88.26% $3,175,720.20
Delta: -35.84% -$1,787,133.19
Subcontractor Percentage Amount
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 4.48% $161,189.52
Total: 4.48% $161,189.52

Bid Items & Bid Tabulations

23 Total 0 of 23
WILLIAMSON  |  US 79  |  AUSTIN  |  0204-01-074  |  02/02/2024  |  $4,943,516.45  |  STP 2024(756)HES  |  INSTL OF MEDIAN CABLE BARRIER  |  368 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
GRATIOT CONSTRUCTION, LTD.
MIJELUM, L.L.C.
MASSANA CONSTRUCTION INC.
SCR CIVIL CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 125.000 $100.000 $20.000 $60.000 $50.000 $65.000 $146.000 $60.000
BACKFILL (TY A)
STA 100.000 $165.000 $215.000 $250.000 $20.000 $425.000 $1,079.000 $450.000
BLADING
STA 1,056.000 $150.000 $55.000 $0.010 $150.000 $75.000 $76.000 $250.000
FURNISHING AND PLACING TOPSOIL (4")
SY 103,726.000 $2.500 $0.750 $0.010 $0.800 $1.100 $2.600 $6.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 51,876.000 $0.400 $0.300 $0.450 $0.300 $0.450 $0.340 $0.500
CELL FBR MLCH SEED(TEMP)(COOL)
SY 51,876.000 $0.400 $0.300 $0.450 $0.300 $0.450 $0.340 $0.500
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 102,825.000 $0.250 $0.200 $0.180 $0.350 $0.200 $0.230 $0.500
VEGETATIVE WATERING
MG 1,775.000 $30.000 $5.000 $10.000 $10.000 $70.500 $34.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 103,726.000 $1.150 $0.700 $1.250 $0.500 $1.250 $0.800 $3.000
RIPRAP (MOW STRIP)(4 IN)
CY 3,871.000 $475.000 $329.500 $468.000 $500.000 $375.000 $532.000 $485.000
MOBILIZATION
LS 1.000 $485,000.000 $355,550.000 $575,000.000 $400,000.000 $485,685.000 $281,500.000 $650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 23.000 $5,000.000 $4,000.000 $1.000 $4,000.000 $7,500.000 $3,675.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 750.000 $6.000 $4.000 $4.250 $20.000 $4.250 $4.570 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 750.000 $2.000 $1.000 $1.000 $0.100 $1.000 $1.150 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 3,050.000 $6.750 $4.000 $4.500 $20.000 $4.500 $4.570 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,050.000 $1.500 $1.000 $1.250 $0.050 $1.250 $1.150 $9.000
CABLE BARRIER SYSTEM (TL-4)
LF 102,506.000 $12.000 $11.250 $9.550 $10.000 $14.000 $13.080 $15.500
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 122.000 $3,200.000 $2,450.000 $2,350.000 $2,000.000 $2,500.000 $2,340.000 $4,500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 50.000 $575.000 $565.000 $380.000 $200.000 $350.000 $435.000 $1,500.000
RELOCATE SM RD SN SUP&AM TY S80
EA 50.000 $840.000 $617.500 $500.000 $200.000 $350.000 $572.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 50.000 $150.000 $105.000 $85.000 $200.000 $300.000 $100.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $6,650.000 $4,500.000 $0.010 $10,000.000 $2,500.000 $9,620.000 $16,500.000
TMA (STATIONARY)
DAY 368.000 $150.000 $65.000 $0.010 $200.000 $85.000 $357.000 $250.000
Totals: $4,943,516.450 $3,597,980.300 $3,968,164.250 $4,312,745.650 $4,531,121.000 $4,986,567.310 $6,773,700.500