WASHINGTON US 290 (0114-10-108)
Items: 27
County: WASHINGTON
Length: 0.0000 MILES
Highway: US 290
District: BRYAN
Control Number: 0114-10-108
DBE Goal: 0.0%
Project: F 2025(700)
Guaranty: $100,000.00
Time: 97 WORKING DAYS
Engineer's Estimate: $6,122,428.62
Date: 04/08/2026 (2 months ago)
Contract Number: 4263215
Type: MILL AND INLAY
Project ID: A00200748
Contract Type: Federal
Project Description: MILL AND INLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JEFF MILES
RENE PEQUENO
WASHINGTON US 290 (0114-10-108)
Project Name: N/A
Project: F 2025(700)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 1.3 MI E OF FM 577
Limits To: 3 MI E OF FM 1371 (BRAZOS RIVER BRIDGE)
Project Description: MILL AND INLAY
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,122,428.62 | |||
| $6,537,277.77 |
6.78%
$414,849.15
|
|||
| $6,715,625.12 |
9.69%
$593,196.50
|
2.73%
$178,347.35
|
||
| $6,985,960.00 |
14.1%
$863,531.38
|
6.86%
$448,682.23
|
-4.03%
-$270,334.88
|
|
| $7,061,411.59 |
15.34%
$938,982.97
|
8.02%
$524,133.82
|
-1.08%
-$75,451.59
|
|
| $7,193,900.44 |
17.5%
$1,071,471.82
|
10.04%
$656,622.67
|
-1.88%
-$132,488.85
|
|
| $7,656,043.40 |
25.05%
$1,533,614.78
|
17.11%
$1,118,765.63
|
-6.42%
-$462,142.96
|
|
| $7,990,312.60 |
30.51%
$1,867,883.98
|
22.23%
$1,453,034.83
|
-4.37%
-$334,269.20
|
E
Engineer's Estimate
$6,122,428.62
1
Awarded
$6,537,277.77
Over/Under Est:
6.78%
$414,849.15
$6,715,625.12
Over/Under Est:
9.69%
$593,196.50
Amt Left:
2.73%
$178,347.35
$6,985,960.00
Over/Under Est:
14.1%
$863,531.38
Amt Left:
6.86%
$448,682.23
Delta:
-4.03%
-$270,334.88
$7,061,411.59
Over/Under Est:
15.34%
$938,982.97
Amt Left:
8.02%
$524,133.82
Delta:
-1.08%
-$75,451.59
$7,193,900.44
Over/Under Est:
17.5%
$1,071,471.82
Amt Left:
10.04%
$656,622.67
Delta:
-1.88%
-$132,488.85
$7,656,043.40
Over/Under Est:
25.05%
$1,533,614.78
Amt Left:
17.11%
$1,118,765.63
Delta:
-6.42%
-$462,142.96
$7,990,312.60
Over/Under Est:
30.51%
$1,867,883.98
Amt Left:
22.23%
$1,453,034.83
Delta:
-4.37%
-$334,269.20
Bid Items & Bid Tabulations
27
Total
0 of 27
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $120,000.00 |
| Total: | $126,000.00 |