TITUS CR (0919-30-062)

Items: 44

County: TITUS
Length: N/A
Highway: CR
District: ATLANTA
Control Number: 0919-30-062
DBE Goal: N/A
Project: BR 2019(354)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $653,809.75
Date: 07/02/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (5)
E
Engineer's Estimate
$653,809.75
Over/Under Est: -14.59% -$95,409.75
$593,811.25
Over/Under Est: -9.18% -$59,998.50
Amt Left: 6.34% $35,411.25
Over/Under Est: -1.14% -$7,472.99
Amt Left: 15.75% $87,936.76
Delta: -8.85% -$52,525.51
Over/Under Est: 7.84% $51,266.75
Amt Left: 26.27% $146,676.50
Delta: -9.09% -$58,739.74
Over/Under Est: 29.23% $191,140.30
Amt Left: 51.32% $286,550.05
Delta: -19.84% -$139,873.55

Bid Items & Bid Tabulations

44 Total 0 of 44
TITUS  |  CR  |  ATLANTA  |  0919-30-062  |  07/02/2021  |  $653,809.75  |  BR 2019(354)  |  BRIDGE REPL  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
CDM HOLDINGS, LLC
HIGHWAY 19 CONSTRUCTION LLC
EAST TEXAS BRIDGE, INC.
DIGG COMMERCIAL, LLC
PREPARING ROW
STA 5.300 $3,000.000 $1,900.000 $2,800.000 $5,000.000 $3,700.000 $4,442.000
REMOVING STAB BASE AND ASPH PAV (3")
SY 886.000 $4.250 $3.000 $5.000 $5.560 $5.000 $16.000
EXCAVATION (ROADWAY)
CY 628.000 $9.000 $15.000 $8.000 $5.000 $20.000 $48.000
EXCAVATION (CHANNEL)
CY 737.000 $10.000 $15.000 $19.000 $5.000 $20.000 $52.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 624.000 $23.000 $20.000 $7.000 $35.000 $25.000 $58.000
FURNISHING AND PLACING TOPSOIL (4")
SY 3,575.000 $2.000 $2.000 $4.000 $0.790 $3.000 $6.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 3,575.000 $1.000 $1.000 $1.750 $0.790 $0.900 $1.170
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 1,790.000 $1.000 $0.500 $0.050 $0.640 $0.800 $1.340
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 1,790.000 $1.000 $0.500 $0.500 $1.200 $0.800 $1.350
VEGETATIVE WATERING
MG 170.000 $7.000 $1.000 $7.000 $100.000 $12.000 $24.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 1,450.000 $1.350 $2.000 $1.750 $3.200 $1.500 $6.000
CEMENT
TON 20.000 $200.000 $200.000 $220.000 $180.000 $275.000 $250.000
CEMENT TREAT (SUBGRADE)(6")
SY 1,229.000 $6.250 $6.000 $5.000 $10.000 $6.000 $14.000
PRIME COAT (MC-30)
GAL 310.000 $4.500 $8.000 $7.000 $10.000 $8.000 $6.000
CEM STABIL BKFL
CY 31.000 $225.000 $200.000 $270.000 $180.000 $275.000 $190.000
DRILL SHAFT (30 IN)
LF 240.000 $250.000 $130.000 $205.000 $200.000 $200.000 $165.000
CL C CONC (ABUT)(HPC)
CY 25.200 $1,000.000 $1,000.000 $1,115.000 $1,100.000 $1,350.000 $1,600.000
REINF CONC SLAB (BOX BEAM)(HPC)
SF 1,701.000 $20.000 $18.000 $23.000 $21.000 $25.000 $40.000
APPROACH SLAB
CY 38.500 $550.000 $600.000 $550.000 $600.000 $700.000 $1,100.000
SHEAR KEY
CY 8.600 $325.000 $500.000 $365.000 $400.000 $700.000 $976.000
PRESTR CONC BOX BEAM (4B20)
LF 258.000 $200.000 $230.000 $250.000 $260.000 $285.000 $195.000
PRESTR CONC BOX BEAM (5B20)
LF 129.000 $205.000 $230.000 $250.000 $260.000 $285.000 $202.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 415.000 $200.000 $100.000 $125.000 $150.000 $140.000 $150.000
BEDDING MATERIAL (6 IN)
CY 92.000 $200.000 $80.000 $142.000 $100.000 $140.000 $166.000
RAIL (TY T223)(HPC)
LF 162.000 $125.000 $120.000 $132.000 $150.000 $125.000 $196.000
ARMOR JOINT
LF 24.000 $65.000 $100.000 $180.000 $180.000 $100.000 $184.000
ARMOR JOINT (SEALED)
LF 44.300 $95.000 $100.000 $140.000 $200.000 $125.000 $170.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $20,000.000 $15,000.000 $5,000.000 $10,000.000 $15,000.000 $29,312.000
MOBILIZATION
LS 1.000 $64,000.000 $50,000.000 $46,000.000 $50,000.000 $70,000.000 $45,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,000.000 $3,000.000 $2,000.000 $1,000.000 $2,700.000 $5,400.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 110.000 $39.000 $10.000 $39.000 $36.550 $35.000 $60.000
ROCK FILTER DAMS (REMOVE)
LF 110.000 $10.000 $5.000 $12.500 $10.000 $10.000 $5.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,445.000 $3.000 $1.000 $3.450 $3.000 $3.300 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,445.000 $1.100 $1.000 $0.950 $1.000 $1.000 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 475.000 $21.500 $25.000 $30.000 $27.400 $26.000 $35.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,425.000 $1,100.000 $1,365.000 $1,200.000 $1,100.000 $1,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,300.000 $1,200.000 $1,490.000 $1,375.000 $1,200.000 $3,000.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 2.000 $2,900.000 $2,800.000 $3,415.000 $2,750.000 $3,000.000 $2,800.000
WIRE FENCE (TY C)
LF 1,175.000 $14.000 $15.000 $10.000 $15.000 $27.000 $7.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $23.000 $30.000 $20.000 $26.000 $30.000 $100.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $30.000 $30.000 $50.000 $10.000 $20.000 $102.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 4.000 $40.000 $30.000 $45.000 $45.000 $35.000 $120.000
ASPHALT-STABILIZED FLEXIBLE BASE
TON 408.000 $120.000 $160.000 $125.000 $150.000 $130.000 $150.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 1.000 $250.000 $500.000 $750.000 $500.000 $1,000.000 $670.000
Totals: $653,809.750 $558,400.000 $593,811.250 $646,336.760 $705,076.500 $844,950.050