PREPARING ROW
|
STA
|
233.000
|
$1,207.000
|
$3,000.000
|
$8,000.000
|
$6,500.000
|
$8,000.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
2,013.000
|
$28.000
|
$5.000
|
$7.000
|
$19.000
|
$11.250
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
400.000
|
$5.580
|
$10.000
|
$15.000
|
$35.000
|
$22.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2")
|
SY
|
7,770.000
|
$3.670
|
$3.000
|
$6.000
|
$5.000
|
$4.600
|
|
|
REMOVING STAB BASE AND ASPH PAV (5")
|
SY
|
6,792.000
|
$5.380
|
$10.000
|
$12.000
|
$6.000
|
$5.300
|
|
|
REMOVING STAB BASE & ASPH PAV (8"-14")
|
SY
|
37,486.000
|
$5.610
|
$5.000
|
$13.000
|
$7.000
|
$5.750
|
|
|
REMOVING STAB BASE & ASPH PAV (18")
|
SY
|
41,715.000
|
$5.340
|
$7.000
|
$15.000
|
$10.000
|
$9.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
346,053.000
|
$8.000
|
$6.320
|
$7.500
|
$9.000
|
$7.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
142,031.000
|
$9.250
|
$7.680
|
$10.000
|
$6.000
|
$8.000
|
|
|
ROAD GRADER WORK (ORD COMP)
|
STA
|
220.000
|
$163.000
|
$250.000
|
$250.000
|
$900.000
|
$100.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
241,592.000
|
$1.500
|
$1.000
|
$1.000
|
$0.900
|
$2.100
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
146,718.000
|
$0.250
|
$0.140
|
$0.090
|
$0.100
|
$0.160
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
241,592.000
|
$0.700
|
$0.140
|
$0.660
|
$0.650
|
$1.320
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
146,718.000
|
$0.700
|
$0.730
|
$0.660
|
$0.630
|
$1.320
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
146,718.000
|
$0.700
|
$0.720
|
$0.650
|
$0.630
|
$1.320
|
|
|
VEGETATIVE WATERING
|
MG
|
2,658.000
|
$10.000
|
$20.000
|
$8.000
|
$25.000
|
$43.000
|
|
|
FL BS (CMP IN PLACE)(TY A GR 1-2)(12")
|
SY
|
136,590.000
|
$13.500
|
$22.150
|
$20.000
|
$31.000
|
$32.000
|
|
|
LIME (QUICKLIME (DRY))
|
TON
|
1,389.000
|
$159.600
|
$268.000
|
$350.000
|
$250.000
|
$307.500
|
|
|
LIME TRT (SUBGRADE)(8")
|
SY
|
77,167.000
|
$10.250
|
$3.250
|
$3.500
|
$3.600
|
$3.000
|
|
|
CEMENT
|
TON
|
1,389.000
|
$152.000
|
$190.000
|
$265.000
|
$240.000
|
$288.600
|
|
|
CEMENT TREAT (EXIST MATL) (10")
|
SY
|
17,882.000
|
$2.000
|
$3.500
|
$8.000
|
$3.600
|
$4.400
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
77,167.000
|
$4.000
|
$6.800
|
$3.000
|
$3.600
|
$4.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
28,909.000
|
$5.000
|
$5.500
|
$6.000
|
$5.500
|
$6.850
|
|
|
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
|
GAL
|
119,149.000
|
$3.250
|
$5.040
|
$4.500
|
$5.000
|
$5.900
|
|
|
AGGR (TY-PD GR-3 OR TY-PL GR-3)
|
CY
|
2,837.000
|
$111.000
|
$150.000
|
$115.000
|
$175.000
|
$179.000
|
|
|
CEM STABIL BKFL
|
CY
|
989.000
|
$289.000
|
$250.000
|
$200.000
|
$290.000
|
$255.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
1,875.000
|
$166.000
|
$250.000
|
$140.000
|
$160.000
|
$138.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
4,621.000
|
$23.250
|
$55.000
|
$50.000
|
$40.000
|
$80.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
5,310.000
|
$340.000
|
$280.000
|
$220.000
|
$212.000
|
$238.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
798.000
|
$240.000
|
$500.000
|
$300.000
|
$270.000
|
$335.000
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
540.000
|
$308.000
|
$570.000
|
$360.000
|
$350.000
|
$424.000
|
|
|
DRILL SHAFT (54 IN)
|
LF
|
504.000
|
$395.000
|
$719.000
|
$480.000
|
$405.000
|
$539.000
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
24.000
|
$205.000
|
$350.000
|
$230.000
|
$220.000
|
$220.000
|
|
|
DRILL SHAFT (SIGN MTS) (30 IN)
|
LF
|
22.600
|
$236.000
|
$350.000
|
$250.000
|
$260.000
|
$330.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
13.000
|
$214.000
|
$250.000
|
$300.000
|
$260.000
|
$275.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (48 IN)
|
LF
|
22.000
|
$682.000
|
$850.000
|
$1,000.000
|
$900.000
|
$935.000
|
|
|
CL C CONC (ABUT)
|
CY
|
236.200
|
$935.000
|
$1,350.000
|
$1,200.000
|
$1,300.000
|
$1,140.000
|
|
|
CL C CONC (ABUT)(EXTEND)
|
CY
|
126.800
|
$1,269.000
|
$1,700.000
|
$1,200.000
|
$1,500.000
|
$1,240.000
|
|
|
CL C CONC (BENT)
|
CY
|
233.400
|
$1,126.000
|
$1,550.000
|
$1,200.000
|
$1,400.000
|
$1,195.000
|
|
|
CL C CONC (CAP)
|
CY
|
317.850
|
$1,000.000
|
$1,750.000
|
$1,200.000
|
$1,600.000
|
$1,145.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
478.500
|
$1,000.000
|
$1,100.000
|
$1,200.000
|
$1,200.000
|
$1,115.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
2.000
|
$991.000
|
$1,500.000
|
$1,500.000
|
$1,600.000
|
$2,500.000
|
|
|
REINF CONC SLAB
|
SF
|
88,340.000
|
$22.000
|
$28.000
|
$27.000
|
$24.000
|
$25.000
|
|
|
REINF CONC SLAB (EXTEND SLAB)
|
SF
|
16,420.000
|
$27.000
|
$35.000
|
$27.000
|
$26.000
|
$28.000
|
|
|
APPROACH SLAB
|
CY
|
342.500
|
$435.000
|
$600.000
|
$750.000
|
$700.000
|
$800.000
|
|
|
APPROACH SLAB (EXTEND)
|
CY
|
199.200
|
$538.000
|
$750.000
|
$750.000
|
$750.000
|
$834.000
|
|
|
RETAINING WALL (TEMP WALL)
|
SF
|
3,356.000
|
$16.000
|
$60.000
|
$35.000
|
$50.000
|
$27.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
3,860.000
|
$158.000
|
$235.000
|
$200.000
|
$210.000
|
$170.000
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
8,758.000
|
$137.000
|
$224.000
|
$230.000
|
$220.000
|
$226.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
63.000
|
$595.000
|
$750.000
|
$900.000
|
$680.000
|
$732.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
12.000
|
$525.000
|
$700.000
|
$1,200.000
|
$800.000
|
$840.000
|
|
|
RIPRAP (STONE TY R)(DRY)(12 IN)
|
CY
|
308.000
|
$229.000
|
$180.000
|
$275.000
|
$130.000
|
$185.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
1,484.000
|
$113.000
|
$150.000
|
$200.000
|
$145.000
|
$228.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
694.000
|
$105.000
|
$180.000
|
$200.000
|
$150.000
|
$250.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
249.000
|
$470.000
|
$550.000
|
$750.000
|
$620.000
|
$660.000
|
|
|
RAIL (TY T223)
|
LF
|
908.000
|
$110.000
|
$150.000
|
$115.000
|
$130.000
|
$152.000
|
|
|
RAIL (TY C221)
|
LF
|
1,648.000
|
$76.000
|
$140.000
|
$180.000
|
$125.000
|
$150.000
|
|
|
RAIL (TY PR22)
|
LF
|
1,600.000
|
$105.000
|
$185.000
|
$180.000
|
$150.000
|
$168.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
480.000
|
$95.000
|
$180.000
|
$115.000
|
$130.000
|
$131.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
360.000
|
$97.000
|
$180.000
|
$230.000
|
$140.000
|
$239.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
50.000
|
$63.500
|
$55.000
|
$65.000
|
$110.000
|
$88.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
101.000
|
$227.000
|
$335.000
|
$400.000
|
$450.000
|
$336.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)
|
LF
|
140.000
|
$203.000
|
$341.000
|
$425.000
|
$480.000
|
$371.000
|
|
|
CONC BOX CULV (5 FT X 3 FT)
|
LF
|
517.000
|
$336.000
|
$450.000
|
$540.000
|
$640.000
|
$495.000
|
|
|
CONC BOX CULV (6 FT X 4 FT)
|
LF
|
157.000
|
$296.000
|
$615.000
|
$760.000
|
$870.000
|
$710.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
2,836.000
|
$37.750
|
$55.000
|
$55.000
|
$53.000
|
$48.760
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
2,989.000
|
$51.000
|
$75.000
|
$70.000
|
$100.000
|
$86.150
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
682.000
|
$99.000
|
$86.000
|
$115.000
|
$150.000
|
$165.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
469.000
|
$101.250
|
$130.000
|
$165.000
|
$200.000
|
$216.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
108.000
|
$370.000
|
$220.000
|
$200.000
|
$240.000
|
$296.500
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
135.000
|
$288.000
|
$280.000
|
$250.000
|
$320.000
|
$332.500
|
|
|
RC PIPE (ELLIP)(CL III)(DES 1)
|
LF
|
72.000
|
$77.000
|
$150.000
|
$250.000
|
$480.000
|
$489.350
|
|
|
MANH (COMPL)(PRM)(72IN)
|
EA
|
6.000
|
$5,877.000
|
$9,000.000
|
$15,000.000
|
$11,000.000
|
$18,270.000
|
|
|
JCTBOX(COMPL)(PJB)(4FTX4FT)
|
EA
|
5.000
|
$4,552.000
|
$6,000.000
|
$10,000.000
|
$7,400.000
|
$10,750.000
|
|
|
JCTBOX(COMPL)(PJB)(6FTX6FT)
|
EA
|
1.000
|
$7,558.000
|
$7,000.000
|
$12,000.000
|
$9,000.000
|
$13,700.000
|
|
|
JCTBOX(COMPL)(PJB)(8FTX8FT)
|
EA
|
1.000
|
$13,824.000
|
$11,500.000
|
$18,000.000
|
$13,000.000
|
$20,410.000
|
|
|
INLET (COMPL)(PCO)(3FT)(NONE)
|
EA
|
2.000
|
$4,173.000
|
$5,000.000
|
$8,000.000
|
$5,300.000
|
$7,015.000
|
|
|
INLET (COMPL)(PCO)(3FT)(RIGHT)
|
EA
|
1.000
|
$4,770.000
|
$5,000.000
|
$8,600.000
|
$5,800.000
|
$7,950.000
|
|
|
INLET (COMPL)(PCO)(3FT)(BOTH)
|
EA
|
5.000
|
$5,700.000
|
$6,000.000
|
$9,500.000
|
$6,800.000
|
$10,215.000
|
|
|
INLET (COMPL)(PCO)(5FT)(NONE)
|
EA
|
2.000
|
$5,258.000
|
$5,000.000
|
$9,000.000
|
$5,300.000
|
$7,970.000
|
|
|
INLET (COMPL)(PCO)(5FT)(LEFT)
|
EA
|
1.000
|
$5,437.000
|
$8,000.000
|
$12,000.000
|
$8,500.000
|
$11,650.000
|
|
|
INLET (COMPL)(PCO)(5FT)(RIGHT)
|
EA
|
1.000
|
$5,523.000
|
$6,000.000
|
$10,000.000
|
$5,800.000
|
$8,890.000
|
|
|
INLET (COMPL)(PCO)(5FT)(BOTH)
|
EA
|
8.000
|
$6,660.000
|
$6,500.000
|
$11,000.000
|
$8,000.000
|
$11,170.000
|
|
|
INLET (COMPL)(PCO)(6FT)(LEFT)
|
EA
|
1.000
|
$5,816.000
|
$6,000.000
|
$11,000.000
|
$7,000.000
|
$9,370.000
|
|
|
INLET (COMPL)(PCO)(6FT)(BOTH)
|
EA
|
5.000
|
$8,522.000
|
$7,000.000
|
$11,000.000
|
$8,000.000
|
$11,650.000
|
|
|
INLET(COMPL)(PSL)(SFG)(4FTX4FT-4FTX4FT)
|
EA
|
2.000
|
$5,321.000
|
$5,500.000
|
$10,000.000
|
$6,500.000
|
$9,740.000
|
|
|
INLET (COMPL)(PAZD)(RC)(4FTX4FT)
|
EA
|
1.000
|
$5,768.000
|
$4,500.000
|
$8,000.000
|
$6,500.000
|
$8,650.000
|
|
|
INLET (COMPL)(PAZD)(RC)(5FTX5FT)
|
EA
|
1.000
|
$7,466.000
|
$5,000.000
|
$8,000.000
|
$5,800.000
|
$9,125.000
|
|
|
INLET (COMPL)(CURB)(TY C)
|
EA
|
9.000
|
$3,612.000
|
$5,000.000
|
$8,500.000
|
$10,000.000
|
$11,100.000
|
|
|
INLET (COMPL)(EXT TY C)
|
EA
|
3.000
|
$1,549.000
|
$4,000.000
|
$5,000.000
|
$4,800.000
|
$5,100.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 24 IN)
|
EA
|
2.000
|
$3,975.000
|
$4,000.000
|
$6,500.000
|
$3,700.000
|
$5,500.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 36 IN)
|
EA
|
4.000
|
$6,550.000
|
$7,500.000
|
$7,500.000
|
$5,800.000
|
$10,360.000
|
|
|
HEADWALL (CH - FW - 15) (DIA= 42 IN)
|
EA
|
2.000
|
$6,948.000
|
$8,500.000
|
$7,500.000
|
$10,000.000
|
$10,450.000
|
|
|
HEADWALL (CH - FW - 30) (DIA= 48 IN)
|
EA
|
2.000
|
$15,000.000
|
$9,000.000
|
$10,000.000
|
$13,000.000
|
$17,200.000
|
|
|
WINGWALL (FW - S) (HW=4 FT)
|
EA
|
4.000
|
$8,385.000
|
$7,500.000
|
$9,000.000
|
$11,000.000
|
$13,450.000
|
|
|
WINGWALL (FW - S) (HW=5 FT)
|
EA
|
2.000
|
$5,800.000
|
$6,000.000
|
$12,000.000
|
$14,000.000
|
$18,100.000
|
|
|
SET (TY I) (30 IN) (3: 1) (C)
|
EA
|
4.000
|
$13,500.000
|
$6,500.000
|
$6,000.000
|
$8,000.000
|
$17,600.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
72.000
|
$573.000
|
$850.000
|
$750.000
|
$900.000
|
$840.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
11.000
|
$835.000
|
$1,100.000
|
$950.000
|
$950.000
|
$1,065.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
18.000
|
$889.000
|
$1,250.000
|
$1,200.000
|
$1,000.000
|
$1,250.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (C)
|
EA
|
6.000
|
$7,000.000
|
$1,350.000
|
$1,300.000
|
$2,600.000
|
$1,560.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
7.000
|
$1,900.000
|
$1,900.000
|
$1,500.000
|
$3,200.000
|
$1,720.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$3,925.000
|
$4,587.000
|
$5,300.000
|
$4,300.000
|
$6,250.000
|
|
|
REMOV STR (INLET)
|
EA
|
8.000
|
$617.000
|
$1,000.000
|
$800.000
|
$900.000
|
$500.000
|
|
|
REMOV STR (MANHOLE)
|
EA
|
1.000
|
$487.000
|
$1,000.000
|
$2,000.000
|
$900.000
|
$1,925.000
|
|
|
REMOV STR (SET)
|
EA
|
5.000
|
$377.000
|
$500.000
|
$800.000
|
$800.000
|
$385.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
38.000
|
$710.000
|
$500.000
|
$800.000
|
$1,600.000
|
$1,100.000
|
|
|
REMOV STR (PIPE)
|
LF
|
2,506.000
|
$30.000
|
$10.000
|
$15.000
|
$36.000
|
$20.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
288.000
|
$59.000
|
$75.000
|
$75.000
|
$220.000
|
$105.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$9,917.000
|
$50,000.000
|
$30,000.000
|
$47,000.000
|
$50,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$3,209,645.200
|
$3,600,000.000
|
$3,000,000.000
|
$4,350,000.000
|
$2,600,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
24.000
|
$9,737.540
|
$1,600.000
|
$10,000.000
|
$15,000.000
|
$4,700.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
4,457.000
|
$27.000
|
$29.000
|
$33.000
|
$31.000
|
$29.700
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,338.000
|
$31.000
|
$32.000
|
$38.000
|
$35.000
|
$34.100
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
5,795.000
|
$8.750
|
$8.000
|
$8.000
|
$7.500
|
$8.800
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
889.000
|
$18.000
|
$20.000
|
$28.000
|
$20.000
|
$29.700
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
889.000
|
$12.000
|
$5.000
|
$8.000
|
$4.000
|
$8.800
|
|
|
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
|
CY
|
2,500.000
|
$40.000
|
$50.000
|
$15.000
|
$16.000
|
$30.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
500.000
|
$76.000
|
$50.000
|
$30.000
|
$80.000
|
$136.000
|
|
|
BULLDOZER WORK (EROSION & SEDMT CONT)
|
HR
|
200.000
|
$141.000
|
$100.000
|
$30.000
|
$150.000
|
$136.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
35,719.000
|
$2.750
|
$2.500
|
$3.600
|
$3.200
|
$3.250
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
35,719.000
|
$1.000
|
$0.500
|
$0.500
|
$0.600
|
$0.550
|
|
|
TRACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
200.000
|
$96.500
|
$50.000
|
$50.000
|
$160.000
|
$250.000
|
|
|
TEMP SDMT CONT FENCE (INLET PROTECTION)
|
LF
|
522.000
|
$5.500
|
$10.000
|
$10.000
|
$8.000
|
$6.600
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
5,700.000
|
$33.000
|
$75.000
|
$75.000
|
$75.000
|
$86.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
1,780.000
|
$100.000
|
$85.000
|
$85.000
|
$75.000
|
$100.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
160.000
|
$100.000
|
$90.000
|
$85.000
|
$75.000
|
$95.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
5,580.000
|
$5.000
|
$20.000
|
$8.000
|
$15.000
|
$11.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
3,220.000
|
$10.000
|
$20.000
|
$8.000
|
$30.000
|
$9.500
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$10.000
|
$20.000
|
$8.000
|
$30.000
|
$11.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
5,700.000
|
$8.000
|
$20.000
|
$5.000
|
$20.000
|
$11.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
1,780.000
|
$10.000
|
$20.000
|
$5.000
|
$20.000
|
$11.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
160.000
|
$10.000
|
$20.000
|
$5.000
|
$20.000
|
$12.500
|
|
|
COLORED TEXTURED CONC (5")
|
SY
|
52.000
|
$73.000
|
$150.000
|
$300.000
|
$160.000
|
$205.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
17,889.000
|
$27.000
|
$35.000
|
$47.000
|
$46.000
|
$28.500
|
|
|
INTERSECTIONS (ACP)
|
SY
|
14,250.000
|
$38.500
|
$60.250
|
$70.000
|
$62.000
|
$112.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
6,055.000
|
$34.000
|
$71.850
|
$65.000
|
$62.000
|
$57.500
|
|
|
DRIVEWAYS (BASE)
|
SY
|
866.000
|
$20.000
|
$35.000
|
$25.000
|
$85.000
|
$51.800
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
2,924.000
|
$91.000
|
$95.000
|
$130.000
|
$160.000
|
$110.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
11,127.000
|
$51.000
|
$70.000
|
$65.000
|
$95.000
|
$64.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
3.000
|
$1,763.000
|
$1,100.000
|
$3,000.000
|
$3,200.000
|
$3,195.000
|
|
|
CURB RAMPS (TY 2)
|
EA
|
16.000
|
$1,973.000
|
$2,500.000
|
$3,000.000
|
$3,200.000
|
$4,635.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
18.000
|
$1,959.000
|
$1,150.000
|
$3,000.000
|
$3,200.000
|
$4,600.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
1.000
|
$2,340.000
|
$1,800.000
|
$3,000.000
|
$3,200.000
|
$5,175.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
2,712.500
|
$20.250
|
$24.020
|
$26.000
|
$25.000
|
$26.420
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
16.000
|
$1,529.000
|
$1,800.000
|
$2,000.000
|
$2,200.000
|
$1,925.000
|
|
|
SHORT RADIUS
|
LF
|
24.000
|
$24.000
|
$45.000
|
$50.000
|
$27.000
|
$49.500
|
|
|
DRIVEWAY TERMINAL ANCHOR SECTION
|
EA
|
1.000
|
$823.000
|
$1,800.000
|
$1,300.000
|
$670.000
|
$1,292.500
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
7.000
|
$1,105.000
|
$1,500.000
|
$1,600.000
|
$1,200.000
|
$1,595.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
300.000
|
$2.200
|
$3.000
|
$4.000
|
$3.500
|
$3.300
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
10.000
|
$2,643.000
|
$2,800.000
|
$3,000.000
|
$3,100.000
|
$3,025.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$248.000
|
$200.000
|
$250.000
|
$325.000
|
$220.000
|
|
|
CRASH CUSH ATTEN (DES SOURCE)
|
EA
|
16.000
|
$15,000.000
|
$2,500.000
|
$3,000.000
|
$3,600.000
|
$2,750.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
12.000
|
$1,191.000
|
$2,500.000
|
$3,000.000
|
$1,600.000
|
$2,750.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
16.000
|
$870.000
|
$1,000.000
|
$1,200.000
|
$1,600.000
|
$1,100.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
30.000
|
$282.000
|
$350.000
|
$300.000
|
$290.000
|
$297.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
7.000
|
$308.000
|
$450.000
|
$330.000
|
$310.000
|
$319.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 2
|
EA
|
7.000
|
$458.000
|
$450.000
|
$600.000
|
$550.000
|
$572.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
233.000
|
$6.000
|
$12.000
|
$14.000
|
$13.000
|
$13.200
|
|
|
CONDT (PVC) (SCH 40) (4") (BORE)
|
LF
|
222.000
|
$30.000
|
$35.000
|
$38.000
|
$37.000
|
$38.500
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
590.000
|
$1.750
|
$2.000
|
$2.000
|
$2.000
|
$1.980
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
25.000
|
$2.250
|
$1.500
|
$2.000
|
$0.400
|
$1.650
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
50.000
|
$2.000
|
$1.750
|
$2.000
|
$2.000
|
$1.930
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
237.000
|
$1.750
|
$3.000
|
$3.500
|
$3.200
|
$3.300
|
|
|
GROUND BOX TY D (162922)
|
EA
|
3.000
|
$997.000
|
$650.000
|
$700.000
|
$690.000
|
$715.000
|
|
|
REMOVE GROUND BOX
|
EA
|
3.000
|
$300.000
|
$300.000
|
$330.000
|
$320.000
|
$330.000
|
|
|
ELC SRV TY D 120/240 060(NS)AL(E)SP(O)
|
EA
|
1.000
|
$6,297.000
|
$6,000.000
|
$6,000.000
|
$5,800.000
|
$6,050.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
918.000
|
$36.500
|
$25.000
|
$33.000
|
$31.000
|
$31.900
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
408.000
|
$27.000
|
$29.000
|
$40.000
|
$34.000
|
$35.200
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
17.000
|
$637.000
|
$600.000
|
$700.000
|
$700.000
|
$726.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
4.000
|
$607.000
|
$650.000
|
$800.000
|
$740.000
|
$770.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
5.000
|
$550.000
|
$1,100.000
|
$1,300.000
|
$1,200.000
|
$1,210.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
6.000
|
$1,100.000
|
$1,000.000
|
$1,300.000
|
$1,200.000
|
$1,155.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
46.000
|
$353.000
|
$350.000
|
$500.000
|
$480.000
|
$495.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
2.000
|
$451.000
|
$450.000
|
$600.000
|
$530.000
|
$550.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
116.000
|
$123.000
|
$46.000
|
$120.000
|
$110.000
|
$110.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-1EXT)
|
EA
|
2.000
|
$825.000
|
$800.000
|
$1,300.000
|
$1,200.000
|
$1,210.000
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
2,118.000
|
$6.250
|
$6.000
|
$7.000
|
$7.000
|
$6.820
|
|
|
REMOVE LRSA (FOUNDATION ONLY)(24 IN)
|
EA
|
2.000
|
$1,500.000
|
$800.000
|
$500.000
|
$430.000
|
$440.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
29.000
|
$15.000
|
$25.000
|
$30.000
|
$18.000
|
$22.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
|
EA
|
44.000
|
$24.250
|
$25.000
|
$30.000
|
$18.000
|
$22.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
41.000
|
$66.000
|
$60.000
|
$60.000
|
$80.000
|
$49.500
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
29,312.000
|
$0.250
|
$0.250
|
$0.280
|
$0.260
|
$0.280
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
11.000
|
$3.000
|
$6.000
|
$7.000
|
$6.300
|
$6.600
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
29,308.000
|
$0.250
|
$0.250
|
$0.270
|
$0.260
|
$0.280
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
3,357.000
|
$4.000
|
$3.500
|
$4.000
|
$3.700
|
$3.850
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
LF
|
61,938.000
|
$0.900
|
$0.850
|
$0.950
|
$0.900
|
$0.940
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
LF
|
67,138.000
|
$0.900
|
$0.850
|
$0.950
|
$0.900
|
$0.940
|
|
|
WK ZN PAV MRK REMOV (W)4"(DOT)
|
LF
|
650.000
|
$1.500
|
$2.000
|
$2.200
|
$2.100
|
$2.200
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
11.000
|
$8.000
|
$10.000
|
$15.000
|
$11.000
|
$11.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(DOT)
|
LF
|
394.000
|
$1.000
|
$2.000
|
$3.000
|
$2.100
|
$2.200
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
261.000
|
$1.500
|
$1.000
|
$1.100
|
$1.100
|
$1.100
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,903.000
|
$1.000
|
$1.000
|
$1.100
|
$1.100
|
$1.100
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
247.000
|
$3.750
|
$4.000
|
$5.000
|
$4.300
|
$4.400
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
1,511.000
|
$5.500
|
$6.000
|
$6.600
|
$6.500
|
$6.600
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
14.000
|
$86.000
|
$75.000
|
$90.000
|
$80.000
|
$82.500
|
|
|
PAVEMENT SEALER 4"
|
LF
|
129,076.000
|
$0.150
|
$0.150
|
$0.160
|
$0.160
|
$0.170
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
9,730.000
|
$0.500
|
$0.600
|
$0.660
|
$0.630
|
$0.660
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
46,621.000
|
$0.500
|
$0.500
|
$0.550
|
$0.530
|
$0.550
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
8,328.000
|
$0.500
|
$0.600
|
$0.660
|
$0.630
|
$0.660
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
52,432.000
|
$0.500
|
$0.500
|
$0.550
|
$0.530
|
$0.550
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
55.000
|
$634.000
|
$215.000
|
$250.000
|
$230.000
|
$236.500
|
|
PREFAB PAV MRK TY B (W)(DBL ARROW)
|
EA
|
3.000
|
$472.000
|
$280.000
|
$300.000
|
$300.000
|
$308.000
|
|
PREFAB PAV MRK TY B (W)(WORD)
|
EA
|
10.000
|
$482.000
|
$250.000
|
$300.000
|
$270.000
|
$275.000
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
2.000
|
$551.000
|
$325.000
|
$350.000
|
$350.000
|
$357.500
|
|
REFL PAV MRKR TY I-C
|
EA
|
478.000
|
$3.250
|
$3.500
|
$4.000
|
$3.700
|
$3.850
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,389.000
|
$3.250
|
$3.500
|
$4.000
|
$3.700
|
$3.850
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
10,188.000
|
$0.500
|
$0.400
|
$0.450
|
$0.450
|
$0.440
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
11.000
|
$3.500
|
$3.000
|
$4.000
|
$3.500
|
$3.300
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
130,240.000
|
$0.250
|
$0.050
|
$0.060
|
$0.050
|
$0.060
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
1.000
|
$24,046.000
|
$24,000.000
|
$26,000.000
|
$25,000.000
|
$26,400.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
1.000
|
$4,167.000
|
$5,000.000
|
$6,000.000
|
$5,300.000
|
$5,500.000
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
4.000
|
$216.000
|
$250.000
|
$300.000
|
$260.000
|
$275.000
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
4.000
|
$217.000
|
$270.000
|
$300.000
|
$280.000
|
$297.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
4.000
|
$217.000
|
$270.000
|
$300.000
|
$280.000
|
$297.000
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
8.000
|
$217.000
|
$270.000
|
$300.000
|
$280.000
|
$297.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
4.000
|
$217.000
|
$270.000
|
$300.000
|
$280.000
|
$297.000
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
4.000
|
$358.000
|
$270.000
|
$300.000
|
$280.000
|
$297.000
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
8.000
|
$542.000
|
$600.000
|
$700.000
|
$650.000
|
$660.000
|
|
|
BACKPLATE W/REFL BRDR(4 SEC)
|
EA
|
4.000
|
$101.000
|
$120.000
|
$140.000
|
$125.000
|
$132.000
|
|
|
BACKPLATE W/REFL BRDR(3 SEC)
|
EA
|
4.000
|
$90.000
|
$140.000
|
$160.000
|
$150.000
|
$154.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
|
LF
|
994.000
|
$1.500
|
$1.500
|
$1.700
|
$1.600
|
$1.650
|
|
|
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
|
LF
|
1,236.000
|
$2.000
|
$3.300
|
$3.600
|
$3.500
|
$3.630
|
|
|
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
|
LF
|
611.000
|
$2.500
|
$3.300
|
$3.600
|
$3.500
|
$3.630
|
|
|
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
|
EA
|
2.000
|
$6,874.000
|
$11,200.000
|
$13,000.000
|
$12,000.000
|
$12,320.000
|
|
|
INS TRF SIG PL AM (S)1 ARM(20')
|
EA
|
2.000
|
$5,700.000
|
$13.300
|
$16,000.000
|
$14,000.000
|
$14,630.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(40')LUM
|
EA
|
1.000
|
$9,172.000
|
$22,250.000
|
$25,000.000
|
$24,000.000
|
$24,475.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(55')
|
EA
|
1.000
|
$18,383.000
|
$36,500.000
|
$40,000.000
|
$38,000.000
|
$40,150.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
8.000
|
$780.000
|
$1.000
|
$1,200.000
|
$1,100.000
|
$1,100.000
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
1.000
|
$3,225.000
|
$2,500.000
|
$3,000.000
|
$2,600.000
|
$2,750.000
|
|
|
D-GR HMA TY-C PG70-22
|
TON
|
5,904.000
|
$67.000
|
$154.050
|
$148.000
|
$152.000
|
$140.750
|
|
|
D-GR HMA TY-D PG64-22 (LEVEL-UP)
|
TON
|
75.000
|
$91.000
|
$204.000
|
$200.000
|
$240.000
|
$173.150
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
7,424.000
|
$100.000
|
$147.000
|
$138.000
|
$140.000
|
$140.000
|
|
|
SP MIXES SP-C PG64-22
|
TON
|
31,295.000
|
$110.000
|
$140.000
|
$140.000
|
$137.000
|
$146.000
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
16,397.000
|
$110.000
|
$161.000
|
$153.000
|
$140.000
|
$175.000
|
|
|
TACK COAT
|
GAL
|
16,379.000
|
$2.500
|
$6.000
|
$4.000
|
$3.800
|
$4.400
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
16.000
|
$1.000
|
$500.000
|
$2,500.000
|
$6,000.000
|
$5,280.000
|
|
|
INSTALL FTB
|
LF
|
117.000
|
$41.000
|
$60.000
|
$100.000
|
$50.000
|
$75.000
|
|
|
REMOVE FTB
|
LF
|
117.000
|
$4.000
|
$60.000
|
$50.000
|
$35.000
|
$33.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
400.000
|
$65.000
|
$100.000
|
$150.000
|
$230.000
|
$465.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$9,304.500
|
$16,000.000
|
$30,000.000
|
$20,000.000
|
$24,000.000
|
|
|
COAXIAL CABLE
|
LF
|
63.000
|
$5.000
|
$10.000
|
$10.000
|
$6.000
|
$25.000
|
|
|
TMA (STATIONARY)
|
DAY
|
60.000
|
$157.000
|
$1,000.000
|
$300.000
|
$500.000
|
$250.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
60.000
|
$81.000
|
$1,000.000
|
$300.000
|
$500.000
|
$250.000
|
|
|
VIVDS PROSR SYS
|
EA
|
1.000
|
$6,154.000
|
$10,500.000
|
$12,000.000
|
$12,000.000
|
$11,550.000
|
|
|
VIVDS CAM ASSY FXD LNS
|
EA
|
2.000
|
$1,654.000
|
$1,950.000
|
$2,300.000
|
$2,100.000
|
$2,145.000
|
|
|
VIVDS CNTRL SOFTWARE
|
EA
|
1.000
|
$128.000
|
$100.000
|
$120.000
|
$110.000
|
$110.000
|
|
|
VIVDS CABLING
|
LF
|
721.000
|
$3.500
|
$3.500
|
$4.000
|
$4.000
|
$3.850
|
|
Totals: |
$35,671,839.555
|
$44,362,526.750
|
$45,161,963.130
|
$47,624,871.870
|
$47,710,695.980
|