SMITH FM 346 (0492-05-026)

Items: 87

County: SMITH
Length: N/A
Highway: FM 346
District: TYLER
Control Number: 0492-05-026
DBE Goal: N/A
Project: BR 2018(611)
Guaranty: N/A
Time: 206 WORKING DAYS
Engineer's Estimate: $2,475,603.25
Date: 03/07/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE & APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,475,603.25
$2,029,446.31
Over/Under Est: -18.02% -$446,156.94
Over/Under Est: -16.35% -$404,649.02
Amt Left: 2.05% $41,507.92
Over/Under Est: -14.82% -$366,916.82
Amt Left: 3.9% $79,240.12
Delta: -1.82% -$37,732.20
$2,183,188.80
Over/Under Est: -11.81% -$292,414.45
Amt Left: 7.58% $153,742.49
Delta: -3.53% -$74,502.37
Over/Under Est: -5.86% -$145,192.85
Amt Left: 14.83% $300,964.09
Delta: -6.74% -$147,221.60
Over/Under Est: 3.33% $82,474.05
Amt Left: 26.05% $528,630.99
Delta: -9.77% -$227,666.90
$2,662,838.22
Over/Under Est: 7.56% $187,234.97
Amt Left: 31.21% $633,391.91
Delta: -4.10% -$104,760.92

Bid Items & Bid Tabulations

87 Total 0 of 87
SMITH  |  FM 346  |  TYLER  |  0492-05-026  |  03/07/2018  |  $2,475,603.25  |  BR 2018(611)  |  REPLACE BRIDGE & APPROACHES  |  206 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
PIERCE R & B LLC
HIGHWAY 19 CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 27.060 $1,500.000 $1,000.000 $1,850.000 $3,500.000 $2,000.000 $1,500.000 $2,800.000 $3,500.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 6,143.000 $6.000 $3.250 $4.000 $2.800 $5.000 $10.000 $4.000 $13.800
EXCAVATION (ROADWAY)
CY 2,691.000 $4.000 $9.000 $7.000 $7.250 $7.500 $15.000 $10.000 $20.000
SUBGRADE WIDENING (ORD COMP)
STA 6.060 $200.000 $750.000 $400.000 $700.000 $2,000.000 $500.000 $650.000 $250.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 19,581.000 $11.000 $9.250 $7.150 $7.250 $12.000 $10.000 $16.000 $7.500
FURNISHING AND PLACING TOPSOIL (4")
SY 11,391.000 $2.500 $2.500 $1.850 $2.000 $1.900 $2.500 $3.000 $2.000
BROADCAST SEED (TEMP) (WARM)
SY 5,697.000 $0.150 $0.200 $0.200 $0.200 $0.210 $0.300 $0.500 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 5,697.000 $0.150 $0.200 $0.200 $0.200 $0.230 $0.300 $0.500 $1.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY)
SY 11,391.000 $0.250 $0.300 $0.310 $0.400 $0.300 $0.300 $0.500 $1.000
VEGETATIVE WATERING
MG 250.800 $12.000 $15.000 $8.000 $8.000 $25.000 $10.000 $1.000 $80.000
CEMENT
TON 128.000 $180.000 $145.000 $150.000 $180.000 $192.000 $180.000 $200.000 $150.000
CEMENT TREAT (SUBGRADE) (8")
SY 9,611.000 $3.000 $5.650 $2.250 $1.750 $5.500 $2.150 $6.000 $6.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 663.000 $6.000 $5.000 $5.000 $3.300 $12.000 $10.000 $8.000 $6.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 4,828.000 $4.000 $3.820 $6.000 $3.550 $3.720 $4.500 $6.000 $6.000
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 116.000 $130.000 $162.000 $245.000 $165.000 $162.330 $350.000 $200.000 $225.000
D-GR HMA(SQ) TY-D PG64-22
TON 58.000 $150.000 $171.000 $150.000 $200.000 $175.160 $217.000 $180.000 $200.000
SUPERPAVE MIXTURES SP-B PG64-22
TON 4,054.000 $110.000 $79.100 $100.000 $100.000 $83.170 $106.000 $90.000 $120.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-22
TON 1,323.000 $110.000 $84.400 $104.000 $100.000 $83.330 $115.750 $95.000 $100.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,302.000 $4.000 $5.750 $3.000 $5.000 $10.000 $10.000 $4.000 $4.500
CEM STABIL BKFL
CY 99.900 $160.000 $180.000 $200.000 $225.000 $197.000 $180.000 $200.000 $220.000
FLOWABLE BACKFILL
CY 5.600 $350.000 $500.000 $250.000 $350.000 $450.000 $250.000 $200.000 $220.000
TEMPORARY SPL SHORING
SF 2,199.000 $35.000 $17.950 $20.000 $35.000 $24.000 $35.000 $30.000 $12.000
DRILL SHAFT (36 IN)
LF 678.000 $200.000 $189.000 $185.000 $195.000 $193.000 $255.000 $170.000 $200.000
CL A CONC (PLUG)
EA 2.000 $450.000 $1,000.000 $1,000.000 $750.000 $500.000 $1,000.000 $600.000 $450.000
CL C CONC (ABUT)
CY 50.800 $1,000.000 $725.000 $800.000 $840.000 $925.000 $900.000 $1,000.000 $1,300.000
CL C CONC (BENT)
CY 57.200 $650.000 $985.000 $800.000 $850.000 $825.000 $817.000 $1,000.000 $1,000.000
CL C CONC (COLLAR)
EA 2.000 $925.000 $1,000.000 $800.000 $1,400.000 $1,000.000 $1,500.000 $500.000 $500.000
REINF CONC SLAB
SF 8,280.000 $20.000 $16.250 $20.000 $17.000 $19.000 $17.000 $24.000 $19.000
APPROACH SLAB
CY 70.600 $500.000 $510.000 $575.000 $475.000 $475.000 $450.000 $600.000 $500.000
PRESTR CONC GIRDER (TX34)
LF 1,071.000 $140.000 $145.000 $140.000 $126.000 $133.000 $151.000 $180.000 $136.610
RIPRAP (STONE PROTECTION)(18 IN)
CY 230.200 $122.000 $105.000 $125.000 $160.000 $128.000 $150.000 $150.000 $99.570
RIPRAP (MOW STRIP)(4 IN)
CY 35.000 $600.000 $450.000 $400.000 $460.000 $425.000 $400.000 $450.000 $450.000
RAIL (TY T223)
LF 396.000 $90.000 $95.000 $90.000 $76.000 $100.000 $100.000 $100.000 $120.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 91.000 $75.000 $95.000 $80.000 $70.000 $90.000 $110.000 $80.000 $60.000
RC PIPE (CL III)(18 IN)
LF 217.000 $45.000 $35.000 $42.000 $38.000 $37.500 $35.000 $60.000 $40.000
RC PIPE (CL III)(24 IN)
LF 28.000 $60.000 $60.000 $55.000 $65.000 $66.000 $45.000 $70.000 $60.000
RC PIPE (CL III)(36 IN)
LF 20.000 $90.000 $78.000 $100.000 $114.000 $113.000 $80.000 $90.000 $112.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $720.000 $600.000 $545.000 $615.000 $550.000 $525.000 $625.000 $710.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $800.000 $950.000 $700.000 $745.000 $680.000 $925.000 $800.000 $1,160.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $2,700.000 $1,100.000 $2,500.000 $1,650.000 $1,400.000 $1,625.000 $1,800.000 $3,000.000
PIPE (PVC) (SCH 40) (6 IN)
LF 88.000 $50.000 $17.000 $60.000 $26.000 $45.000 $10.000 $40.000 $10.000
REMOV STR (PIPE)
LF 174.000 $10.000 $9.000 $10.000 $16.500 $14.000 $10.000 $20.000 $15.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $70,000.000 $40,000.000 $35,000.000 $15,000.000 $35,000.000 $50,000.000 $75,000.000 $150,000.000
MOBILIZATION
LS 1.000 $226,000.000 $175,000.000 $150,000.000 $145,000.000 $217,000.000 $100,000.000 $175,000.000 $259,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $5,000.000 $1,750.000 $1,000.000 $1,700.000 $1,700.000 $1,000.000 $4,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 356.000 $40.000 $28.000 $29.000 $27.500 $27.750 $25.000 $40.000 $35.000
ROCK FILTER DAMS (REMOVE)
LF 356.000 $6.000 $10.000 $5.000 $9.850 $10.500 $10.000 $20.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 312.000 $22.000 $28.000 $22.000 $28.800 $21.000 $25.000 $10.000 $6.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $6.000 $10.000 $5.000 $9.800 $10.600 $5.000 $5.000 $1.500
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 75.000 $35.000 $35.000 $40.000 $34.000 $50.000 $50.000 $20.000 $99.900
BACKHOE WORK (EROSION & SEDMT CONT)
HR 180.000 $180.000 $45.000 $45.000 $100.000 $50.000 $10.000 $20.000 $75.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,337.000 $3.000 $2.750 $2.650 $2.900 $2.500 $3.000 $4.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,337.000 $1.100 $1.000 $0.500 $1.200 $1.050 $1.000 $2.000 $1.500
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 2,700.000 $20.000 $12.000 $12.000 $12.000 $6.500 $17.000 $16.000 $12.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 80.000 $25.000 $12.000 $12.000 $20.000 $6.500 $35.000 $16.000 $10.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 2,850.000 $15.000 $6.000 $4.000 $5.000 $3.250 $10.000 $6.000 $12.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 180.000 $20.000 $6.000 $4.000 $5.000 $3.250 $35.000 $6.000 $10.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 2,700.000 $20.000 $12.000 $12.000 $12.000 $6.500 $15.000 $16.000 $7.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 80.000 $25.000 $12.000 $12.000 $20.000 $6.500 $25.000 $16.000 $8.000
DRIVEWAYS (ACP)
SY 406.000 $45.000 $34.550 $25.000 $35.000 $58.000 $35.000 $60.000 $50.000
MTL W-BEAM GD FEN (TIM POST)
LF 625.000 $25.000 $24.000 $20.000 $25.000 $20.600 $17.700 $19.000 $20.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,700.000 $1,600.000 $1,500.000 $1,650.000 $1,009.000 $1,325.000 $1,400.000 $1,700.000
REMOVE METAL BEAM GUARD FENCE
LF 875.000 $4.000 $2.000 $3.500 $4.400 $3.120 $3.000 $4.000 $10.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $2,700.000 $2,350.000 $2,300.000 $2,475.000 $1,987.000 $2,400.000 $2,600.000 $300.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $250.000 $200.000 $360.000 $275.000 $234.000 $200.000 $400.000 $300.000
WIRE FENCE (TY A)
LF 226.000 $10.000 $15.000 $14.000 $14.000 $13.000 $17.000 $15.000 $15.000
GATE (TY 1)
EA 2.000 $600.000 $1,000.000 $850.000 $900.000 $832.000 $1,000.000 $200.000 $600.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 16.000 $500.000 $425.000 $450.000 $450.000 $368.000 $570.000 $400.000 $100.000
REMOVE SM RD SN SUP&AM
EA 13.000 $90.000 $150.000 $85.000 $135.000 $100.000 $100.000 $150.000 $25.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $40.000 $30.000 $23.000 $70.000 $13.500 $24.000 $30.000 $35.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 4.000 $75.000 $70.000 $55.000 $98.000 $56.250 $50.000 $55.000 $70.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 20.000 $15.000 $10.000 $10.000 $76.000 $6.000 $10.000 $10.000 $40.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $50.000 $49.000 $36.000 $84.000 $21.500 $29.000 $30.000 $25.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 4,972.000 $0.150 $0.800 $0.830 $0.820 $0.570 $0.750 $1.000 $1.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 5,172.000 $0.150 $0.800 $0.830 $0.820 $0.570 $0.750 $1.000 $1.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 440.000 $0.500 $1.100 $1.100 $1.100 $3.120 $1.000 $4.000 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 440.000 $0.500 $1.100 $1.100 $1.100 $3.120 $1.000 $4.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 249.000 $2.000 $2.000 $2.000 $1.200 $4.000 $1.000 $2.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 249.000 $2.000 $2.000 $2.000 $1.200 $4.000 $1.000 $2.000 $0.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 12.000 $5.750 $6.600 $6.500 $6.600 $26.000 $6.000 $26.000 $3.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 440.000 $0.250 $1.100 $1.100 $1.100 $2.080 $1.000 $3.000 $1.500
REFL PAV MRK TY II (Y) 4" (SLD)
LF 440.000 $0.250 $1.100 $1.100 $1.100 $2.080 $1.000 $3.000 $1.200
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 5,348.000 $0.500 $1.750 $1.750 $1.750 $1.400 $1.600 $2.000 $1.000
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 70.000 $0.600 $1.750 $1.750 $1.750 $1.600 $1.600 $2.000 $1.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 5,008.000 $0.700 $1.750 $1.750 $1.750 $1.400 $1.600 $2.000 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 42.000 $125.000 $85.000 $90.000 $100.000 $101.000 $100.000 $100.000 $100.000
REFL PAV MRKR TY II A-A
EA 67.000 $4.000 $5.500 $5.500 $5.500 $10.500 $5.000 $12.000 $35.000
Totals: $2,475,603.250 $2,029,446.310 $2,070,954.230 $2,108,686.430 $2,183,188.800 $2,330,410.400 $2,558,077.300 $2,662,838.224