County: SCURRY Highway: FM 1673 Date: 01/04/2024 (10 months ago) Engineer's Estimate: $5,587,891 Control Number: 2189-01-020
Project: BR 2024(664) District: ABILENE Time: 126 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,587,891.30
HODGES AND SON CONSTRUCTION COMPANY, INC.   $7,348,904.50 1
31.51% | $1,761,013.20
Subcontractor Percentage Amount
MORRIS COUNTY CONTRACTORS, L.L.C. 0.42% $30,865.40
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.25% $18,372.26
TRP CONSTRUCTION GROUP, LLC 0.15% $11,023.36
FC TRAFFIC CONTROL, INC. 0.08% $5,879.12
TORO BRAVO CONSTRUCTION, LLC 0.08% $5,879.12
AWP SAFETY 0.07% $5,144.23
S & S BRIDGE PAINTING, INC. 0.00% $0.00
Total: 1.05% $77,163.49

Bid Items

Items: 61, 0 filtered
SCURRY FM 1673  |  ABILENE  |  2189-01-020  |  01/04/2024  |  $5,587,891  |  BR 2024(664)  |  BRIDGE REPL  |  126 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HODGES AND SON CONSTRUCTION COMPANY, INC.
100 6002 PREPARING ROW STA 2.000 $2,500.000 $20,000.000
110 6001 EXCAVATION (ROADWAY) CY 437.000 $35.000 $50.000
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 573.000 $40.000 $50.000
162 6002 BLOCK SODDING SY 1,814.000 $10.000 $10.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 907.000 $2.000 $2.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 907.000 $2.000 $2.000
168 6001 VEGETATIVE WATERING MG 3.500 $70.000 $1.000
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 270.000 $110.000 $150.000
310 6009 PRIME COAT (MC-30) GAL 233.000 $8.000 $30.000
316 6001 ASPH (MULTI OPTION) GAL 466.000 $15.000 $30.000
316 6017 ASPH (AC-20-5TR) GAL 419.000 $15.000 $30.000
316 6173 AGGR(TY-B GR-3 SAC-B) CY 11.000 $320.000 $1,000.000
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 10.000 $340.000 $1,000.000
400 6005 CEM STABIL BKFL CY 111.000 $300.000 $250.000
416 6004 DRILL SHAFT (36 IN) LF 576.000 $350.000 $240.000
420 6013 CL C CONC (ABUT) CY 45.800 $2,200.000 $2,500.000
420 6029 CL C CONC (CAP) CY 70.800 $2,200.000 $2,500.000
420 6037 CL C CONC (COLUMN) CY 62.700 $2,200.000 $2,500.000
422 6001 REINF CONC SLAB SF 13,112.000 $30.000 $45.000
422 6013 BRIDGE SIDEWALK SF 2,314.000 $75.000 $70.000
422 6015 APPROACH SLAB CY 125.400 $900.000 $1,200.000
423 6001 RETAINING WALL (MSE) SF 3,430.000 $85.000 $140.000
427 6006 EPOXY WATERPROOF FINISH SF 310.000 $40.000 $10.000
432 6001 RIPRAP (CONC)(4 IN) CY 37.100 $4,000.000 $800.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 12.900 $1,500.000 $700.000
434 6021 ELASTOMERIC BEARING (E2) EA 14.000 $4,000.000 $2,500.000
434 6030 ELASTOMERIC BEARING (F2) EA 7.000 $4,000.000 $3,000.000
442 6004 STR STEEL (ROLLED BEAM) LB 501,100.000 $3.750 $6.500
442 6007 STR STEEL (MISC NON - BRIDGE) LB 1,370.000 $30.000 $20.000
450 6032 RAIL (TY C223) LF 875.000 $220.000 $150.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 86.000 $260.000 $200.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $600,000.000 $400,000.000
500 6001 MOBILIZATION LS 1.000 $506,950.300 $630,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $25,000.000 $44,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 610.000 $20.000 $5.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 610.000 $5.000 $2.000
529 6005 CONC CURB (MONO) (TY II) LF 377.000 $14.000 $50.000
529 6008 CONC CURB & GUTTER (TY II) LF 65.000 $70.000 $80.000
530 6006 DRIVEWAYS (SURF TREAT) SY 604.000 $80.000 $50.000
531 6003 CONC SIDEWALKS (6") SY 35.000 $120.000 $200.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 50.000 $40.000 $30.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 3.000 $3,000.000 $2,500.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,700.000 $2,000.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 25.000 $5.000 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 2.000 $250.000 $500.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 1.000 $4,000.000 $3,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $400.000 $500.000
545 6028 CRASH CUSH ATTEN (INSTL) (S) (TL3) EA 1.000 $10,000.000 $20,000.000
560 6008 MAILBOX INSTALL-D (WC-POST) TY 3 EA 1.000 $300.000 $500.000
644 6008 IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL) EA 1.000 $70.000 $2,000.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 7.000 $70.000 $3,500.000
644 6065 IN BRIDGE MNT CLEARANCE SGN ASSM(TY S) EA 6.000 $2,600.000 $5,000.000
644 6076 REMOVE SM RD SN SUP&AM EA 8.000 $70.000 $120.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $70.000 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 1.000 $50.000 $50.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 1,246.000 $2.000 $6.000
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 1,452.000 $2.000 $6.000
672 6009 REFL PAV MRKR TY II-A-A EA 20.000 $12.000 $20.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $12,000.000 $22,000.000
6185 6002 TMA (STATIONARY) DAY 27.000 $350.000 $300.000
6185 6005 TMA (MOBILE OPERATION) DAY 2.000 $450.000 $300.000
Totals: $5,587,891.30 $7,348,904.50