Job Info for 0540-02-027

County: ROBERTSON Highway: FM 46 Date: 02/02/2024 (9 months ago) Engineer's Estimate: $1,878,353 Control Number: 0540-02-027
Project: BR 2024(732) District: BRYAN Time: 112 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,878,353.20
KNIFE RIVER CORPORATION - SOUTH   $1,750,129.90 1
-6.83% | -$128,223.30
LARRY YOUNG PAVING, INC.   $1,864,484.85 2
-0.74% | -$13,868.35
6.53% | $114,354.95
TALBERT COMPANIES LLC   $1,985,628.88 3
5.71% | $107,275.68
13.46% | $235,498.98
6.50% | $121,144.03
C. E. BARKER, LTD.   $2,098,179.44 4
11.7% | $219,826.24
19.89% | $348,049.54
5.67% | $112,550.56
PROJECT ALLIED RESOURCES, LLC   $2,106,645.95 5
12.15% | $228,292.75
20.37% | $356,516.05
0.40% | $8,466.51
TEXAS MATERIALS GROUP, INC.   $2,163,580.05 6
15.18% | $285,226.85
23.62% | $413,450.15
2.70% | $56,934.10
BRAZOS PAVING, INC.   $2,203,823.06 7
17.33% | $325,469.86
25.92% | $453,693.16
1.86% | $40,243.01
TREVWAY, INC.   $2,254,517.89 8
20.03% | $376,164.69
28.82% | $504,387.99
2.30% | $50,694.83
HODGES AND SON CONSTRUCTION COMPANY, INC.   $2,408,838.00 9
28.24% | $530,484.80
37.64% | $658,708.10
6.84% | $154,320.11
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 8.63% $151,036.21
WILLOW CITY SIGN & RAIL, INC. 3.52% $61,604.57
STRIPE LINES, INC. 1.61% $28,177.09
CEN TEX HYDROSEED, INC. 1.26% $22,051.64
TORO BRAVO CONSTRUCTION, LLC 0.64% $11,200.83
BATTEN DRILLING, INC. 0.54% $9,450.70
PRIMATE CONSTRUCTION, LP 0.50% $8,750.65
TEXAS CUTTING & CORING GP, INC. 0.49% $8,575.64
CEN-TREE SOLUTIONS LLC 0.21% $3,675.27
Total: 17.40% $304,522.60

Bid Items

Items: 72, 0 filtered
ROBERTSON FM 46  |  BRYAN  |  0540-02-027  |  02/02/2024  |  $1,878,353  |  BR 2024(732)  |  BRIDGE REPL  |  112 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate KNIFE RIVER CORPORATION - SOUTH LARRY YOUNG PAVING, INC. TALBERT COMPANIES LLC C. E. BARKER, LTD. PROJECT ALLIED RESOURCES, LLC TEXAS MATERIALS GROUP, INC. BRAZOS PAVING, INC. TREVWAY, INC. HODGES AND SON CONSTRUCTION COMPANY, INC.
100 6002 PREPARING ROW STA 4.400 $6,000.000 $1,360.000 $1,113.810 $10,000.000 $21,600.000 $3,170.000 $16,000.000 $6,900.000 $25,000.000 $8,000.000
105 6095 REMOVING STAB BASE & ASPH PAV (12"-14") SY 1,102.000 $17.000 $12.000 $15.420 $7.000 $4.760 $14.000 $25.000 $17.750 $7.000 $25.000
110 6001 EXCAVATION (ROADWAY) CY 906.000 $40.000 $12.300 $36.330 $100.000 $24.020 $30.700 $41.000 $40.900 $25.000 $20.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 285.000 $30.000 $10.400 $83.550 $100.000 $49.860 $44.500 $50.000 $61.000 $41.500 $50.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 1,158.000 $4.000 $3.700 $15.550 $6.000 $3.930 $2.330 $15.000 $10.350 $4.000 $4.000
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 1,158.000 $1.000 $1.100 $1.320 $1.000 $1.000 $1.300 $1.000 $0.750 $3.000 $4.000
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 579.000 $3.000 $1.100 $1.320 $1.000 $0.900 $1.300 $1.000 $0.750 $3.000 $2.000
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 579.000 $3.000 $1.100 $1.320 $1.000 $0.840 $1.300 $1.000 $0.750 $3.000 $2.000
168 6001 VEGETATIVE WATERING MG 11.600 $45.000 $70.000 $104.360 $1.000 $168.760 $66.000 $63.000 $104.350 $100.000 $1.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 118.000 $4.000 $2.000 $1.990 $6.000 $7.430 $1.950 $1.600 $6.200 $15.000 $5.000
247 6219 FL BS (CMP IN PLC)(TY A GR 1-2)(9") SY 1,562.000 $35.000 $22.800 $36.450 $52.000 $61.530 $58.000 $60.000 $32.600 $110.000 $60.000
275 6001 CEMENT TON 17.000 $300.000 $317.000 $397.320 $200.000 $318.240 $296.000 $305.000 $335.000 $400.000 $300.000
275 6010 CEMENT TREAT (SUBGRADE) (8") SY 1,670.000 $6.000 $6.240 $12.770 $6.500 $9.550 $8.900 $16.000 $14.610 $12.000 $15.000
310 6028 PRIME COAT (MC-30 OR EC-30) GAL 368.000 $12.000 $12.800 $7.080 $7.000 $10.610 $33.800 $19.000 $8.000 $21.000 $20.000
316 6014 ASPH (AC-10-2TR) GAL 890.000 $12.000 $7.550 $10.600 $7.000 $10.610 $17.600 $5.000 $14.000 $22.000 $20.000
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 19.000 $600.000 $459.000 $198.660 $300.000 $265.200 $273.000 $900.000 $848.000 $1,424.000 $2,000.000
354 6021 PLANE ASPH CONC PAV(0" TO 2") SY 556.000 $13.000 $10.500 $15.280 $20.000 $9.550 $16.300 $22.000 $22.150 $42.000 $20.000
400 6005 CEM STABIL BKFL CY 169.200 $200.000 $162.000 $222.200 $225.000 $154.880 $287.000 $250.000 $137.850 $100.000 $280.000
403 6001 TEMPORARY SPL SHORING SF 796.000 $60.000 $99.000 $43.090 $45.000 $31.820 $61.000 $50.000 $75.000 $35.000 $50.000
416 6001 DRILL SHAFT (18 IN) LF 180.000 $110.000 $130.000 $269.950 $125.000 $154.090 $209.000 $116.000 $285.000 $166.570 $200.000
416 6004 DRILL SHAFT (36 IN) LF 540.000 $370.000 $353.400 $383.990 $345.000 $372.220 $407.000 $365.000 $420.000 $501.000 $300.000
420 6013 CL C CONC (ABUT) CY 71.000 $1,400.000 $1,300.000 $937.610 $1,200.000 $1,493.610 $1,990.000 $1,700.000 $1,610.000 $1,200.000 $2,000.000
422 6001 REINF CONC SLAB SF 4,165.000 $36.000 $40.000 $36.610 $32.000 $36.940 $36.100 $47.000 $37.900 $48.000 $50.000
422 6015 APPROACH SLAB CY 77.000 $950.000 $979.000 $1,148.370 $855.000 $806.890 $1,050.000 $830.000 $803.200 $841.000 $1,200.000
425 6036 PRESTR CONC GIRDER (TX34) LF 591.510 $250.000 $232.200 $267.810 $177.770 $282.590 $251.000 $275.000 $328.600 $266.980 $340.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 1,163.000 $200.000 $163.500 $121.650 $200.000 $233.380 $186.000 $150.000 $156.000 $197.510 $200.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 53.000 $600.000 $782.000 $611.780 $300.000 $887.540 $771.000 $810.000 $365.900 $500.000 $700.000
450 6006 RAIL (TY T223) LF 250.000 $180.000 $208.000 $165.000 $170.000 $214.600 $191.000 $184.000 $270.000 $181.750 $160.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 96.000 $230.000 $260.000 $346.610 $230.000 $212.160 $328.000 $270.000 $140.000 $98.160 $200.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $30,000.000 $20,300.000 $68,824.230 $85,000.000 $37,128.000 $43,500.000 $40,000.000 $99,650.000 $44,000.000 $150,000.000
500 6001 MOBILIZATION LS 1.000 $181,000.000 $169,700.000 $260,000.000 $174,500.000 $200,000.000 $221,000.000 $210,000.000 $220,000.000 $210,000.000 $230,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $5,000.000 $1,940.000 $2,273.150 $10,000.000 $10,608.000 $2,220.000 $10,000.000 $7,940.000 $1,035.760 $10,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 160.000 $40.000 $42.200 $50.330 $6.000 $47.740 $45.700 $38.000 $49.500 $22.000 $1.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 160.000 $11.000 $11.000 $13.240 $3.000 $14.850 $14.000 $10.000 $13.050 $10.000 $1.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 120.000 $34.000 $39.900 $46.350 $6.000 $30.950 $48.500 $30.000 $45.650 $15.000 $1.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 120.000 $12.000 $16.600 $19.870 $3.000 $9.280 $16.400 $10.000 $19.600 $5.000 $1.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,254.000 $5.000 $4.170 $4.970 $6.000 $6.360 $5.900 $5.000 $4.900 $4.000 $1.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,254.000 $1.500 $1.000 $1.320 $3.000 $1.590 $1.620 $1.000 $1.300 $3.000 $1.000
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 510.000 $100.000 $50.000 $10.560 $97.280 $47.740 $106.000 $75.000 $106.150 $100.000 $95.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 180.000 $15.000 $12.000 $10.180 $37.000 $12.380 $19.500 $35.000 $21.700 $50.000 $50.000
512 6049 PORT CTB (REMOVE)(SGL SLP)(TY 1) LF 510.000 $20.000 $27.800 $10.380 $75.000 $20.340 $28.500 $30.000 $16.500 $25.000 $40.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 575.000 $27.000 $25.000 $29.800 $31.000 $23.870 $30.000 $23.000 $32.600 $23.580 $28.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,300.000 $2,602.000 $2,714.990 $225.000 $2,174.640 $2,220.000 $2,500.000 $2,515.000 $2,200.000 $1,500.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 613.000 $3.000 $4.000 $3.970 $6.750 $3.180 $3.000 $3.000 $7.850 $5.000 $2.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,200.000 $3,206.000 $3,820.860 $3,500.000 $3,060.410 $3,600.000 $2,900.000 $4,360.000 $3,900.000 $3,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $275.000 $220.000 $264.880 $400.000 $212.160 $300.000 $210.000 $542.000 $646.000 $500.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $1,000.000 $2,100.000 $229.480 $2,000.000 $1,962.480 $1,230.000 $950.000 $2,242.000 $1,524.000 $4,000.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $1,000.000 $1,100.000 $395.030 $1,000.000 $1,060.800 $1,080.000 $1,400.000 $1,750.000 $1,000.000 $2,000.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $10,000.000 $9,800.000 $4,460.930 $8,700.000 $9,335.040 $10,100.000 $12,000.000 $10,285.000 $9,700.000 $16,000.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 3.000 $700.000 $628.000 $435.560 $675.000 $599.350 $866.000 $570.000 $429.000 $517.000 $2,000.000
644 6076 REMOVE SM RD SN SUP&AM EA 5.000 $130.000 $167.000 $172.170 $110.000 $159.120 $136.000 $108.000 $170.000 $259.000 $50.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 4.000 $28.000 $28.000 $16.410 $25.000 $26.520 $27.600 $25.000 $16.150 $15.000 $30.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 13.000 $35.000 $39.000 $33.110 $30.000 $37.130 $36.000 $35.000 $33.600 $15.000 $30.000
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 2,295.000 $2.000 $3.200 $1.920 $3.000 $1.540 $5.800 $2.900 $1.900 $1.880 $5.000
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 35.000 $15.000 $12.500 $16.550 $10.000 $13.260 $23.000 $11.500 $16.300 $16.180 $45.000
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 735.000 $2.000 $3.200 $1.920 $4.000 $1.540 $5.800 $2.900 $1.900 $1.880 $5.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 400.000 $3.000 $2.200 $0.610 $4.000 $1.690 $1.350 $1.200 $1.800 $6.470 $5.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 400.000 $2.000 $2.200 $0.640 $4.000 $1.590 $1.180 $1.200 $1.800 $6.470 $5.000
666 6225 PAVEMENT SEALER 6" LF 644.000 $3.000 $0.400 $0.300 $2.000 $0.240 $1.150 $0.370 $0.300 $0.300 $2.000
666 6284 REF PROF PAV MRK TY I(W)6"(SLD)(060MIL) LF 2,198.000 $1.500 $2.780 $6.620 $2.250 $5.300 $5.800 $2.600 $6.500 $6.470 $2.000
666 6289 REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL) LF 2,198.000 $2.250 $2.780 $6.620 $2.250 $5.300 $5.800 $2.600 $6.500 $6.470 $2.000
666 6293 REF PROF PAV MRK TY I(Y)6"(BRK)(090MIL) LF 184.000 $4.000 $2.780 $6.620 $3.000 $5.300 $5.800 $2.600 $6.500 $6.470 $3.000
672 6009 REFL PAV MRKR TY II-A-A EA 47.000 $8.000 $9.000 $7.950 $3.000 $6.360 $11.500 $7.500 $7.850 $7.770 $20.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 884.000 $0.750 $0.900 $0.950 $4.000 $0.770 $3.450 $0.820 $3.900 $0.930 $2.000
678 6002 PAV SURF PREP FOR MRK (6") LF 644.000 $0.300 $0.200 $0.300 $4.000 $0.240 $1.730 $0.160 $0.300 $0.320 $2.000
3077 6011 SP MIXES SP-C PG64-22 TON 168.000 $240.000 $249.000 $199.930 $185.000 $228.070 $219.000 $300.000 $170.250 $258.000 $250.000
3077 6012 SP MIXES SP-C SAC-A PG64-22 TON 199.000 $250.000 $250.000 $206.840 $165.000 $238.680 $190.000 $300.000 $207.700 $258.000 $250.000
3084 6001 BONDING COURSE GAL 180.000 $10.000 $4.500 $8.930 $8.100 $12.730 $40.200 $16.000 $12.300 $33.000 $8.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $6,600.000 $5,032.670 $15,000.000 $10,608.000 $8,720.000 $11,000.000 $18,640.000 $15,000.000 $20,000.000
6185 6002 TMA (STATIONARY) DAY 4.000 $300.000 $500.000 $59.260 $300.000 $307.630 $483.000 $500.000 $260.000 $600.000 $400.000
6185 6005 TMA (MOBILE OPERATION) DAY 6.000 $300.000 $800.000 $79.010 $300.000 $318.240 $509.000 $500.000 $620.000 $600.000 $400.000
6509 6001 DRIVEWAY ASSISTANCE DEVICE(DAD) SYSTEM MO 7.000 $4,500.000 $7,550.000 $5,827.300 $8,000.000 $7,956.000 $8,040.000 $7,500.000 $10,300.000 $6,500.000 $6,000.000
Totals: $1,878,353.20 $1,750,129.90 $1,864,484.86 $1,985,628.88 $2,098,179.45 $2,106,645.95 $2,163,580.05 $2,203,823.07 $2,254,517.90 $2,408,838.00