RANDALL IH 27 (0168-09-083)

Items: 354

County: RANDALL
Length: N/A
Highway: IH 27
District: AMARILLO
Control Number: 0168-09-083
DBE Goal: 500.0%
Project: F 2024(864)
Guaranty: N/A
Time: 1155 WORKING DAYS
Engineer's Estimate: $235,609,131.26
Date: 02/01/2024 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT NEW ROAD
Mail/Deliver Bids To: N/A
JOE CHAPPELL
CC SYSOMBATH
KENNETH PETR
DARRELL CALDWELL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$235,609,131.26
1
$312,507,980.84
Over/Under Est: 32.64% $76,898,849.58
Subcontractor Percentage Amount
J. LEE MILLIGAN, INC. 27.30% $85,013,409.31
APOLLO CONSTRUCTORS, INC. 5.06% $15,757,064.14
TURKEY CREEK HDD, LLC 1.86% $5,792,122.39
H & F TRUCKING 1.77% $5,511,858.41
ALAMO BROTHERS CONCRETE INC 1.68% $5,231,594.42
J. H. ODEN CONTRACTING COMPANY 0.70% $2,179,831.01
TRP CONSTRUCTION GROUP, LLC 0.67% $2,086,409.68
KING GEORGE TRAFFIC SOLUTIONS LLC 0.51% $1,588,162.59
2H, LLC 0.48% $1,494,741.26
TORO BRAVO CONSTRUCTION, LLC 0.34% $1,058,775.06
A BROTHERS MILLING, LLC 0.29% $903,072.85
GIBSON & ASSOCIATES, INC. 0.27% $840,791.96
ACT SAW CUTTING & REMOVAL 0.20% $622,808.86
PRIMATE CONSTRUCTION, LP 0.15% $467,106.64
DK CONTRACTING, LLC 0.15% $467,106.64
SCOTT DERR PAINTING CO, LLC 0.13% $404,825.76
TRUMBLE CRANE & RIGGING 0.10% $311,404.43
JBC CONSOLIDATED, LLC 0.08% $249,123.54
FC TRAFFIC CONTROL, INC. 0.07% $217,983.10
ADRIAN CONTRACTING, INC 0.06% $186,842.66
ANTIGO CONSTRUCTION, INC. 0.05% $155,702.21
GORMAN OUTDOOR, INC. 0.03% $93,421.33
TEX OP CONSTRUCTION, LP 0.02% $62,280.89
HOWELL SAND COMPANY, INC. 0.02% $62,280.89
NELSON INDUSTRIAL SERVICES, INC. 0.00% $0.00
Total: 41.99% $130,758,720.03

Bid Items & Bid Tabulations

354 Total 0 of 354
RANDALL  |  IH 27  |  AMARILLO  |  0168-09-083  |  02/01/2024  |  $235,609,131.26  |  F 2024(864)  |  CONSTRUCT NEW ROAD  |  1155 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
WEBBER, LLC
PREPARING ROW
STA 358.000 $42,000.000 $85,997.500
PREPARING ROW(OPT1)
STA 15.000 $4,000.000 $3,250.000
REMOVING CONC (PAV)
SY 88,810.000 $14.000 $11.210
REMOVING CONC (RIPRAP)
SY 444.000 $15.750 $35.230
REMOVING CONC (DRIVEWAYS)
SY 157.000 $20.000 $50.410
REMOVING CONC (CURB AND GUTTER)
LF 738.000 $9.400 $10.320
REMOVING CONC (CTB)
LF 30.000 $28.000 $46.750
REMOVE CONC (RAIL)
LF 496.000 $28.000 $26.620
REMOVING CONC (FLUME)
SY 151.000 $15.750 $94.050
REMOVING CONCRETE(MOW STRIP)
LF 34,995.000 $10.000 $7.790
REMOV STAB BASE AND ASPH PAV (10"-18")
SY 161,189.000 $12.000 $18.610
EXCAVATION (ROADWAY)
CY 158,456.000 $14.000 $38.720
EXCAVATION (SPECIAL)
CY 85,584.000 $20.200 $37.050
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 96,077.000 $18.000 $28.650
ROAD GRADER WORK (ORD COMP)
SY 13,306.000 $3.000 $4.870
GENERAL USE COMPOST (1")
SY 4,668.000 $2.000 $2.920
COMPOST MANUF TOPSOIL (4")
SY 384,013.000 $1.750 $4.420
EROSION CONTROL COMPOST (4")
SY 4,668.000 $6.000 $6.120
COMPOST MANUF TOPSOIL (18" AVG)
SY 4,668.000 $6.000 $14.370
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
AC 40.000 $2,230.000 $2,500.000
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 40.000 $610.000 $750.000
VEGETATIVE WATERING
MG 6,495.000 $35.000 $42.950
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 35,823.000 $2.000 $1.950
PLANT MATERIAL (45-GAL)
EA 147.000 $500.000 $1,400.000
PLANT BED PREP (TYPE I)
SY 4,668.000 $9.000 $5.000
PLANT MAINTENANCE
MO 12.000 $8,000.000 $1,500.000
FL BS(CMP IN PLC)(TY A,B OR D GR4)(12")
SY 67,351.000 $40.000 $58.880
LIME (QUICKLIME (DRY))
TON 4,464.000 $330.000 $420.000
LIME TRT (EXST MATL)(8")
SY 444,940.000 $8.000 $9.590
PRIME COAT (MC-30)
GAL 111,255.000 $5.500 $6.750
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 54,836.000 $35.000 $54.000
PLANE ASPH CONC PAV(0" TO 2")
SY 2,180.000 $5.000 $13.020
PLANE ASPH CONC PAV(0" TO 6")
SY 50,455.000 $5.000 $9.670
PLANE CONC PAV(0" TO 2")
SY 451.000 $5.000 $45.000
PLANE ASPH CONC PAV (1.5")
SY 1,349.000 $5.000 $28.310
PLANE ASPH CONC PAV (0" TO 3 1/2")
SY 34,281.000 $3.000 $7.400
PLANE ASPH CONC PAV (3 1/2")
SY 13,422.000 $3.000 $8.930
CONC PVMT (CONT REINF - CRCP) (13")
SY 416,184.000 $122.000 $126.230
CEM STABIL BKFL
CY 539.000 $245.000 $550.000
CUT & RESTORING PAV
SY 7,798.000 $200.000 $135.000
CUT & RESTORE CONC PAVING
SY 1,089.000 $300.000 $410.000
CUT & RESTORE ASPH PAVING
SY 18.000 $200.000 $325.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 55.000 $245.000 $550.000
FLOWABLE BACKFILL
CY 786.000 $290.000 $550.000
TRENCH EXCAVATION PROTECTION
LF 38,239.000 $5.330 $3.000
TEMPORARY SPL SHORING
SF 48,081.000 $20.000 $19.000
DRILL SHAFT (36 IN)
LF 550.000 $340.000 $850.000
DRILL SHAFT (42 IN)
LF 32.000 $403.000 $1,050.000
DRILL SHAFT (48 IN)
LF 550.000 $510.000 $395.000
DRILL SHAFT (54 IN)
LF 20.000 $619.000 $1,250.000
DRILL SHAFT (SIGN MTS) (12 IN)
LF 77.000 $138.000 $205.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 299.000 $220.000 $467.000
DRILL SHAFT (SIGN MTS) (30 IN)
LF 80.000 $250.000 $655.000
DRILL SHAFT (SIGN MTS) (36 IN)
LF 376.000 $357.000 $785.000
DRILL SHAFT (SIGN MTS) (42 IN)
LF 82.000 $403.000 $807.000
DRILL SHAFT (SIGN MTS) (48 IN)
LF 125.000 $570.000 $1,250.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 223.000 $640.000 $825.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 2,562.000 $715.000 $975.000
CL C CONC (ABUT)(HPC)
CY 61.300 $1,790.000 $3,755.000
CL C CONC (CAP)(HPC)
CY 101.200 $1,764.000 $3,544.000
CL C CONC (COLUMN)(HPC)
CY 153.300 $1,723.000 $3,501.000
CL C CONC (RAIL FOUNDATION)
CY 725.000 $652.000 $2,011.000
REINF CONC SLAB (HPC)
SF 20,976.000 $44.500 $44.770
APPROACH SLAB (HPC)
CY 73.800 $934.000 $2,050.000
RETAINING WALL (MSE)
SF 7,023.000 $90.000 $155.000
PRESTR CONC GIRDER (TX54)
LF 2,957.580 $304.000 $899.000
CONCRETE PAINT FINISH
SF 169,784.000 $0.950 $1.750
EPOXY WATERPROOF FINISH (TY X)
SF 4,949.000 $9.000 $15.100
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 3.000 $178.000 $1,424.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 74.000 $239.000 $1,350.000
RIPRAP (CONC)(4 IN)
CY 1,778.110 $750.000 $643.920
RIPRAP (CONC)(5 IN)
CY 3,582.000 $750.000 $793.760
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 1,365.000 $300.000 $479.360
RIPRAP (MOW STRIP)(4 IN)
CY 507.000 $750.000 $627.780
CLEANING AND SEALING JOINTS (CL 7)
LF 166.000 $41.000 $132.560
CLEANING EXISTING JOINTS
LF 228.000 $13.700 $91.200
CLEANING AND SEALING JOINTS (FOAM)
LF 228.000 $85.700 $207.860
RAIL (TY SSTR)
LF 15,884.000 $79.000 $117.000
RAIL (TY T80SS)
LF 1,675.000 $96.000 $135.000
RAIL (TY T80SS) (MOD)
LF 80.000 $125.000 $305.000
RAIL (TY PR11)
LF 537.000 $160.000 $103.400
RAIL (TY T80PP)
LF 16,290.000 $198.000 $138.000
RAIL (TY T80PP-TS)
LF 616.000 $400.000 $425.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 153.000 $199.000 $274.600
WATERPROOFING (TY 10)
SY 82.000 $165.000 $15.100
GABION MATTRESSES (GALV)(12 IN)
SY 1,406.000 $240.000 $227.750
CONC BOX CULV (3 FT X 2 FT)
LF 1,474.000 $350.000 $493.000
CONC BOX CULV (4 FT X 2 FT)
LF 2,418.000 $400.000 $528.000
CONC BOX CULV (4 FT X 3 FT)
LF 322.000 $475.000 $591.000
CONC BOX CULV (4 FT X 4 FT)
LF 384.000 $525.000 $651.000
CONC BOX CULV (5 FT X 2 FT)
LF 2,931.000 $475.000 $675.000
CONC BOX CULV (5 FT X 3 FT)
LF 1,933.000 $525.000 $698.000
CONC BOX CULV (5 FT X 4 FT)
LF 5,652.000 $575.000 $809.000
CONC BOX CULV (6 FT X 3 FT)
LF 2,592.000 $720.000 $885.000
CONC BOX CULV (6 FT X 4 FT)
LF 1,187.000 $740.000 $888.000
CONC BOX CULV (7 FT X 3 FT)
LF 2,280.000 $720.000 $869.000
CONC BOX CULV (7 FT X 4 FT)
LF 2,317.000 $770.000 $997.000
CONC BOX CULV (8 FT X 4 FT)
LF 5,408.000 $800.000 $1,197.000
CONC BOX CULV (6 FT X 2 FT)
LF 215.000 $650.000 $825.000
RC PIPE (CL III)(18 IN)
LF 994.000 $140.000 $165.000
RC PIPE (CL III)(24 IN)
LF 8,753.000 $155.000 $188.000
RC PIPE (CL III)(30 IN)
LF 2,698.000 $175.000 $199.000
RC PIPE (CL III)(36 IN)
LF 8,253.000 $210.000 $226.000
RC PIPE (CL III)(42 IN)
LF 1,554.000 $260.000 $291.000
RC PIPE (CL III)(48 IN)
LF 839.000 $300.000 $429.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 14.000 $8,300.000 $6,714.000
INLET (COMPL)(PCO)(3FT)(LEFT)
EA 1.000 $7,350.000 $8,242.000
INLET (COMPL)(PCO)(3FT)(RIGHT)
EA 5.000 $10,000.000 $7,657.000
INLET (COMPL)(PCO)(3FT)(BOTH)
EA 1.000 $12,500.000 $9,317.000
INLET (COMPL)(PCU)(3FT)(NONE)
EA 3.000 $9,000.000 $10,899.000
INLET (COMPL)(PMBD)(4FT)
EA 10.000 $7,700.000 $12,325.000
INLET (COMPL)(POD)(SFG)(3FTX3FT)
EA 11.000 $7,700.000 $10,850.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 2.000 $8,300.000 $14,888.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 29.000 $8,700.000 $9,629.000
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
EA 68.000 $8,000.000 $11,490.000
INLET (COMPL)(PSL)(FG)(5FTX5FT-4FTX4FT)
EA 1.000 $9,500.000 $11,689.000
INLET (COMPL)(PSL)(FG)(5FTX5FT-3FTX5FT)
EA 93.000 $8,000.000 $12,725.000
INLET (COMPL)(PSL)(FG)(6FTX6FT-3FTX5FT)
EA 2.000 $9,500.000 $14,318.000
INLET (COMPL)(PSL)(FG)(8FTX8FT-3FTX3FT)
EA 1.000 $14,000.000 $20,531.000
INLET (COMPL)(PSL)(FG)(8FTX8FT-3FTX5FT)
EA 3.000 $15,000.000 $22,400.000
INLET(COMPL)(PSL)(SFG)(3FTX3FT-3FTX3FT)
EA 1.000 $9,600.000 $13,560.000
INLET(COMPL)(PSL)(SFG)(3FTX5FT-3FTX5FT)
EA 55.000 $9,000.000 $9,899.000
INLET (COMPL)(TY MSE2)
EA 10.000 $11,200.000 $16,882.000
JCT BOX (COMPL)(SPL)
EA 2.000 $75,000.000 $186,429.680
WINGWALL (PW - 1) (HW=5 FT)
EA 2.000 $20,990.000 $47,948.520
WINGWALL (PW - 1) (HW=7 FT)
EA 4.000 $35,145.000 $54,604.950
WINGWALL (PW - 1) (HW=8 FT)
EA 2.000 $44,000.000 $55,537.660
WINGWALL (SW - 0) (HW=6 FT)
EA 1.000 $15,290.000 $56,916.990
SET (TY I)(S= 4 FT)(HW= 2 FT)(4:1) (C)
EA 1.000 $8,500.000 $11,136.130
SET (TY I)(S= 4 FT)(HW= 2 FT)(6:1) (P)
EA 1.000 $9,000.000 $17,843.090
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P)
EA 2.000 $10,300.000 $19,683.240
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
EA 4.000 $12,960.000 $13,315.500
SET (TY I)(S= 5 FT)(HW= 2 FT)(4:1) (C)
EA 1.000 $8,500.000 $13,182.830
SET (TY I)(S= 5 FT)(HW= 2 FT)(6:1) (P)
EA 1.000 $9,350.000 $14,822.090
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 1.000 $13,840.000 $15,908.640
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (P)
EA 2.000 $11,000.000 $15,463.170
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 10.000 $12,000.000 $13,858.550
SET (TY I)(S= 6 FT)(HW= 4 FT)(6:1) (P)
EA 1.000 $15,550.000 $26,344.720
SET (TY I)(S= 8 FT)(HW= 4 FT)(4:1) (P)
EA 2.000 $22,000.000 $26,362.740
SET (TY I)(S= 8 FT)(HW= 4 FT)(6:1) (P)
EA 1.000 $25,000.000 $31,821.350
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $1,520.000 $2,772.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 5.000 $2,365.000 $2,872.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 5.000 $1,740.000 $2,879.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 2.000 $3,270.000 $3,127.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 13.000 $2,700.000 $3,129.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $3,800.000 $5,090.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $5,712.000 $5,829.000
SET (TY II) (36 IN) (RCP) (4: 1) (P)
EA 2.000 $6,397.000 $6,182.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $7,650.000 $8,868.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 1.000 $6,900.000 $11,925.000
SET (TY II) (48 IN) (RCP) (4: 1) (P)
EA 7.000 $8,000.000 $14,621.000
SET (TY II) (48 IN) (RCP) (6: 1) (P)
EA 4.000 $8,333.000 $16,818.000
SET (TY II) (60 IN) (RCP) (4: 1) (P)
EA 1.000 $17,500.000 $23,675.000
CLEAN EXIST CULVERTS
EA 8.000 $1,625.000 $12,500.000
MILLING CONCRETE SLAB (1 IN)
SY 588.000 $15.000 $27.870
MILLING CONCRETE SLAB (1/4IN)
SY 2,436.000 $15.000 $21.790
REMOV STR (INLET)
EA 12.000 $1,200.000 $4,500.000
REMOV STR (SET)
EA 44.000 $501.000 $4,250.000
REMOV STR (WINGWALL)
EA 24.000 $1,565.000 $12,500.000
REMOV STR (HEADWALL)
EA 13.000 $1,450.000 $4,900.000
REMOV STR (PIPE)
LF 6,479.000 $33.000 $39.500
REMOV STR (BOX CULVERT)
LF 32.000 $128.000 $495.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $192,800.000 $375,000.000
REMOVE STR (JUNCTION BOX)
EA 11.000 $2,500.000 $2,900.000
REMOV STR (SMALL FENCE)
LF 4,848.000 $4.400 $7.750
MOBILIZATION
LS 1.000 $20,000,000.000 $31,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 55.000 $45,000.000 $96,425.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 152.000 $125.000 $85.000
ROCK FILTER DAMS (REMOVE)
LF 152.000 $13.000 $25.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 3,120.000 $45.000 $32.000
CONSTRUCTION EXITS (REMOVE)
SY 3,120.000 $10.000 $25.000
BLADING WORK (EROSION & SEDMT CONT)
HR 1,913.000 $175.000 $65.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 6,186.000 $7.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 9,679.000 $11.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 15,865.000 $1.600 $1.500
CONSTRUCTING DETOURS (TY 1)
SY 111,665.000 $150.000 $136.880
CONSTRUCTING DETOURS (TY 2)
SY 23,451.000 $150.000 $140.730
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 67,500.000 $72.000 $107.220
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 22,540.000 $11.800 $14.660
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 720.000 $13.900 $61.540
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 336,840.000 $11.000 $8.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 13,300.000 $11.000 $20.690
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 620.000 $11.000 $20.690
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 67,500.000 $20.000 $7.230
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 22,540.000 $13.400 $6.370
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 720.000 $14.600 $56.660
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 23,528.000 $162.000 $149.000
PERM CTB (SGL SLOPE) (TY 1) SPECIAL
LF 40.000 $255.000 $475.000
PERM CTB (SGL SLOPE) (TY 3) SPECIAL
LF 106.500 $165.000 $535.000
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
LF 140.000 $395.000 $405.000
REMOVE AND RELAY PAVERS
SY 403.000 $100.000 $92.260
CONC CURB & GUTTER (TY II)
LF 2,136.000 $25.500 $52.550
DRIVEWAYS (ACP)
SY 5,976.000 $92.000 $118.250
MTL W-BEAM GD FEN (STEEL POST)
LF 2,600.000 $37.000 $38.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 41.000 $2,415.000 $3,099.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 11.000 $1,565.000 $2,270.000
REMOVE METAL BEAM GUARD FENCE
LF 6,500.000 $3.000 $3.750
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $322.000 $525.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 15.000 $334.000 $525.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 3.000 $352.000 $825.000
CABLE BARRIER SYSTEM (TL-4)
LF 1,800.000 $18.000 $18.750
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 4.000 $6,000.000 $3,100.000
REMOVE CABLE BARRIER
LF 33,440.000 $4.700 $5.000
REMOVE CABLE BARRIER TERMINAL SECTION
EA 18.000 $613.000 $560.000
GUARDRAIL END TREATMENT (INSTALL)
EA 52.000 $3,600.000 $3,300.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $319.000 $740.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 48.000 $3,500.000 $5,544.000
CRASH CUSH ATTEN (REMOVE)
EA 38.000 $2,000.000 $3,750.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 7.000 $27,500.000 $46,800.000
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
EA 1.000 $34,000.000 $52,420.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 31.000 $13,500.000 $20,988.000
REMOVE RD IL ASM (TRANS-BASE)
EA 40.000 $1,238.000 $3,200.000
HI MST IL POLE (150 FT)(100 MPH)
EA 60.000 $61,000.000 $63,700.000
CONDT (PVC) (SCH 40) (2")
LF 585.000 $22.000 $22.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 250.000 $34.000 $38.000
CONDT (PVC) (SCH 40) (3")
LF 270.000 $50.000 $30.000
CONDT (PVC) (SCH 40) (3") (BORE)
LF 450.000 $72.000 $42.500
CONDT (PVC) (SCH 80) (2")
LF 36,390.000 $29.000 $21.500
CONDT (PVC) (SCH 80) (2") (BORE)
LF 8,840.000 $42.000 $33.500
ELEC CONDR (NO.14) INSULATED
LF 39,830.000 $1.040 $1.870
ELEC CONDR (NO.8) BARE
LF 30,350.000 $2.000 $2.330
ELEC CONDR (NO.8) INSULATED
LF 81,662.000 $2.100 $2.550
ELEC CONDR (NO.6) BARE
LF 12,095.000 $2.400 $2.650
ELEC CONDR (NO.6) INSULATED
LF 35,670.000 $3.000 $2.970
ELEC CONDR (NO.4) BARE
LF 4,805.000 $4.000 $3.250
ELEC CONDR (NO.4) INSULATED
LF 10,145.000 $5.000 $3.650
GROUND BOX TY A (122311)W/APRON
EA 220.000 $1,875.000 $1,463.000
REMOVE GROUND BOX
EA 3.000 $365.000 $4,500.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $500.000 $12,500.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 10.000 $9,000.000 $9,350.000
ELC SRV TY D 120/240 060(NS)AL(N)SP(O)
EA 4.000 $9,000.000 $7,725.000
ALUMINUM SIGNS (TY G)
SF 2,173.000 $39.000 $36.500
ALUMINUM SIGNS (TY O)
SF 4,346.890 $39.000 $39.750
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $900.000 $3,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 1.000 $1,200.000 $3,250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 227.000 $1,150.000 $1,155.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $1,500.000 $3,044.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 6.000 $1,700.000 $2,250.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 26.000 $1,700.000 $1,672.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 22.000 $1,850.000 $1,809.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 8.000 $620.000 $945.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 12.000 $4,600.000 $2,927.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 6.000 $4,000.000 $3,126.000
REMOVE SM RD SN SUP&AM
EA 130.000 $200.000 $300.000
INSTALL LRSS (STRUCT STEEL)
LB 10,898.100 $10.000 $19.250
REMOVE LRSA
EA 24.000 $2,500.000 $3,500.000
INS OH SN SUP(25 FT CANT)
EA 4.000 $46,000.000 $41,250.000
INS OH SN SUP(30 FT CANT)
EA 5.000 $49,500.000 $46,500.000
INS OH SN SUP(35 FT BAL TEE)
EA 1.000 $64,000.000 $48,750.000
INS OH SN SUP(35 FT CANT)
EA 1.000 $54,000.000 $49,200.000
INS OH SN SUP(40 FT CANT)
EA 6.000 $59,000.000 $54,250.000
INS OH SN SUP(60 FT BRDG)
EA 1.000 $63,000.000 $61,000.000
INS OH SN SUP(75 FT BRDG)
EA 2.000 $73,000.000 $74,450.000
INS OH SN SUP(85 FT BRDG)
EA 2.000 $90,000.000 $87,450.000
REMOVE OVERHD SIGN SUP
EA 1.000 $7,900.000 $12,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 130.000 $20.000 $33.560
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 221.000 $43.000 $32.020
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 240.000 $41.000 $14.040
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 55.000 $40.000 $32.610
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 23.000 $41.000 $56.900
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 71.000 $150.000 $129.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GND
EA 14.000 $150.000 $229.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
EA 79.000 $150.000 $129.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 89.000 $150.000 $129.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 38,738.000 $0.700 $0.170
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 331.000 $1.290 $0.970
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 235,692.000 $0.700 $0.170
WK ZN PAV MRK NON-REMOV(W)18"(YLD TRI)
EA 62.000 $35.000 $1.010
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 183,945.000 $0.700 $0.170
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 48,329.000 $2.000 $0.500
WK ZN PAV MRK REMOV (W)6"(DOT)
LF 572.000 $2.000 $0.500
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 253,322.000 $1.400 $0.550
WK ZN PAV MRK REMOV (W)18"(YLD TRI)
EA 64.000 $35.000 $100.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 232,695.000 $1.400 $0.500
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 2,211.000 $3.000 $1.090
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,653.000 $3.200 $1.910
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 10,198.000 $5.300 $2.720
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 826.000 $11.000 $7.060
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 3.000 $200.000 $257.630
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 5.000 $300.000 $349.550
REFL PAV MRK TY I (W)(NUMBER)(100MIL)
EA 30.000 $286.000 $262.680
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $300.000 $255.610
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 20.000 $2,000.000 $1,971.540
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 19.000 $2,700.000 $2,224.300
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 84.000 $53.000 $35.390
PAVEMENT SEALER 6"
LF 206,798.000 $0.350 $0.110
PAVEMENT SEALER 12"
LF 10,952.000 $1.500 $0.120
PAVEMENT SEALER 24"
LF 409.000 $3.000 $1.960
PAVEMENT SEALER (ARROW)
EA 2.000 $50.000 $386.950
PAVEMENT SEALER (WORD)
EA 10.000 $50.000 $406.270
PAVEMENT SEALER (UTURN ARROW)
EA 5.000 $50.000 $331.440
PAVEMENT SEALER (ENTR GORE)
EA 20.000 $580.000 $189.320
PAVEMENT SEALER (EXIT GORE)
EA 19.000 $705.000 $183.990
PAVEMENT SEALER (YLD TRI)
EA 84.000 $53.000 $92.570
PAVEMENT SEALER (NUMBER)
EA 30.000 $45.000 $191.020
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 126,338.000 $0.780 $0.810
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 127,191.000 $0.780 $0.810
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 2,638.000 $3.000 $2.920
PLOWABLE REFL PAV MRKR TY II-C-R
EA 3,706.000 $108.000 $25.280
REFL PAV MRKR TY II-A-A
EA 96.000 $7.000 $4.900
ELIM EXT PAV MRK & MRKS (6")
LF 233,052.000 $0.600 $0.120
ELIM EXT PAV MRK & MRKS (18")(YLD TRI)
EA 61.000 $25.000 $1.290
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 12,635.000 $33.000 $0.120
PAV SURF PREP FOR MRK (6")
LF 206,798.000 $0.100 $0.150
PAV SURF PREP FOR MRK (12")
LF 10,952.000 $0.200 $0.150
PAV SURF PREP FOR MRK (24")
LF 409.000 $1.000 $0.150
PAV SURF PREP FOR MRK (ARROW)
EA 1.000 $25.000 $15.170
PAV SURF PREP FOR MRK (UTURN ARR)
EA 5.000 $25.000 $40.440
PAV SURF PREP FOR MRK (NUMBER)
EA 30.000 $25.000 $12.130
PAV SURF PREP FOR MRK (WORD)
EA 10.000 $25.000 $12.130
PAV SURF PREP FOR MRK (ENTR GORE)
EA 20.000 $300.000 $25.280
PAV SURF PREP FOR MRK (EXIT GORE)
EA 19.000 $300.000 $25.280
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 84.000 $25.000 $5.060
CRACK CLEANING AND SEALING (JCP)
LF 1,268.000 $18.600 $30.810
FULL - WIDTH MOWING
CYC 15.000 $8,000.000 $5,500.000
CLEAN/SWEEP AREA 1
CYC 40.000 $5,000.000 $3,500.000
ANTI - GRAFFITI COATING(PERMNENT-TY II)
SF 4,941.000 $0.700 $3.440
DRAIN INLET CLEANING
EA 4.000 $750.000 $3,500.000
D-GR HMA TY-B PG64-22
TON 103,934.000 $142.000 $255.270
D-GR HMA TY-B PG64-22 (LEVEL-UP)
TON 1,206.900 $180.000 $325.000
SP MIXES SP-D SAC-A PG70-28
TON 50,978.000 $156.000 $305.470
TACK COAT
GAL 56,817.000 $7.000 $14.040
POLYESTER POLYMER CONC OVERLAY (1")
SY 3,023.000 $105.000 $164.380
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $1,300.000 $1,500.000
PATCHING MILLED CONCRETE RUMBLE STRIPS
LF 9,986.000 $33.000 $11.250
FILLING MILLED ASPHALT RUMBLE STRIPS
LF 9,635.000 $33.000 $13.250
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $19,000.000 $32,015.000
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
LF 43,205.000 $3.300 $5.760
FIBER OPTIC CBL (SNGLE-MODE)(144 FIBER)
LF 38,515.000 $4.750 $6.830
FIBER OPTIC SPLICE ENCLOSURE
EA 1.000 $1,500.000 $2,574.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 9.000 $1,500.000 $1,245.000
FIBER OPTIC CABLE ROAD MARKER
EA 51.000 $250.000 $226.000
FIBER OPTIC PATCH PANEL (144 POSITION)
EA 1.000 $2,400.000 $7,264.000
ITS GRND MNT CAB (TY 4) (CONF 1)
EA 2.000 $20,500.000 $14,258.000
ITS GRND MNT CAB (TY 5) (CONF 2)
EA 1.000 $23,000.000 $17,454.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 4.000 $19,000.000 $7,942.000
CCTV MOUNT (POLE)
EA 4.000 $1,800.000 $1,500.000
ITS MULTI-DUCT CND (PVC-40)
LF 31,090.000 $28.000 $37.500
ITS MULTI-DUCT CND (PVC-40)(BORE)
LF 5,240.000 $48.000 $63.000
PREFB PV MK W/WNTY TY B(W)6"(BRK)CNTST
LF 49,782.000 $18.000 $14.410
CONDUIT (PREPARE)
LF 2,635.000 $3.000 $3.240
GROUND BOX (PREPARE)
EA 10.000 $920.000 $1,000.000
INSTALL DMS (FOUNDATION MTD CABINET)
EA 2.000 $29,000.000 $17,568.000
ITS POLE (50 FT)(90 MPH)
EA 2.000 $19,500.000 $19,750.000
ITS POLE MNT CAB (TY 2)(CONF 1)
EA 2.000 $9,000.000 $8,500.000
ETHERNET SWITCH (INSTALL ONLY)
EA 6.000 $175.000 $750.000
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
EA 60.000 $34,000.000 $37,850.000
REMOVE EXISTING CABLES (FIBER)
LF 2,635.000 $0.500 $2.000
TMA (STATIONARY)
DAY 67.000 $292.000 $1,210.000
TMA (MOBILE OPERATION)
HR 480.000 $90.000 $128.000
ITS GND BOX(PCAST) TY 1 (243648)W/APRN
EA 75.000 $4,500.000 $5,426.000
TEMP Q-DETECT SYS
EA 3.000 $100,000.000 $225,000.000
REMOVE DYNAMIC MESSAGE SIGN SYSTEM
EA 1.000 $11,000.000 $32,000.000
REMOVE HIGH MAST LIGHTING ASSEMBLY
EA 3.000 $8,250.000 $28,955.000
Totals: $235,609,131.260 $312,507,980.854