Bid Cobra

PRESIDIO CS (0924-07-017)

Items: 37

County: PRESIDIO
Length: N/A
Highway: CS
District: EL PASO
Control Number: 0924-07-017
DBE Goal: N/A
Project: STP 2020(072)TP
Guaranty: N/A
Time: 49 WORKING DAYS
Engineer's Estimate: $470,999.11
Date: 04/09/2020 (6 years ago)
Contract Number: N/A
Type: CONSTRUCTION OF SHARED USE PATH AND SIDEWALKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$470,999.11
$531,477.00
Over/Under Est: 12.84% $60,477.89
$549,460.10
Over/Under Est: 16.66% $78,460.99
Amt Left: 3.38% $17,983.10
Over/Under Est: 27.36% $128,878.89
Amt Left: 12.87% $68,401.00
Delta: -9.18% -$50,417.90
Over/Under Est: 35.74% $168,325.04
Amt Left: 20.29% $107,847.15
Delta: -6.58% -$39,446.15
Over/Under Est: 111.39% $524,645.09
Amt Left: 87.34% $464,167.20
Delta: -55.73% -$356,320.05

Bid Items & Bid Tabulations

37 Total 0 of 37
PRESIDIO  |  CS  |  EL PASO  |  0924-07-017  |  04/09/2020  |  $470,999.11  |  STP 2020(072)TP  |  CONSTRUCTION OF SHARED USE PATH AND...  |  49 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
MIJELUM, L.L.C.
ENCINO LANDSCAPE, INC.
TI-ZACK CONCRETE, INC.
EARTH BUILDERS, L.P.
PREPARING ROW
STA 28.000 $2,000.000 $1,400.000 $5,500.000 $5,000.000 $1,500.000 $6,500.000
REMOVING CONC (DRIVEWAYS)
SY 93.000 $15.000 $30.000 $15.000 $20.000 $35.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 10.250 $50.000 $150.000 $150.000 $30.000 $75.000 $100.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 24.000 $250.000 $400.000 $200.000 $300.000 $350.000 $600.000
ADJUSTING MANHOLES (TELEPHONE BOX)
EA 2.000 $3,375.000 $950.000 $2,000.000 $1,000.000 $250.000 $2,000.000
MOBILIZATION
LS 1.000 $46,073.880 $50,000.000 $25,000.000 $49,000.000 $28,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $8,000.000 $5,000.000 $5,000.000 $7,500.000 $2,500.000 $5,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,437.000 $5.000 $3.500 $3.000 $1.000 $0.100 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,437.000 $1.000 $1.250 $1.000 $1.000 $0.100 $3.000
CONC SIDEWALKS (4")
SY 2,991.000 $55.860 $80.000 $60.000 $80.000 $120.000 $130.000
CONC SIDEWALKS (6")
SY 288.000 $70.000 $90.000 $80.000 $80.000 $135.000 $175.000
CURB RAMPS (TY 1)
EA 2.000 $1,600.000 $1,500.000 $2,500.000 $1,700.000 $1,500.000 $4,000.000
CURB RAMPS (TY 7)
EA 3.000 $1,700.000 $1,500.000 $2,500.000 $1,700.000 $1,500.000 $4,000.000
CURB RAMPS (TY 10)
EA 6.000 $1,700.000 $1,500.000 $2,600.000 $1,700.000 $1,500.000 $4,000.000
CURB RAMPS (TY 7)(MOD)
EA 7.000 $2,700.000 $2,500.000 $2,990.000 $2,100.000 $1,500.000 $4,000.000
CURB RAMP (TY 1) (MOD)
EA 1.000 $2,200.000 $2,500.000 $3,000.000 $2,100.000 $1,500.000 $4,000.000
IN RD IL (TY SA) 40T-10 (250W EQ) LED
EA 3.000 $4,340.000 $5,500.000 $3,550.000 $5,000.000 $10,000.000 $9,000.000
CONDT (PVC) (SCH 40) (2")
LF 701.000 $14.500 $18.000 $10.000 $10.000 $18.000 $25.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 64.000 $30.000 $65.000 $20.000 $78.000 $45.000 $100.000
ELEC CONDR (NO.12) INSULATED
LF 1,610.000 $2.750 $1.250 $1.500 $1.000 $2.000 $2.400
ELEC CONDR (NO.8) INSULATED
LF 805.000 $2.500 $2.250 $1.600 $1.500 $3.000 $3.000
GROUND BOX TY A (122311)W/APRON
EA 5.000 $1,400.000 $1,600.000 $900.000 $800.000 $850.000 $1,200.000
ELC SRV TY A 120/240 060(NS)AL(E)SP(O)
EA 1.000 $5,966.370 $7,500.000 $6,000.000 $7,500.000 $30,000.000 $15,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $600.000 $900.000 $600.000 $500.000 $800.000 $1,200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $775.000 $1,000.000 $900.000 $600.000 $800.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 6.000 $600.000 $1,000.000 $580.000 $600.000 $800.000 $2,500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $500.000 $750.000 $790.000 $400.000 $800.000 $2,000.000
REMOVE SM RD SN SUP&AM
EA 4.000 $400.000 $200.000 $98.000 $100.000 $80.000 $800.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 86.000 $0.750 $2.250 $1.000 $1.000 $25.000 $9.000
PAVEMENT SEALER 4"
LF 1,813.000 $0.500 $1.500 $0.550 $1.000 $1.000 $1.500
PAVEMENT SEALER 8"
LF 86.000 $0.750 $3.000 $1.000 $1.000 $2.000 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,813.000 $0.700 $4.000 $0.350 $1.000 $2.000 $2.500
PAV SURF PREP FOR MRK (4")
LF 1,813.000 $1.000 $1.000 $0.500 $1.000 $1.000 $1.000
PAV SURF PREP FOR MRK (8")
LF 86.000 $5.000 $1.000 $0.400 $1.000 $1.000 $1.200
TMA (STATIONARY)
DAY 61.000 $500.000 $150.000 $400.000 $200.000 $100.000 $350.000
ADJUST WATER VALVE BOX
EA 3.000 $275.000 $1,000.000 $2,000.000 $500.000 $350.000 $800.000
REMOVE AND RELOCATE FIRE HYDRANT
EA 1.000 $2,100.000 $9,500.000 $5,000.000 $6,000.000 $7,000.000 $5,000.000
Totals: $470,999.110 $531,477.000 $549,460.100 $599,878.000 $639,324.150 $995,644.200