PARKER IH 20 (0008-03-144)
Items: 21
County: PARKER
Length: 0.0000 MILES (0.1023 MILES)
Highway: IH 20
District: FORT WORTH
Control Number: 0008-03-144
DBE Goal: 0.0%
Project: F 2026(728)
Guaranty: $8,000.00
Time: 36 WORKING DAYS
Engineer's Estimate: $375,912.50
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263233
Type: LANDSCAPE DEVELOPMENT
Project ID: A00217109
Contract Type: FEDERAL
Project Description: FY 2026 GREEN RIBBON PROJECT: LANDSCAPE ENHANCEMENT- FIH 20 FROM MIKUS RD TO EAST OF MIKUS RD CITY OF WILLOW PARK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
PARKER IH 20 (0008-03-144)
Project Name: N/A
Project: F 2026(728)
Engineer's Estimate: $375,912.50
Length: 0.0000 MILES (0.1023 MILES)
Project Class: LANDSCAPE & SCENIC ENHANCEMENT
Limits From: MIKUS ROAD
Limits To: EAST OF MIKUS ROAD
Project Description: FY 2026 GREEN RIBBON PROJECT: LANDSCAPE ENHANCEMENT- FIH 20 FROM MIKUS RD TO EAST OF MIKUS RD CITY OF WILLOW PARK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$375,912.50 | |||
| $291,493.75 |
-22.46%
-$84,418.75
|
|||
| $326,470.50 |
-13.15%
-$49,442.00
|
12%
$34,976.75
|
||
| $336,570.00 |
-10.47%
-$39,342.50
|
15.46%
$45,076.25
|
-3.09%
-$10,099.50
|
|
| $355,433.75 |
-5.45%
-$20,478.75
|
21.94%
$63,940.00
|
-5.60%
-$18,863.75
|
|
| $379,676.26 |
1%
$3,763.76
|
30.25%
$88,182.51
|
-6.82%
-$24,242.51
|
|
| $456,909.29 |
21.55%
$80,996.79
|
56.75%
$165,415.54
|
-20.34%
-$77,233.03
|
|
| $473,845.07 |
26.05%
$97,932.57
|
62.56%
$182,351.32
|
-3.71%
-$16,935.78
|
E
Engineer's Estimate
$375,912.50
$291,493.75
Over/Under Est:
-22.46%
-$84,418.75
$326,470.50
Over/Under Est:
-13.15%
-$49,442.00
Amt Left:
12%
$34,976.75
$336,570.00
Over/Under Est:
-10.47%
-$39,342.50
Amt Left:
15.46%
$45,076.25
Delta:
-3.09%
-$10,099.50
$355,433.75
Over/Under Est:
-5.45%
-$20,478.75
Amt Left:
21.94%
$63,940.00
Delta:
-5.60%
-$18,863.75
$379,676.26
Over/Under Est:
1%
$3,763.76
Amt Left:
30.25%
$88,182.51
Delta:
-6.82%
-$24,242.51
$456,909.29
Over/Under Est:
21.55%
$80,996.79
Amt Left:
56.75%
$165,415.54
Delta:
-20.34%
-$77,233.03
$473,845.07
Over/Under Est:
26.05%
$97,932.57
Amt Left:
62.56%
$182,351.32
Delta:
-3.71%
-$16,935.78
Bid Items & Bid Tabulations
21
Total
0 of 21
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $10,000.00 |