MORRIS VARIOUS (0919-20-033)
Items: 33
County: MORRIS
Length: 0.1000 MILES
Highway: VARIOUS
District: ATLANTA
Control Number: 0919-20-033
DBE Goal: 0.0%
Project: C 919-20-33
Guaranty: $6,000.00
Time: 75 WORKING DAYS
Engineer's Estimate: $276,302.05
Date: 08/07/2025 1:00 PM CDT (11 months ago)
Contract Number: 8253026
Type: CONSTRUCT PARKING FOR CABINS & LODG
Project ID: A00043462
Project Description: CONSTRUCT PARKING FOR CABINS AND BASS LODGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
WENDY STARKES
OSCAR FLORES
MORRIS VARIOUS (0919-20-033)
Project Name: N/A
Project: C 919-20-33
Length: 0.1000 MILES
Project Class: CONSTRUCTION
Limits From: AT DAINGERFIELD STATE PARK
Limits To: .
Project Description: CONSTRUCT PARKING FOR CABINS AND BASS LODGE
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$276,302.05 | |||
| $246,934.93 |
-10.63%
-$29,367.12
|
|||
| $397,457.00 |
43.85%
$121,154.95
|
60.96%
$150,522.07
|
||
| $444,776.00 |
60.97%
$168,473.95
|
80.12%
$197,841.07
|
-11.91%
-$47,319.00
|
|
| $500,564.25 |
81.17%
$224,262.20
|
102.71%
$253,629.32
|
-12.54%
-$55,788.25
|
|
| $825,542.13 |
198.78%
$549,240.08
|
234.32%
$578,607.20
|
-64.92%
-$324,977.88
|
E
Engineer's Estimate
$276,302.05
1
Awarded
$246,934.93
Over/Under Est:
-10.63%
-$29,367.12
$397,457.00
Over/Under Est:
43.85%
$121,154.95
Amt Left:
60.96%
$150,522.07
$444,776.00
Over/Under Est:
60.97%
$168,473.95
Amt Left:
80.12%
$197,841.07
Delta:
-11.91%
-$47,319.00
$500,564.25
Over/Under Est:
81.17%
$224,262.20
Amt Left:
102.71%
$253,629.32
Delta:
-12.54%
-$55,788.25
$825,542.13
Over/Under Est:
198.78%
$549,240.08
Amt Left:
234.32%
$578,607.20
Delta:
-64.92%
-$324,977.88
Bid Items & Bid Tabulations
33
Total
0 of 33
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| Total: | $10,000.00 |