MONTGOMERY IH 45 (0675-08-111)

Items: 48

County: MONTGOMERY
Length: N/A
Highway: IH 45
District: HOUSTON
Control Number: 0675-08-111
DBE Goal: N/A
Project: NH 2020(596)
Guaranty: N/A
Time: 270 WORKING DAYS
Engineer's Estimate: $2,365,921.88
Date: 04/09/2020 (6 years ago)
Contract Number: N/A
Type: INSTALL ITS EQUIPMENT AND INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,365,921.88
1
Awarded
$2,147,330.65
Over/Under Est: -9.24% -$218,591.23
$2,152,836.97
Over/Under Est: -9.01% -$213,084.91
Amt Left: 0.26% $5,506.32
Over/Under Est: 12.98% $307,014.54
Amt Left: 24.48% $525,605.77
Delta: -24.16% -$520,099.45
$2,802,024.24
Over/Under Est: 18.43% $436,102.36
Amt Left: 30.49% $654,693.59
Delta: -4.83% -$129,087.82
Over/Under Est: 36.72% $868,801.86
Amt Left: 50.64% $1,087,393.09
Delta: -15.44% -$432,699.50
Subcontractor Percentage Amount
USA AMTECH, INC. 10.84% $243,872.68
ODUM SERVICES, LLC 3.63% $81,665.85
THIRD COAST SERVICES LLC 2.03% $45,669.88
GROUND HOG FOUNDATION DRILLING 1.72% $38,695.67
Total: 18.22% $409,904.08

Bid Items & Bid Tabulations

48 Total 0 of 48
MONTGOMERY  |  IH 45  |  HOUSTON  |  0675-08-111  |  04/09/2020  |  $2,365,921.88  |  NH 2020(596)  |  INSTL ITS EQUIPMENT AND INFRASTRUCT  |  270 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SICE, INC.
TRAF-TEX, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
MICA CORPORATION
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
DRILL SHAFT (42 IN)
LF 312.000 $300.000 $497.609 $572.000 $543.650 $280.250 $378.360
DRILL SHAFT (54 IN)
LF 54.000 $330.000 $692.004 $655.000 $730.860 $424.000 $501.800
RIPRAP (MOW STRIP)(4 IN)
CY 60.000 $465.000 $450.829 $715.000 $773.590 $788.000 $777.500
MOBILIZATION
LS 1.000 $260,000.000 $203,921.860 $79,880.000 $267,017.690 $177,500.000 $334,617.980
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $6,000.000 $7,151.667 $1,947.000 $981.300 $9,940.000 $10,075.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $2.400 $3.248 $3.900 $4.170 $2.850 $5.820
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $0.800 $1.129 $0.570 $1.790 $1.950 $2.420
MTL W-BEAM GD FEN (TIM POST)
LF 1,050.000 $21.000 $25.488 $24.200 $20.900 $21.550 $27.180
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,200.000 $1,171.230 $1,485.000 $1,249.650 $1,323.000 $1,265.250
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,600.000 $3,398.387 $2,750.000 $3,101.520 $2,688.000 $9,091.000
CONDT (PVC) (SCH 40) (3")
LF 8,664.000 $10.700 $7.381 $11.000 $10.790 $14.150 $12.010
CONDT (PVC) (SCH 80) (2")
LF 6,535.000 $7.700 $12.122 $13.050 $7.890 $9.250 $10.780
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,955.000 $12.500 $20.291 $26.600 $20.050 $36.260 $25.900
CONDT (PVC) (SCH 80) (3")
LF 280.000 $12.500 $6.237 $14.800 $12.840 $8.900 $15.060
CONDT (PVC) (SCH 80) (3") (BORE)
LF 1,190.000 $20.000 $21.117 $26.650 $45.240 $24.000 $27.790
ELEC CONDR (NO.14) INSULATED
LF 151,166.000 $0.700 $0.364 $0.700 $0.700 $1.050 $1.000
ELEC CONDR (NO.8) BARE
LF 645.000 $1.000 $0.702 $1.050 $0.890 $1.200 $1.200
ELEC CONDR (NO.8) INSULATED
LF 1,310.000 $1.100 $0.697 $1.250 $0.970 $1.250 $1.260
ELEC CONDR (NO.6) BARE
LF 760.000 $1.200 $1.010 $1.200 $1.030 $1.300 $1.430
ELEC CONDR (NO.6) INSULATED
LF 2,010.000 $1.260 $1.102 $1.550 $1.210 $1.400 $1.530
ELEC CONDR (NO.4) BARE
LF 1,426.000 $1.600 $1.016 $1.650 $1.510 $1.500 $1.760
ELEC CONDR (NO.4) INSULATED
LF 2,852.000 $1.840 $1.127 $1.800 $1.580 $1.550 $1.790
ELEC CONDR (NO.2) BARE
LF 3,966.000 $2.000 $1.467 $2.500 $2.010 $2.300 $1.900
ELEC CONDR (NO.2) INSULATED
LF 7,932.000 $2.300 $1.526 $2.900 $2.200 $2.360 $2.270
GROUND BOX TY A (122311)
EA 34.000 $500.000 $795.130 $594.000 $374.420 $732.000 $896.650
ELC SRV TY D 120/240 100(NS)SS(N)SP(O)
EA 12.000 $4,000.000 $4,007.844 $4,009.000 $3,850.970 $5,935.000 $5,555.000
INS OH SN SUP(35 FT BAL TEE)
EA 2.000 $24,000.000 $31,503.394 $29,668.000 $30,518.500 $33,465.000 $31,347.000
SIGN WALKWAY (36 IN) WITH HNDRL
LF 62.000 $300.000 $320.110 $350.000 $417.660 $140.000 $313.500
FIBER OPTIC CBL (SNGLE-MODE)(6 FIBER)
LF 39,000.000 $2.000 $0.857 $1.700 $2.270 $3.200 $3.710
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
LF 21,371.000 $2.800 $0.982 $1.830 $2.800 $3.190 $4.000
FIBER OPTIC CBL (SNGLE-MODE)(144 FIBER)
LF 42,624.000 $3.700 $2.473 $2.800 $3.660 $3.660 $5.620
FIBER OPTIC PATCH PANEL (144 POSITION)
EA 3.000 $3,000.000 $5,928.323 $5,420.000 $506.720 $4,191.000 $12,317.000
FIBER OPTIC FUSION SPLICE
EA 468.000 $60.000 $18.200 $27.350 $34.840 $37.300 $37.530
CCTV FIELD EQUIPMENT (ANALOG)
EA 13.000 $8,000.000 $7,437.080 $9,764.000 $8,396.890 $10,815.000 $9,528.150
REMOVE CCTV FIELD EQUIPMENT
EA 1.000 $1,350.000 $857.080 $1,620.000 $290.430 $1,564.000 $1,210.000
ITS MULTI-DUCT CND (PVC-40)
LF 9,144.000 $15.000 $10.308 $13.450 $14.140 $19.060 $27.330
ITS MULTI-DUCT CND (PVC-80)
LF 180.000 $14.300 $11.150 $14.000 $22.280 $19.400 $28.480
ITS MULTI-DUCT CND (PVC-80)(BORE)
LF 1,484.000 $33.000 $24.828 $54.350 $52.380 $38.480 $35.830
COMMUNICATION HUB BUILDING
EA 3.000 $26,000.000 $30,158.566 $20,105.000 $26,269.730 $31,210.000 $25,165.000
CONDUIT (PREPARE)
LF 123,628.000 $1.600 $1.000 $0.530 $2.910 $2.060 $1.590
INSTALL DMS (FOUNDATION MTD CABINET)
EA 2.000 $13,800.000 $10,407.998 $13,440.000 $8,017.500 $23,910.000 $13,987.500
RADAR VEHICLE SENSING DEVICE
EA 5.000 $8,700.000 $8,628.643 $11,145.000 $6,794.870 $11,713.000 $11,344.000
FIBER OPTIC VIDEO DATA TRANSMITTER
EA 13.000 $1,400.000 $1,410.033 $1,180.000 $1,348.730 $2,644.000 $3,367.500
FIBER OPTIC VIDEO DATA RECEIVER
EA 13.000 $1,400.000 $1,410.033 $1,180.000 $1,348.730 $2,644.000 $3,460.380
ITS POLE (55 FT)(110 MPH)
EA 13.000 $14,600.000 $13,115.783 $11,515.000 $13,061.740 $12,675.000 $16,361.350
ITS POLE MNT CAB (TY 2)(CONF 1)
EA 13.000 $5,200.000 $3,385.918 $6,863.000 $5,421.070 $5,881.000 $6,546.000
TMA (STATIONARY)
DAY 240.000 $200.000 $469.525 $222.000 $451.870 $155.200 $234.500
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 13.000 $2,750.000 $3,261.681 $3,045.000 $2,703.470 $3,260.000 $4,497.900
Totals: $2,365,921.880 $2,147,330.781 $2,152,836.970 $2,672,936.420 $2,802,024.240 $3,234,723.740