Job Info for 0055-15-079

County: MCLENNAN Highway: US 84 Date: 09/05/2024 (2 months ago) Engineer's Estimate: $8,243,562 Control Number: 0055-15-079
Project: F 2B24(523) District: WACO Time: 135 WORKING DAYS Type: REHABILITATE EXISTING ROADWAY
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $8,243,561.94
SILVER CREEK CONSTRUCTION, INC.   $8,584,310.10 1
4.13% | $340,748.16
BIG CREEK CONSTRUCTION, LTD.   $10,190,652.45 2
23.62% | $1,947,090.51
18.71% | $1,606,342.35
KNIFE RIVER CORPORATION - SOUTH   $10,411,607.05 3
26.3% | $2,168,045.11
21.29% | $1,827,296.95
2.17% | $220,954.60
TEXAS MATERIALS GROUP, INC.   $10,421,995.77 4
26.43% | $2,178,433.83
21.41% | $1,837,685.67
0.10% | $10,388.72

Bid Items

Items: 47, 0 filtered
MCLENNAN US 84  |  WACO  |  0055-15-079  |  09/05/2024  |  $8,243,562  |  F 2B24(523)  |  REHAB EXIST ROADWAY  |  135 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SILVER CREEK CONSTRUCTION, INC. BIG CREEK CONSTRUCTION, LTD. KNIFE RIVER CORPORATION - SOUTH TEXAS MATERIALS GROUP, INC.
104 7016 REMOV CONC (CURB) LF 2,000.000 $45.000 $20.000 $40.000 $33.000 $10.000
347 7001 TOM-C PG76-22 SAC-A TON 10,591.000 $188.660 $183.000 $180.000 $168.650 $220.000
347 7009 TOM-F PG76-28 SAC-B TON 5,296.000 $131.400 $203.000 $180.000 $187.850 $265.000
347 7011 TACK COAT GAL 57,774.000 $7.090 $4.400 $4.000 $4.150 $3.000
354 7045 PLANE ASPH CONC PAV(0" TO 1" MICRO) SY 5,269.000 $3.000 $4.500 $10.000 $7.850 $10.300
354 7062 PLANE CONC PAV(0" TO 0.5") SY 203,434.000 $6.480 $4.500 $5.000 $4.100 $4.000
361 7004 FULL - DEPTH REPAIR CRCP (9") CY 1,883.000 $750.000 $820.000 $1,500.000 $1,230.000 $1,075.000
400 7010 CEM STABIL BKFL CY 20.000 $255.000 $400.000 $300.000 $200.000 $350.000
420 7052 CL C CONC (RAIL FOUNDATION) CY 27.000 $318.800 $1,200.000 $1,300.000 $1,090.000 $1,800.000
429 7003 CONC STR REPAIR(DECK REP(PART DEPTH)) SF 412.000 $155.000 $155.000 $200.000 $141.000 $130.000
438 7004 CLEANING AND SEALING EXIST JOINTS (CL3) LF 112.000 $50.000 $50.000 $40.000 $58.850 $68.000
438 7007 CLEANING AND SEALING EXIST JOINTS (CL7) LF 1,782.000 $50.000 $22.000 $50.000 $67.000 $56.000
438 7008 CLEANING EXISTING JOINTS LF 198.000 $20.000 $5.000 $20.000 $29.400 $24.000
439 7014 MULTI-LAYER POLYMER OVERLAY SY 5,269.000 $49.000 $35.000 $70.000 $47.000 $45.000
450 7036 RAIL (TY C402) LF 190.000 $206.000 $300.000 $300.000 $335.000 $280.000
479 7001 ADJUSTING MANHOLES EA 41.000 $1,500.000 $2,000.000 $2,700.000 $4,865.000 $1,800.000
479 7007 ADJUSTING MANHOLES (WATER VALVE BOX) EA 50.000 $1,500.000 $1,500.000 $1,700.000 $2,955.000 $1,800.000
483 7016 SHOT BLASTING SY 5,269.000 $7.000 $5.000 $6.000 $4.100 $4.000
500 7001 MOBILIZATION LS 1.000 $742,187.000 $850,000.000 $1,012,500.000 $998,375.000 $1,000,000.000
502 7001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $6,500.000 $16,500.000 $7,000.000 $10,500.000 $2,600.000
503 7001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 30.000 $171.430 $250.000 $100.000 $295.000 $76.000
503 7002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $10,000.000 $17,500.000 $15,000.000 $3,000.000 $20,000.000
505 7001 TMA (STATIONARY) DAY 180.000 $150.000 $250.000 $275.000 $615.000 $270.630
505 7002 TMA (MOBILE OPERATION) HR 720.000 $50.000 $65.000 $90.000 $95.000 $40.000
529 7002 CONC CURB (TY II) LF 2,000.000 $35.000 $15.000 $80.000 $33.000 $40.000
530 7002 INTERSECTIONS (ACP) SY 10,858.000 $15.230 $42.000 $40.000 $35.500 $40.000
662 7005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 15,600.000 $0.880 $0.600 $0.400 $1.180 $0.350
662 7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 25,660.000 $0.660 $0.450 $0.400 $1.180 $0.320
662 7012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 10,105.000 $0.940 $2.000 $0.400 $1.180 $0.400
662 7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 160.000 $0.670 $3.000 $0.400 $1.180 $0.320
662 7112 WK ZN PAV MRK SHT TERM (TAB)TY W EA 5,186.000 $1.600 $4.000 $1.500 $1.390 $1.310
662 7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 16.000 $1.620 $4.000 $5.000 $1.400 $1.310
666 7018 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 162.000 $2.190 $3.000 $1.350 $5.880 $1.200
666 7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 10,105.000 $1.600 $1.500 $0.950 $1.350 $0.850
666 7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 3,710.000 $9.940 $12.000 $7.000 $7.650 $6.900
666 7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) LF 15,600.000 $0.880 $1.200 $0.700 $1.180 $0.620
666 7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) LF 25,660.000 $1.010 $1.000 $0.700 $1.180 $0.600
666 7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) LF 160.000 $0.950 $3.000 $0.700 $5.880 $0.600
668 7091 PREFAB PM TY C (W)(ARROW) EA 94.000 $189.420 $330.000 $250.000 $247.000 $220.000
668 7103 PREFAB PM TY C (W)(WORD) EA 94.000 $213.400 $500.000 $300.000 $277.000 $280.000
668 7111 PREFAB PM TY C (W)(36")(YLD TRI) EA 23.000 $70.390 $90.000 $55.000 $88.000 $50.000
672 7001 REFL PAV MRKR TY I-A EA 501.000 $6.400 $8.000 $4.500 $7.000 $4.000
672 7006 REFL PAV MRKR TY II-C-R EA 197.000 $6.030 $8.000 $4.500 $7.000 $4.000
713 7001 JT CLEANING AND SEALING(TRANS CNTR JTS) LF 35,250.000 $2.050 $3.750 $3.500 $30.600 $26.000
713 7004 CRACK CLEANING AND SEALING (JCP) LF 2,600.000 $39.630 $7.000 $10.000 $28.250 $24.000
720 7001 SPALLING REPAIR (HYDRAULIC CEMENT) CF 500.000 $296.290 $315.000 $185.000 $208.850 $180.000
7001 7002 BENT CAP/ABUTMENT CAP CLEANING EA 2.000 $1,700.000 $2,000.000 $6,500.000 $6,120.000 $2,500.000
Totals: $8,243,561.94 $8,584,310.10 $10,190,652.45 $10,411,607.05 $10,421,995.77