Show Job Controls
Bid Cobra

LUBBOCK US 84 (0052-07-071)

Items: 24

County: LUBBOCK
Length: N/A
Highway: US 84
District: LUBBOCK
Control Number: 0052-07-071
DBE Goal: N/A
Project: NH 2020(749)
Guaranty: N/A
Time: 234 WORKING DAYS
Engineer's Estimate: $7,108,870.25
Date: 04/09/2020 (6 years ago)
Contract Number: N/A
Type: INSTALL CABLE BARRIERS IN MEDIANS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$7,108,870.25
$6,065,949.86
Over/Under Est: -14.67% -$1,042,920.39
$7,017,455.50
Over/Under Est: -1.29% -$91,414.75
Amt Left: 15.69% $951,505.64
$7,110,802.95
Over/Under Est: 0.03% $1,932.70
Amt Left: 17.22% $1,044,853.09
Delta: -1.33% -$93,347.45

Bid Items & Bid Tabulations

24 Total 0 of 24
LUBBOCK  |  US 84  |  LUBBOCK  |  0052-07-071  |  04/09/2020  |  $7,108,870.25  |  NH 2020(749)  |  INSTL CABLE BARRIERS IN MEDIANS  |  234 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCR CIVIL CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
HJC FARMS, INC.
OBLITERATING ABANDONED ROAD
STA 72.720 $600.000 $1,645.000 $1,000.000 $800.000
BACKFILL (TY A)
STA 72.720 $175.000 $618.000 $450.000 $185.000
BLADING
STA 1,468.720 $225.000 $105.000 $250.000 $150.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 32,267.000 $4.000 $4.000 $10.000 $4.000
FOG SEAL (CSS-1H)
GAL 452.000 $4.000 $34.000 $10.000 $4.000
RIPRAP (MOW STRIP)(5 IN)
CY 6,465.000 $550.000 $518.000 $550.000 $650.000
REMOV STR (SET)
EA 4.000 $650.000 $800.000 $500.000 $575.000
REMOV STR (PIPE)
LF 120.000 $20.000 $86.000 $30.000 $25.000
MOBILIZATION
LS 1.000 $650,000.000 $215,900.000 $700,000.000 $750,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $10,000.000 $10,925.000 $8,500.000 $2,500.000
SANDBAGS FOR EROSION CONTROL
EA 306.000 $8.000 $5.600 $10.000 $50.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,590.000 $6.500 $6.050 $18.000 $6.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,590.000 $2.000 $1.400 $9.000 $1.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 7,525.000 $0.250 $3.200 $1.000 $2.250
CABLE BARRIER SYSTEM (TL-4)
LF 139,618.000 $12.500 $9.350 $8.000 $8.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 110.000 $3,000.000 $2,450.000 $3,000.000 $3,000.000
PAVEMENT SEALER 4"
LF 7,525.000 $0.250 $0.600 $1.000 $1.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 7,525.000 $0.500 $1.150 $1.500 $2.000
ELIM EXT PAV MRK & MRKS (8")
LF 3,130.000 $1.000 $1.350 $1.500 $2.400
PAV SURF PREP FOR MRK (4")
LF 7,525.000 $0.250 $0.650 $1.000 $1.500
FULL - WIDTH MOWING
CYC 4.000 $4,000.000 $11,100.000 $3,500.000 $10,000.000
LITTER REMOVAL
CYC 4.000 $2,500.000 $4,320.000 $3,500.000 $5,000.000
TMA (STATIONARY)
DAY 468.000 $225.000 $350.000 $550.000 $200.000
TMA (MOBILE OPERATION)
DAY 24.000 $225.000 $465.000 $850.000 $250.000
Totals: $7,108,870.250 $6,065,949.860 $7,017,455.500 $7,110,802.950