Job Info for 0052-07-071

County: LUBBOCK Highway: US 84 Date: 04/09/2020 (4 years ago) Engineer's Estimate: $7,108,870 Control Number: 0052-07-071
Project: NH 2020(749) District: LUBBOCK Time: 234 WORKING DAYS Type: INSTALL CABLE BARRIERS IN MEDIANS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $7,108,870.25
SCR CIVIL CONSTRUCTION, LLC   $6,065,949.86 1
-14.67% | -$1,042,920.39
FNH CONSTRUCTION, LLC   $7,017,455.50 2
-1.29% | -$91,414.75
15.69% | $951,505.64
HJC FARMS, INC.   $7,110,802.95 3
0.03% | $1,932.70
17.22% | $1,044,853.09
1.33% | $93,347.45

Bid Items

Items: 24, 0 filtered
LUBBOCK US 84  |  LUBBOCK  |  0052-07-071  |  04/09/2020  |  $7,108,870  |  NH 2020(749)  |  INSTL CABLE BARRIERS IN MEDIANS  |  234 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SCR CIVIL CONSTRUCTION, LLC FNH CONSTRUCTION, LLC HJC FARMS, INC.
106 6001 OBLITERATING ABANDONED ROAD STA 72.720 $600.000 $1,645.000 $1,000.000 $800.000
134 6001 BACKFILL (TY A) STA 72.720 $175.000 $618.000 $450.000 $185.000
150 6001 BLADING STA 1,468.720 $225.000 $105.000 $250.000 $150.000
314 6013 EMULS ASPH (EROSN CONT)(CSS-1H) GAL 32,267.000 $4.000 $4.000 $10.000 $4.000
315 6004 FOG SEAL (CSS-1H) GAL 452.000 $4.000 $34.000 $10.000 $4.000
432 6046 RIPRAP (MOW STRIP)(5 IN) CY 6,465.000 $550.000 $518.000 $550.000 $650.000
496 6004 REMOV STR (SET) EA 4.000 $650.000 $800.000 $500.000 $575.000
496 6007 REMOV STR (PIPE) LF 120.000 $20.000 $86.000 $30.000 $25.000
500 6001 MOBILIZATION LS 1.000 $650,000.000 $215,900.000 $700,000.000 $750,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 14.000 $10,000.000 $10,925.000 $8,500.000 $2,500.000
506 6035 SANDBAGS FOR EROSION CONTROL EA 306.000 $8.000 $5.600 $10.000 $50.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 1,590.000 $6.500 $6.050 $18.000 $6.250
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,590.000 $2.000 $1.400 $9.000 $1.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 7,525.000 $0.250 $3.200 $1.000 $2.250
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 139,618.000 $12.500 $9.350 $8.000 $8.000
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 110.000 $3,000.000 $2,450.000 $3,000.000 $3,000.000
666 6224 PAVEMENT SEALER 4" LF 7,525.000 $0.250 $0.600 $1.000 $1.500
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 7,525.000 $0.500 $1.150 $1.500 $2.000
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 3,130.000 $1.000 $1.350 $1.500 $2.400
678 6001 PAV SURF PREP FOR MRK (4") LF 7,525.000 $0.250 $0.650 $1.000 $1.500
730 6107 FULL - WIDTH MOWING CYC 4.000 $4,000.000 $11,100.000 $3,500.000 $10,000.000
734 6002 LITTER REMOVAL CYC 4.000 $2,500.000 $4,320.000 $3,500.000 $5,000.000
6185 6002 TMA (STATIONARY) DAY 468.000 $225.000 $350.000 $550.000 $200.000
6185 6005 TMA (MOBILE OPERATION) DAY 24.000 $225.000 $465.000 $850.000 $250.000
Totals: $7,108,870.25 $6,065,949.86 $7,017,455.50 $7,110,802.95