Show Job Controls
Bid Cobra

LIMESTONE PR 28A (0625-01-001)

Items: 65

County: LIMESTONE
Length: 3.2840 MILES (1.5143 MILES)
Highway: PR 28A
District: WACO
Control Number: 0625-01-001
DBE Goal: 0.0%
Project: C 625-1-1
Guaranty: $43,000.00
Time: 128 WORKING DAYS
Engineer's Estimate: $2,150,632.74
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263219
Type: REHAB PRK RDS
Project ID: A00002054
Project Description: REHABILITATE PARK ROADS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOSH VOILES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,150,632.74
Over/Under Est: -14.01% -$301,305.19
Over/Under Est: -12.64% -$271,774.67
Amt Left: 1.6% $29,530.52
Over/Under Est: 9.65% $207,607.94
Amt Left: 27.52% $508,913.13
Delta: -25.51% -$479,382.61
$2,659,819.59
Over/Under Est: 23.68% $509,186.85
Amt Left: 43.83% $810,492.04
Delta: -12.79% -$301,578.91
Over/Under Est: 29.82% $641,366.26
Amt Left: 50.97% $942,671.45
Delta: -4.97% -$132,179.41
$3,464,815.00
Over/Under Est: 61.11% $1,314,182.26
Amt Left: 87.36% $1,615,487.45
Delta: -24.10% -$672,816.00

Bid Items & Bid Tabulations

65 Total 0 of 65
LIMESTONE  |  PR 28A  |  WACO  |  0625-01-001  |  07/02/2026 1:00 PM CDT  |  $2,150,632.74  |  C 625-1-1  |  REHAB PRK RDS  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
PRATER DIRT WORK LLC
JOE BLAND CONSTRUCTION LLC
A. L. HELMCAMP, INC.
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 3.000 $925.000 $1,500.000 $1,220.000 $2,765.000 $800.000 $975.000 $2,700.000
PREP ROW (TREE PRUNE AND TRIM)
STA 5.000 $860.000 $1,200.000 $1,465.000 $3,105.000 $2,000.000 $1,150.000 $10,000.000
TREE PROTECTION (INSTALL)
EA 3.000 $539.520 $500.000 $520.000 $600.000 $400.000 $350.000 $530.000
TREE PROTECTION (REMOVE)
EA 3.000 $105.500 $100.000 $420.000 $300.000 $100.000 $50.000 $210.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 98.000 $25.000 $15.000 $28.000 $36.000 $30.000 $60.000 $45.000
REMOV CONC (CURB)
LF 95.000 $15.000 $15.000 $28.000 $35.000 $14.000 $30.000 $20.000
RMV (8") TRT/UNTRT BASE & ASPH PAV
SY 2,600.000 $25.000 $11.000 $8.200 $10.000 $9.000 $32.000 $30.000
EXCAV (ROADWAY)
CY 89.000 $19.000 $65.000 $35.000 $45.000 $200.000 $90.000 $100.000
EMBANK (VEH)(DC)(TY C)
CY 192.000 $34.790 $65.000 $38.000 $60.000 $150.000 $60.000 $100.000
BACKFILL (TY A)(VEH)
CY 605.000 $50.000 $50.000 $33.000 $150.000 $75.000 $100.000 $100.000
BACKFILL (TY A OR B)(VEH)
CY 27.000 $40.000 $95.000 $148.000 $150.000 $200.000 $105.000 $145.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 2,665.000 $1.750 $1.000 $1.000 $1.150 $1.100 $0.500 $1.250
BROADCAST SEED (TEMP_WARM_COOL)
SY 2,665.000 $0.250 $0.750 $1.000 $0.850 $1.100 $0.500 $0.900
VEGETATIVE WATERING
TGL 43.300 $25.500 $25.000 $70.000 $10.000 $100.000 $50.000 $35.000
RDSIDE AMENITY (WHEEL STOP)
EA 28.000 $250.000 $165.000 $150.000 $60.000 $300.000 $175.000 $150.000
RDSIDE AMENITY
EA 2.000 $500.000 $450.000 $2,500.000 $3,000.000 $20,000.000 $925.000 $2,900.000
RDSIDE AMENITY (TYPE 1)
EA 1.000 $1,500.000 $500.000 $1,650.000 $950.000 $15,000.000 $15,500.000 $2,900.000
RDSIDE AMENITY (REMOV)
EA 28.000 $140.000 $70.000 $45.000 $40.000 $1,500.000 $425.000 $215.000
PROOF ROLLING
HR 16.000 $115.000 $200.000 $121.000 $105.000 $100.000 $450.000 $230.000
REWORK BS MTL (TY C)(6")(ORD COMP)
SY 23,296.000 $2.400 $1.500 $1.100 $1.750 $2.350 $5.000 $6.000
CEMENT
TON 176.000 $225.000 $250.000 $240.000 $270.000 $235.000 $450.000 $275.000
CEMENT TRT (EXIST MATL)(5")
SY 23,296.000 $3.250 $2.750 $1.600 $2.950 $7.000 $14.000 $7.000
PRIME COAT(MC-30 OR AE-P)
GAL 4,660.000 $9.120 $6.000 $5.500 $5.000 $7.000 $5.500 $8.250
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 73.000 $207.660 $175.000 $163.000 $200.000 $150.000 $135.000 $220.000
SP MIXES SP-C SAC-B PG70-22
TON 6,408.000 $118.000 $110.000 $125.000 $149.000 $148.000 $130.000 $205.000
TACK COAT
GAL 63.000 $4.400 $10.000 $3.200 $6.850 $50.000 $5.000 $24.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 500.000 $61.000 $65.000 $65.000 $89.350 $45.000 $58.000 $174.000
PLANE ASPH CONC PAV(0" TO 2")
SY 2,600.000 $3.000 $5.000 $4.900 $2.150 $6.000 $4.000 $7.000
RETAINING WALL (CONC BLOCK)
SF 295.000 $60.000 $65.000 $79.690 $95.000 $72.000 $36.000 $98.000
RIPRAP (CONC)(CL A)
CY 36.000 $841.000 $650.000 $710.000 $785.000 $852.000 $1,400.000 $1,630.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 25.000 $200.000 $300.000 $300.000 $140.000 $360.000 $190.000 $530.000
CLEAN EXIST CULVERTS
EA 14.000 $1,750.000 $1,000.000 $2,000.000 $935.000 $2,400.000 $1,150.000 $2,500.000
REMOV STR (RR TIMBER TIES)
EA 18.000 $200.000 $300.000 $137.000 $60.000 $200.000 $350.000 $325.000
REMOV STR (WOOD STR)
LF 3,473.000 $25.000 $4.500 $3.550 $5.500 $5.000 $10.000 $6.500
MOBILIZATION
LS 1.000 $195,923.880 $120,000.000 $133,110.000 $194,385.000 $210,000.000 $125,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $1,500.000 $1,002.000 $3,550.000 $7,500.000 $1,500.000 $6,250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $10,000.000 $5,500.000 $295.000 $18,000.000 $12,000.000 $12,000.000
TMA (STATIONARY)
DAY 34.000 $160.000 $250.000 $91.000 $100.000 $200.000 $215.000 $280.000
TMA (MOBILE OPERATION)
DAY 9.000 $260.000 $400.000 $1.000 $100.000 $300.000 $975.000 $675.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 30.000 $53.000 $40.000 $65.000 $47.000 $70.000 $50.000 $42.000
ROCK FILTER DAMS (REMOVE)
LF 30.000 $13.000 $10.000 $25.000 $12.000 $30.000 $20.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,180.000 $4.300 $3.250 $4.000 $3.800 $4.000 $6.000 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,180.000 $1.100 $1.000 $1.000 $1.200 $1.050 $1.000 $1.250
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 654.000 $6.000 $4.850 $7.000 $5.700 $7.350 $8.000 $5.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 654.000 $1.450 $1.000 $1.000 $1.200 $1.100 $2.000 $1.250
CONC CURB (TY II)
LF 6,003.000 $30.000 $30.000 $30.000 $33.400 $36.000 $45.000 $48.000
CONC CURB (RIBBON)
LF 65.000 $35.000 $60.000 $43.000 $79.000 $51.600 $120.000 $300.000
TURNOUTS (ACP)
SY 2,600.000 $69.800 $70.000 $70.000 $92.850 $105.000 $130.000 $80.000
CONC SIDEWALKS (6")
SY 89.000 $90.000 $115.000 $96.000 $115.000 $115.200 $120.000 $250.000
CURB RAMPS (TY 10)
EA 1.000 $3,250.000 $2,650.000 $3,000.000 $1,625.000 $3,600.000 $3,500.000 $3,300.000
FIXED BOLLARD
EA 28.000 $1,500.000 $1,200.000 $800.000 $1,000.000 $960.000 $575.000 $950.000
PIPE UNDERDRAINS (TY 6)(4")
LF 165.000 $18.000 $65.000 $40.000 $13.550 $48.000 $130.000 $90.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $715.000 $500.000 $675.000 $795.000 $708.750 $600.000 $775.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 10.000 $350.000 $225.000 $275.000 $325.000 $288.750 $260.000 $350.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 1.000 $441.000 $250.000 $285.000 $335.000 $300.000 $290.000 $325.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,273.000 $1.250 $1.500 $1.000 $1.000 $2.000 $1.250 $0.750
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 174.000 $8.500 $7.500 $10.000 $14.000 $10.050 $12.000 $11.000
RE PM TY II (R&W) 6" (FIRE LANE)
LF 155.000 $25.000 $2.000 $2.000 $2.350 $2.100 $2.250 $2.250
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 662.000 $0.760 $0.650 $1.600 $3.550 $1.700 $2.000 $2.000
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 27,864.000 $0.740 $0.650 $0.580 $1.000 $0.610 $0.750 $0.750
PREFAB PM TY C (W)(NUMBER)
EA 50.000 $200.000 $150.000 $150.000 $141.000 $158.000 $175.000 $158.000
PREFAB PM TY C (W)(SYMBOL)
EA 3.000 $361.820 $300.000 $300.000 $0.010 $315.000 $350.000 $320.000
PRE PM TY C(BL&WH)(ACC PRK)(W/BORDR)LG
EA 2.000 $500.000 $450.000 $250.000 $295.000 $263.000 $290.000 $260.000
PRE PM TY C(BL&WH)(ACC PRK)(W/BORDR)SM
EA 1.000 $300.000 $250.000 $250.000 $235.000 $263.000 $290.000 $260.000
UNDERSEAL COURSE
GAL 13,925.000 $3.500 $4.500 $4.250 $5.300 $4.000 $5.000 $3.750
Totals: $2,150,632.740 $1,849,327.550 $1,878,858.070 $2,358,240.680 $2,659,819.590 $2,791,999.000 $3,464,815.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $10,000.00
Total: $15,000.00