Job Info for 6371-69-001

County: LAMAR Highway: FM0038 Date: 12/17/2020 (3 years ago) Engineer's Estimate: $254,537 Control Number: 6371-69-001
Project: BPM - 637169001 District: PARIS Time: 48 W Type: BPM - ABUTMENT AND RIPRAP EROSION REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $254,537.00
SHALOM SERVICES CORPORATION   $177,715.40 1
-30.18% | -$76,821.60
RED BARON BUILDING COMPANY, LLC   $183,923.00 2
-27.74% | -$70,614.00
3.49% | $6,207.60
SJ&J CONSTRUCTION, LLC   $241,341.00 3
-5.18% | -$13,196.00
35.8% | $63,625.60
31.22% | $57,418.00
STRAIGHT LINE SAWING & SEALING, INC.   $244,884.00 4
-3.79% | -$9,653.00
37.8% | $67,168.60
1.47% | $3,543.00
LELAND & BRADLEE CONSTRUCTION, INC.   $251,550.00 5
-1.17% | -$2,987.00
41.55% | $73,834.60
2.72% | $6,666.00
HIGHWAY 19 CONSTRUCTION LLC   $286,813.00 6
12.68% | $32,276.00
61.39% | $109,097.60
14.02% | $35,263.00
HODGES AND SON CONSTRUCTION COMPANY, INC.   $308,024.00 7
21.01% | $53,487.00
73.32% | $130,308.60
7.40% | $21,211.00
FNH CONSTRUCTION, LLC   $367,390.00 8
44.34% | $112,853.00
106.73% | $189,674.60
19.27% | $59,366.00

Bid Items

Items: 13, 0 filtered
LAMAR FM0038  |  PARIS  |  6371-69-001  |  12/17/2020  |  $254,537  |  BPM - 637169001  |  BPM - ABUTMENT AND RIPRAP EROSION REPAIR  |  48 W
Item code Description Unit Quantity Engineer's Estimate SHALOM SERVICES CORPORATION RED BARON BUILDING COMPANY, LLC SJ&J CONSTRUCTION, LLC STRAIGHT LINE SAWING & SEALING, INC. LELAND & BRADLEE CONSTRUCTION, INC. HIGHWAY 19 CONSTRUCTION LLC HODGES AND SON CONSTRUCTION COMPANY, INC. FNH CONSTRUCTION, LLC
104 6028 REMOVING CONC (MISC) SY 75.000 $70.000 $30.000 $40.000 $30.000 $30.000 $75.000 $100.000 $50.000 $150.000
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 200.000 $60.000 $35.000 $36.000 $25.000 $40.000 $45.000 $30.000 $30.000 $50.000
162 6002 BLOCK SODDING SY 66.000 $12.000 $6.400 $4.500 $6.000 $4.000 $55.000 $10.000 $30.000 $10.000
401 6001 FLOWABLE BACKFILL CY 44.000 $275.000 $177.000 $225.000 $180.000 $250.000 $320.000 $250.000 $250.000 $350.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 25.000 $165.000 $324.000 $185.000 $150.000 $250.000 $550.000 $350.000 $300.000 $500.000
432 6008 RIPRAP (CONC)(CL B)(RR8&RR9) CY 99.000 $500.000 $500.000 $450.000 $675.000 $450.000 $305.000 $600.000 $650.000 $650.000
432 6032 RIPRAP (STONE PROTECTION)(15 IN) CY 88.000 $225.000 $145.000 $200.000 $180.000 $180.000 $200.000 $180.000 $260.000 $185.000
438 6002 CLEANING AND SEALING EXIST JOINTS(CL3) LF 1,805.000 $40.000 $35.000 $15.000 $40.000 $18.000 $10.000 $35.000 $28.000 $50.000
438 6004 CLEANING AND SEALING EXIST JOINTS(CL7) LF 208.000 $40.000 $30.000 $22.000 $45.000 $55.000 $15.000 $55.000 $28.000 $50.000
446 6022 CLEAN & PAINT EXIST PILING (SYSTEM I-A) LS 1.000 $10,000.000 $1,000.000 $1,000.000 $10,000.000 $60,000.000 $48,000.000 $38,000.000 $75,000.000 $60,000.000
500 6001 MOBILIZATION LS 1.000 $30,000.000 $16,000.000 $50,000.000 $25,000.000 $24,000.000 $30,000.000 $50,000.000 $28,000.000 $34,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $5,750.000 $1,000.000 $1,500.000 $6,000.000 $4,000.000 $7,500.000 $5,000.000 $8,000.000 $8,500.000
6185 6002 TMA (STATIONARY) DAY 48.000 $275.000 $10.000 $200.000 $100.000 $350.000 $750.000 $1.000 $150.000 $350.000
Totals: $254,537.00 $177,715.40 $183,923.00 $241,341.00 $244,884.00 $251,550.00 $286,813.00 $308,024.00 $367,390.00