REMOVING CONC (DRIVEWAYS)
|
SY
|
357.000
|
$15.000
|
$25.000
|
$20.000
|
$44.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
1,169.000
|
$15.000
|
$30.000
|
$20.000
|
$55.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
217.000
|
$25.000
|
$50.000
|
$40.000
|
$50.000
|
|
|
BACKFILL (TY A)
|
STA
|
58.000
|
$200.000
|
$300.000
|
$250.000
|
$250.000
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
18,746.000
|
$0.100
|
$0.100
|
$0.100
|
$0.360
|
|
|
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
18,746.000
|
$0.200
|
$0.300
|
$0.240
|
$0.880
|
|
|
VEGETATIVE WATERING
|
MG
|
112.000
|
$20.000
|
$100.000
|
$15.000
|
$358.510
|
|
|
PLANE ASPH CONC PAV(0" TO 6")
|
SY
|
6,458.000
|
$5.500
|
$10.000
|
$10.000
|
$7.980
|
|
|
DRILL SHAFT (NON - REINFORCED) (12 IN)
|
LF
|
7.000
|
$120.000
|
$180.000
|
$200.000
|
$99.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
43.200
|
$425.000
|
$450.000
|
$450.000
|
$715.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
726.000
|
$70.000
|
$60.000
|
$55.000
|
$148.500
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
28.000
|
$1,250.000
|
$1,150.000
|
$900.000
|
$1,320.000
|
|
|
REMOV STR (SET)
|
EA
|
6.000
|
$450.000
|
$500.000
|
$500.000
|
$825.000
|
|
|
REMOV STR (PIPE)
|
LF
|
334.000
|
$13.000
|
$50.000
|
$15.000
|
$44.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$120,000.000
|
$250,000.000
|
$350,000.000
|
$722,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$6,000.000
|
$5,000.000
|
$20,000.000
|
$21,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
60.000
|
$32.000
|
$42.000
|
$45.000
|
$170.560
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
60.000
|
$7.500
|
$10.000
|
$10.000
|
$38.270
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
23.000
|
$75.000
|
$10.000
|
$75.000
|
$300.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
470.000
|
$2.300
|
$3.000
|
$4.000
|
$7.300
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
470.000
|
$0.750
|
$1.000
|
$1.000
|
$3.770
|
|
|
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
|
LF
|
1,935.000
|
$20.000
|
$25.000
|
$40.000
|
$20.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
2,300.000
|
$6.000
|
$15.000
|
$10.000
|
$10.000
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
1,935.000
|
$7.500
|
$25.000
|
$10.000
|
$10.000
|
|
|
PTB (FUR & INST)(STEEL)
|
LF
|
3,225.000
|
$100.000
|
$25.000
|
$170.000
|
$180.000
|
|
|
PTB (MOVE)(STEEL)
|
LF
|
4,500.000
|
$7.500
|
$25.000
|
$10.000
|
$8.000
|
|
|
PTB (STKPL)(STEEL)
|
LF
|
3,225.000
|
$7.500
|
$25.000
|
$10.000
|
$8.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
515.000
|
$55.000
|
$150.000
|
$90.000
|
$200.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
357.000
|
$100.000
|
$110.000
|
$90.000
|
$154.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
935.000
|
$42.000
|
$75.000
|
$40.000
|
$41.380
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
850.000
|
$23.000
|
$31.000
|
$33.000
|
$31.900
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
1.000
|
$1,800.000
|
$2,500.000
|
$2,600.000
|
$2,640.000
|
|
|
MTL BM GD FEN TRANS (ANCHOR PLATE)
|
EA
|
1.000
|
$600.000
|
$1,000.000
|
$1,000.000
|
$825.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
875.000
|
$2.500
|
$2.000
|
$3.000
|
$1.650
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$2,500.000
|
$3,200.000
|
$3,700.000
|
$3,520.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
1.000
|
$300.000
|
$250.000
|
$300.000
|
$16.500
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,250.000
|
$1,500.000
|
$2,000.000
|
$1,375.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
5.000
|
$500.000
|
$800.000
|
$1,000.000
|
$550.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
7.000
|
$7,500.000
|
$23,500.000
|
$16,000.000
|
$13,926.830
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
4.000
|
$200.000
|
$250.000
|
$400.000
|
$240.900
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
1.000
|
$250.000
|
$350.000
|
$400.000
|
$295.900
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
10.000
|
$535.000
|
$950.000
|
$800.000
|
$645.700
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
4.000
|
$550.000
|
$850.000
|
$1,000.000
|
$777.700
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
14.000
|
$75.000
|
$100.000
|
$125.000
|
$85.800
|
|
|
RELOCATE LRSA
|
EA
|
1.000
|
$2,000.000
|
$1,000.000
|
$4,000.000
|
$4,015.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
|
EA
|
39.000
|
$30.000
|
$55.000
|
$25.000
|
$16.500
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
18,165.000
|
$0.750
|
$2.000
|
$1.100
|
$1.100
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
2,425.000
|
$1.250
|
$1.000
|
$2.200
|
$2.200
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
17,340.000
|
$0.750
|
$1.000
|
$1.100
|
$1.100
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
881.000
|
$1.000
|
$1.000
|
$2.000
|
$1.650
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
534.000
|
$1.250
|
$1.000
|
$2.000
|
$1.650
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
2,146.000
|
$0.750
|
$0.850
|
$1.000
|
$0.940
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
22.000
|
$6.500
|
$5.000
|
$6.000
|
$5.500
|
|
REFL PAV MRK TY I (W)(ARROW)(090MIL)
|
EA
|
13.000
|
$125.000
|
$130.000
|
$150.000
|
$143.000
|
|
REFL PAV MRK TY I(W)(DBL ARROW)(090MIL)
|
EA
|
1.000
|
$175.000
|
$200.000
|
$250.000
|
$220.000
|
|
REFL PAV MRK TY I (W)(WORD)(090MIL)
|
EA
|
13.000
|
$150.000
|
$150.000
|
$175.000
|
$165.000
|
|
REF PAV MRK TY I(W)18"(YLD TRI)(090MIL)
|
EA
|
68.000
|
$45.000
|
$35.000
|
$40.000
|
$38.500
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
2,190.000
|
$0.500
|
$1.000
|
$1.100
|
$1.100
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
1,649.000
|
$0.250
|
$1.000
|
$1.100
|
$1.100
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
1,012.000
|
$0.300
|
$1.000
|
$1.100
|
$1.100
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
8,670.000
|
$0.700
|
$1.000
|
$1.100
|
$1.100
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
8,670.000
|
$0.750
|
$1.000
|
$1.100
|
$1.100
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
26.000
|
$3.000
|
$5.000
|
$6.000
|
$5.500
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
324.000
|
$3.500
|
$5.000
|
$6.000
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
17,340.000
|
$0.400
|
$0.500
|
$0.550
|
$0.550
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
2,140.000
|
$0.750
|
$0.750
|
$1.000
|
$0.830
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
15.000
|
$75.000
|
$50.000
|
$55.000
|
$55.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
14.000
|
$80.000
|
$75.000
|
$85.000
|
$82.500
|
|
|
ELIM EXT PAV MRK & MRKS (18")(YLD TRI)
|
EA
|
68.000
|
$3.750
|
$30.000
|
$35.000
|
$33.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
14,890.000
|
$0.150
|
$0.050
|
$0.070
|
$0.060
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
1,398.000
|
$0.250
|
$0.050
|
$0.550
|
$0.550
|
|
|
TEXTURING CONCRETE PAVEMENT)
|
SY
|
11,915.000
|
$4.000
|
$6.000
|
$5.000
|
$5.000
|
|
|
D-GR HMA TY-C PG64-22
|
TON
|
3,942.000
|
$100.000
|
$92.000
|
$100.000
|
$150.000
|
|
|
BONDING COURSE
|
GAL
|
904.000
|
$3.500
|
$6.000
|
$6.000
|
$3.000
|
|
|
CONC PVMT (CONT REINF-CRCP) (5")
|
SY
|
11,914.000
|
$70.000
|
$77.000
|
$90.000
|
$150.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$10,000.000
|
$10,000.000
|
$20,000.000
|
$18,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
400.000
|
$225.000
|
$200.000
|
$200.000
|
$157.500
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
240.000
|
$75.000
|
$50.000
|
$30.000
|
$73.500
|
|
Totals: |
$2,496,884.150
|
$2,962,393.900
|
$3,538,564.440
|
$5,059,737.150
|