Job Info for 0221-01-074

County: LAMAR Highway: US 271 Date: 10/03/2017 (7 years ago) Engineer's Estimate: $9,586,977 Control Number: 0221-01-074
Project: NH 2018(127) District: PARIS Time: 197 WORKING DAYS Type: WIDEN NON-FREEWAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $9,586,977.31
RK HALL, LLC   $8,915,686.62 1
-7% | -$671,290.69
HIGHWAY 19 CONSTRUCTION LLC   $9,007,814.55 2
-6.04% | -$579,162.76
1.03% | $92,127.93
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.   $9,483,086.80 3
-1.08% | -$103,890.51
6.36% | $567,400.18
5.28% | $475,272.25
D. L. LENNON INCORPORATED - CONTRACTOR   $9,999,211.73 4
4.3% | $412,234.42
12.15% | $1,083,525.11
5.44% | $516,124.93
AUSTIN BRIDGE & ROAD SERVICES, LP   $11,000,559.74 5
14.74% | $1,413,582.43
23.38% | $2,084,873.12
10.01% | $1,001,348.01
FNH CONSTRUCTION, LLC   $11,389,779.15 6
18.8% | $1,802,801.84
27.75% | $2,474,092.53
3.54% | $389,219.41
EAST TEXAS BRIDGE, INC.   $11,415,622.43 7
19.07% | $1,828,645.12
28.04% | $2,499,935.81
0.23% | $25,843.28

Bid Items

Items: 100, 0 filtered
LAMAR US 271  |  PARIS  |  0221-01-074  |  10/03/2017  |  $9,586,977  |  NH 2018(127)  |  WIDEN NON-FREEWAY  |  197 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate RK HALL, LLC HIGHWAY 19 CONSTRUCTION LLC RICHARD DRAKE CONSTRUCTION COMPANY, L.P. D. L. LENNON INCORPORATED - CONTRACTOR AUSTIN BRIDGE & ROAD SERVICES, LP FNH CONSTRUCTION, LLC EAST TEXAS BRIDGE, INC.
100 6002 PREPARING ROW STA 262.810 $1,000.000 $450.000 $450.000 $430.000 $449.000 $750.000 $2,000.000 $1,100.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 1,126.000 $15.000 $12.600 $10.000 $12.000 $17.000 $12.000 $20.000 $15.000
105 6077 REMOVING STAB BASE & ASPH PAV (8") SY 3,811.000 $15.000 $6.270 $5.000 $3.200 $20.500 $4.500 $20.000 $6.000
110 6001 EXCAVATION (ROADWAY) CY 816.000 $8.500 $13.710 $10.000 $15.000 $18.000 $21.000 $20.000 $12.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 375.000 $15.000 $31.230 $20.000 $30.000 $38.000 $60.000 $30.000 $12.000
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 8,640.000 $10.000 $14.100 $17.000 $20.000 $21.000 $18.000 $30.000 $12.000
134 6002 BACKFILL (TY B) STA 828.590 $165.000 $89.700 $150.000 $150.000 $330.000 $190.000 $250.000 $400.000
152 6001 ROAD GRADER WORK (ORD COMP) STA 238.060 $185.000 $218.800 $200.000 $200.000 $575.000 $320.000 $450.000 $400.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 3,811.000 $1.350 $5.510 $3.000 $3.000 $4.500 $4.000 $4.500 $3.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 115,646.000 $0.100 $0.110 $0.100 $0.100 $0.100 $0.090 $0.250 $0.130
164 6011 BROADCAST SEED (TEMP) (COOL) SY 115,646.000 $0.100 $0.120 $0.110 $0.110 $0.110 $0.100 $0.250 $0.130
164 6013 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 231,284.000 $0.250 $0.240 $0.230 $0.230 $0.230 $0.240 $0.250 $0.300
168 6001 VEGETATIVE WATERING MG 1,388.000 $10.000 $19.490 $5.000 $18.000 $30.000 $24.850 $50.000 $15.000
247 6223 FL BS (CMP IN PLC)(TY A GR 4)(10") SY 50,930.000 $16.200 $14.540 $17.000 $17.690 $18.250 $14.000 $16.500 $17.000
251 6481 REWORK BS MATL (TYB)(20")(OC) SY 27,193.000 $4.000 $6.300 $3.920 $4.100 $7.850 $13.000 $3.000 $8.000
275 6001 CEMENT TON 825.000 $150.000 $147.000 $140.000 $140.000 $132.000 $155.000 $171.000 $150.000
275 6011 CEMENT TREAT(EXIST MATL)(8") SY 50,930.000 $3.500 $2.040 $3.750 $4.000 $4.350 $2.450 $3.500 $3.000
316 6017 ASPH (AC-20-5TR) GAL 24,989.000 $4.000 $3.410 $3.500 $3.500 $4.800 $3.200 $5.000 $4.000
316 6029 ASPH (RC-250) GAL 15,212.000 $4.000 $4.410 $4.000 $4.200 $5.700 $4.800 $5.000 $5.000
316 6403 AGGR (TY-B GR-5 OR TY-L GR-5) CY 388.000 $100.000 $120.720 $137.000 $137.000 $125.000 $114.500 $125.000 $105.000
316 6440 AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B) CY 518.000 $90.000 $114.230 $110.000 $110.000 $113.000 $93.000 $125.000 $100.000
341 6038 D-GR HMA TY-D SAC-A PG64-22 TON 56,638.000 $85.000 $72.750 $72.550 $72.550 $72.750 $81.650 $76.500 $85.000
351 6015 FLEXIBLE PAVEMENT STRUCTURE REPAIR(24") SY 567.000 $130.000 $130.000 $180.000 $195.000 $120.000 $175.000 $150.000 $165.000
351 6017 FLEXIBLE PAVEMENT STRUCTURE REPAIR(20") SY 7,300.000 $40.000 $88.500 $111.000 $115.000 $87.740 $136.000 $105.000 $100.000
354 6030 PLANE ASPH CONC PAV(0" TO 8") SY 9,765.000 $5.000 $3.640 $3.500 $4.200 $4.360 $8.000 $12.500 $5.000
416 6016 DRILL SHAFT (SIGN MTS) (12 IN) LF 14.000 $110.000 $89.250 $85.000 $150.000 $200.000 $85.000 $150.000 $250.000
416 6029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 6.000 $210.000 $231.000 $220.000 $220.000 $175.000 $220.000 $250.000 $250.000
432 6009 RIPRAP (CONC) (CL B) (4") CY 0.350 $417.000 $525.000 $1,000.000 $1,000.000 $950.000 $3,000.000 $650.000 $5,000.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 706.700 $475.000 $393.750 $380.000 $400.000 $375.000 $488.000 $550.000 $400.000
438 6005 CLEANING AND SEALING JOINTS LF 568.000 $35.000 $29.400 $30.000 $30.000 $26.000 $40.000 $100.000 $38.000
462 6045 CONC BOX CULV (3 FT X 2 FT)(EXTEND) LF 5.000 $400.000 $409.500 $500.000 $525.000 $390.000 $460.000 $650.000 $800.000
462 6046 CONC BOX CULV (3 FT X 3 FT)(EXTEND) LF 20.000 $475.000 $420.000 $500.000 $525.000 $400.000 $410.000 $750.000 $800.000
462 6048 CONC BOX CULV (4 FT X 3 FT)(EXTEND) LF 13.000 $500.000 $472.500 $500.000 $525.000 $450.000 $510.000 $750.000 $800.000
462 6053 CONC BOX CULV (5 FT X 5 FT)(EXTEND) LF 12.000 $500.000 $551.250 $500.000 $525.000 $525.000 $615.000 $850.000 $1,000.000
462 6055 CONC BOX CULV (6 FT X 4 FT)(EXTEND) LF 4.000 $550.000 $551.250 $700.000 $700.000 $525.000 $765.000 $950.000 $1,000.000
466 6194 WINGWALL (PW - 2) (HW=5 FT) EA 2.000 $9,000.000 $8,400.000 $7,000.000 $7,500.000 $8,000.000 $13,800.000 $8,000.000 $8,000.000
467 6111 SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C) EA 1.000 $6,800.000 $4,725.000 $4,500.000 $500.000 $4,500.000 $10,715.000 $6,000.000 $3,000.000
467 6137 SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C) EA 1.000 $7,000.000 $5,040.000 $5,000.000 $5,000.000 $4,800.000 $8,700.000 $6,000.000 $6,000.000
467 6185 SET (TY I)(S= 5 FT)(HW= 6 FT)(3:1) (C) EA 1.000 $4,500.000 $7,875.000 $7,000.000 $7,000.000 $7,500.000 $14,100.000 $10,000.000 $11,000.000
467 6217 SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C) EA 1.000 $10,000.000 $7,875.000 $7,500.000 $7,500.000 $7,500.000 $12,760.000 $12,000.000 $8,000.000
472 6004 REMOV & RE - LAY PIPE (18 IN) LF 478.000 $75.000 $23.100 $30.000 $30.000 $22.000 $77.000 $30.000 $45.000
472 6006 REMOV & RE - LAY PIPE (24 IN) LF 116.000 $90.000 $28.350 $40.000 $40.000 $27.000 $97.000 $30.000 $55.000
500 6001 MOBILIZATION LS 1.000 $525,728.010 $500,000.000 $500,000.000 $626,698.000 $668,000.000 $1,025,000.000 $1,000,000.000 $1,100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 14.000 $4,000.000 $1,051.380 $2,000.000 $2,500.000 $5,239.000 $5,000.000 $8,500.000 $12,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 705.000 $30.000 $29.400 $28.000 $28.000 $28.000 $34.530 $30.000 $35.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 705.000 $10.000 $8.400 $8.000 $8.000 $8.000 $9.710 $15.000 $5.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 390.000 $3.000 $3.150 $3.000 $3.000 $3.000 $5.780 $4.000 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 390.000 $0.750 $15.000 $1.000 $1.000 $1.000 $3.060 $2.000 $1.000
530 6002 INTERSECTIONS (ACP) SY 2,597.000 $30.000 $14.600 $12.900 $12.900 $19.650 $22.000 $25.000 $42.000
530 6004 DRIVEWAYS (CONC) SY 1,032.000 $70.000 $89.500 $65.000 $75.000 $85.000 $98.000 $95.000 $115.000
530 6005 DRIVEWAYS (ACP) SY 2,995.000 $27.000 $35.000 $13.200 $13.200 $48.250 $38.000 $25.000 $42.000
530 6016 DRIVEWAYS (BASE) SY 1,416.000 $14.000 $28.390 $25.000 $20.000 $25.000 $33.000 $18.000 $8.000
530 6021 DRIVEWAYS (ACP) (TYPE 2) SY 1,644.000 $20.000 $25.000 $30.500 $30.500 $25.350 $72.000 $45.000 $42.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 213,734.000 $0.150 $0.110 $0.079 $0.120 $0.120 $0.160 $0.150 $0.150
533 6002 RUMBLE STRIPS (CENTERLINE) LF 102,077.000 $0.200 $0.110 $0.079 $0.120 $0.120 $0.170 $0.150 $0.150
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 7,825.000 $25.000 $17.060 $16.250 $22.250 $16.250 $16.250 $22.000 $22.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 20.000 $1,900.000 $1,359.750 $1,295.000 $1,575.000 $1,545.000 $1,295.000 $1,850.000 $1,800.000
540 6009 MTL BEAM GD FEN TRANS (T6) EA 22.000 $700.000 $488.250 $465.000 $775.000 $465.000 $465.000 $2,850.000 $600.000
540 6014 SHORT RADIUS LF 25.000 $40.000 $33.600 $32.000 $35.000 $32.000 $32.000 $35.000 $40.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 1.000 $1,100.000 $918.750 $875.000 $1,250.000 $875.000 $875.000 $1,850.000 $1,200.000
540 6017 MTL BM GD FEN (LONG SPAN SYSTEM) LF 200.000 $25.000 $23.100 $22.000 $30.000 $22.000 $22.000 $35.000 $25.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 9,475.000 $2.500 $1.580 $1.500 $3.000 $1.500 $1.500 $3.000 $3.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 1.000 $250.000 $105.000 $100.000 $110.000 $100.000 $100.000 $500.000 $250.000
544 6002 GUARDRAIL END TREATMENT (MOVE & RESET) EA 86.000 $1,200.000 $945.000 $900.000 $1,000.000 $900.000 $900.000 $1,250.000 $1,100.000
560 6014 MAILBOX INSTALL-S (TWG-POST) TY 4 EA 1.000 $350.000 $204.750 $195.000 $650.000 $110.000 $195.000 $650.000 $500.000
560 6022 MAILBOX INSTALL-D (TWG-POST) TY 4 EA 1.000 $400.000 $257.250 $245.000 $750.000 $150.000 $245.000 $650.000 $500.000
610 6009 REMOVE RD IL ASM (TRANS-BASE) EA 1.000 $535.000 $1,575.000 $1,500.000 $1,500.000 $500.000 $1,500.000 $50.000 $2,000.000
610 6083 IN RD IL AM (TY SA) 50T-8 (400W) S EA 1.000 $3,700.000 $5,460.000 $5,200.000 $5,200.000 $3,700.000 $5,200.000 $3,600.000 $7,000.000
618 6075 CONDT (RM) (3") (BORE) LF 85.000 $38.000 $44.100 $42.000 $42.000 $35.000 $42.000 $65.000 $45.000
622 6002 DCT CBL (3 NO.8) (2 INSULATED 1 BARE) LF 250.000 $12.660 $18.900 $18.000 $18.000 $16.000 $18.000 $20.000 $25.000
636 6002 ALUMINUM SIGNS (TY G) SF 50.000 $24.000 $26.250 $25.000 $30.000 $30.000 $25.000 $50.000 $30.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 75.000 $500.000 $435.750 $415.000 $550.000 $370.000 $415.000 $650.000 $700.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 11.000 $600.000 $488.250 $465.000 $575.000 $420.000 $465.000 $650.000 $800.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 6.000 $650.000 $687.750 $655.000 $650.000 $540.000 $655.000 $650.000 $900.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 1.000 $800.000 $813.750 $775.000 $650.000 $590.000 $775.000 $650.000 $1,000.000
644 6034 IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT) EA 1.000 $900.000 $876.750 $835.000 $725.000 $750.000 $835.000 $650.000 $1,300.000
644 6076 REMOVE SM RD SN SUP&AM EA 111.000 $95.000 $78.750 $75.000 $110.000 $45.000 $75.000 $50.000 $115.000
647 6001 INSTALL LRSS (STRUCT STEEL) LB 570.800 $4.750 $5.200 $5.000 $5.250 $15.000 $4.950 $8.500 $10.000
658 6048 INSTL OM ASSM (OM-2Z)(FLX)GND EA 98.000 $65.000 $39.900 $38.000 $65.000 $38.000 $38.000 $100.000 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 163.000 $35.000 $19.950 $19.000 $42.000 $19.000 $19.000 $100.000 $25.000
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 150,576.000 $0.150 $0.160 $0.150 $0.100 $0.150 $0.150 $0.200 $0.120
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 12,327.000 $0.800 $0.800 $0.500 $1.100 $0.780 $1.000 $2.000 $2.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 11,526.000 $0.750 $0.800 $0.500 $1.100 $0.780 $1.000 $2.000 $2.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 1,795.000 $0.800 $0.780 $0.740 $0.880 $0.740 $0.740 $1.000 $1.000
666 6045 REFL PAV MRK TY I (W)18"(SLD)(100MIL) LF 208.000 $4.000 $7.040 $6.700 $4.500 $6.700 $6.700 $5.000 $5.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 82.000 $5.000 $7.460 $7.100 $5.500 $7.100 $7.100 $10.000 $6.000
666 6054 REFL PAV MRK TY I (W)(ARROW)(100MIL) EA 9.000 $115.000 $123.900 $118.000 $145.500 $118.000 $118.000 $165.000 $170.000
666 6078 REFL PAV MRK TY I (W)(WORD)(100MIL) EA 11.000 $150.000 $148.050 $141.000 $180.500 $141.000 $141.000 $200.000 $200.000
666 6102 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 15.000 $25.000 $77.700 $74.000 $48.500 $74.000 $74.000 $100.000 $60.000
666 6147 REFL PAV MRK TY I (Y)24"(SLD)(100MIL) LF 2,120.000 $5.000 $6.410 $6.100 $5.250 $6.100 $6.100 $6.000 $6.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 5,440.000 $0.300 $0.370 $0.350 $0.420 $0.350 $0.350 $0.500 $0.460
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 213,720.000 $0.250 $0.320 $0.300 $0.350 $0.300 $0.300 $0.400 $0.380
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 14,510.000 $0.280 $0.370 $0.350 $0.420 $0.350 $0.350 $0.500 $0.460
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 143,355.000 $0.250 $0.320 $0.300 $0.350 $0.300 $0.300 $0.400 $0.380
672 6007 REFL PAV MRKR TY I-C EA 387.000 $3.000 $5.250 $5.000 $3.300 $5.000 $5.000 $5.000 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 3,417.000 $3.000 $3.150 $3.000 $3.300 $3.000 $3.000 $5.000 $4.000
5001 6002 GEOGRID BASE REINFORCEMENT (TY II) SY 50,930.000 $1.250 $3.740 $1.750 $2.400 $2.540 $1.950 $2.250 $2.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $16,154.960 $6,000.000 $13,000.000 $25,000.000 $24,000.000 $16,500.000 $20,000.000
6185 6002 TMA (STATIONARY) DAY 120.000 $115.000 $262.500 $300.000 $225.000 $950.000 $330.000 $400.000 $200.000
6185 6003 TMA (MOBILE OPERATION) HR 20.000 $128.000 $26.250 $100.000 $110.000 $1,130.000 $75.000 $150.000 $200.000
Totals: $9,586,977.31 $8,915,686.64 $9,007,814.56 $9,483,086.80 $9,999,211.73 $11,000,559.74 $11,389,779.15 $11,415,622.43