County: KAUFMAN Highway: FM2728 Date: 09/13/2023 (1 year ago) Engineer's Estimate: $267,000 Control Number: 6450-59-001
Project: MMC - 645059001 District: DALLAS Time: 180 CALENDAR DAYS Type: EMULSION
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $267,000.00
WRIGHT ASPHALT PRODUCTS COMPANY LLC   $262,200.00 1
-1.8% | -$4,800.00
ERGON ASPHALT & EMULSIONS, INC.   $264,300.00 2
-1.01% | -$2,700.00
0.8% | $2,100.00
MARTIN RESOURCE MANAGEMENT CORPORATION   $268,260.00 3
0.47% | $1,260.00
2.31% | $6,060.00
1.50% | $3,960.00

Bid Items

Items: 4, 0 filtered
KAUFMAN FM2728  |  DALLAS  |  6450-59-001  |  09/13/2023  |  $267,000  |  MMC - 645059001  |  EMULSION  |  180 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate WRIGHT ASPHALT PRODUCTS COMPANY LLC ERGON ASPHALT & EMULSIONS, INC. MARTIN RESOURCE MANAGEMENT CORPORATION
8010 6001 CUTBACK ASPHALT (RC-250)(DELIVERY) GAL 30,000.000 $4.400 $4.080 $4.320 $4.260
8010 6008 EMULSION (CSS-1H) (PICKUP) GAL 6,000.000 $3.000 $3.000 $2.750 $2.850
8010 6010 EMULSION (CSS-1H)(DELIVERY) GAL 6,000.000 $2.000 $3.150 $2.950 $3.260
8010 6012 EMULSION (CRS-2P)(DELIVERY) GAL 30,000.000 $3.500 $3.430 $3.350 $3.460
Totals: $267,000.00 $262,200.00 $264,300.00 $268,260.00