KAUFMAN FM 3039 (3089-01-013)
Items: 63
County: KAUFMAN
Length: 0.2840 MILES
Highway: FM 3039
District: DALLAS
Control Number: 3089-01-013
DBE Goal: 0.0%
Project: F 2026(772)
Guaranty: $15,000.00
Time: 79 WORKING DAYS
Engineer's Estimate: $726,590.00
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263030
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00196687
Contract Type: FEDERAL
Project Description: CONSTRUCT SIDEWALK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NICHOLAS WADLINGTON
CODY JOLLEY
KAUFMAN FM 3039 (3089-01-013)
Project Name: N/A
Project: F 2026(772)
Engineer's Estimate: $726,590.00
Length: 0.2840 MILES
Project Class: PEDESTRIAN, SIDEWALKS & CURB RAMPS
Limits From: SOUTH OF HUNTER LANE
Limits To: SOUTH OF WEST LEWIS
Project Description: CONSTRUCT SIDEWALK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$726,590.00 | |||
| $598,150.10 |
-17.68%
-$128,439.90
|
|||
| $640,294.25 |
-11.88%
-$86,295.75
|
7.05%
$42,144.15
|
||
| $685,106.19 |
-5.71%
-$41,483.81
|
14.54%
$86,956.09
|
-7.00%
-$44,811.94
|
|
| $698,125.47 |
-3.92%
-$28,464.53
|
16.71%
$99,975.37
|
-1.90%
-$13,019.28
|
|
| $754,504.10 |
3.84%
$27,914.10
|
26.14%
$156,354.00
|
-8.08%
-$56,378.63
|
|
| $789,378.15 |
8.64%
$62,788.15
|
31.97%
$191,228.05
|
-4.62%
-$34,874.05
|
|
| $852,159.50 |
17.28%
$125,569.50
|
42.47%
$254,009.40
|
-7.95%
-$62,781.35
|
|
| $944,534.00 |
30%
$217,944.00
|
57.91%
$346,383.90
|
-10.84%
-$92,374.50
|
|
| $1,176,330.30 |
61.9%
$449,740.30
|
96.66%
$578,180.20
|
-24.54%
-$231,796.30
|
E
Engineer's Estimate
$726,590.00
$598,150.10
Over/Under Est:
-17.68%
-$128,439.90
$640,294.25
Over/Under Est:
-11.88%
-$86,295.75
Amt Left:
7.05%
$42,144.15
$685,106.19
Over/Under Est:
-5.71%
-$41,483.81
Amt Left:
14.54%
$86,956.09
Delta:
-7.00%
-$44,811.94
$698,125.47
Over/Under Est:
-3.92%
-$28,464.53
Amt Left:
16.71%
$99,975.37
Delta:
-1.90%
-$13,019.28
$754,504.10
Over/Under Est:
3.84%
$27,914.10
Amt Left:
26.14%
$156,354.00
Delta:
-8.08%
-$56,378.63
$789,378.15
Over/Under Est:
8.64%
$62,788.15
Amt Left:
31.97%
$191,228.05
Delta:
-4.62%
-$34,874.05
$852,159.50
Over/Under Est:
17.28%
$125,569.50
Amt Left:
42.47%
$254,009.40
Delta:
-7.95%
-$62,781.35
$944,534.00
Over/Under Est:
30%
$217,944.00
Amt Left:
57.91%
$346,383.90
Delta:
-10.84%
-$92,374.50
$1,176,330.30
Over/Under Est:
61.9%
$449,740.30
Amt Left:
96.66%
$578,180.20
Delta:
-24.54%
-$231,796.30
Bid Items & Bid Tabulations
63
Total
0 of 63
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $15,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $15,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $40,000.00 |