KAUFMAN FM 3039 (3089-01-013)

Items: 63

County: KAUFMAN
Length: 0.2840 MILES
Highway: FM 3039
District: DALLAS
Control Number: 3089-01-013
DBE Goal: 0.0%
Project: F 2026(772)
Guaranty: $15,000.00
Time: 79 WORKING DAYS
Engineer's Estimate: $726,590.00
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263030
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00196687
Contract Type: FEDERAL
Project Description: CONSTRUCT SIDEWALK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NICHOLAS WADLINGTON
CODY JOLLEY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$726,590.00
$598,150.10
Over/Under Est: -17.68% -$128,439.90
Over/Under Est: -11.88% -$86,295.75
Amt Left: 7.05% $42,144.15
Over/Under Est: -5.71% -$41,483.81
Amt Left: 14.54% $86,956.09
Delta: -7.00% -$44,811.94
Over/Under Est: -3.92% -$28,464.53
Amt Left: 16.71% $99,975.37
Delta: -1.90% -$13,019.28
Over/Under Est: 3.84% $27,914.10
Amt Left: 26.14% $156,354.00
Delta: -8.08% -$56,378.63
Over/Under Est: 8.64% $62,788.15
Amt Left: 31.97% $191,228.05
Delta: -4.62% -$34,874.05
Over/Under Est: 17.28% $125,569.50
Amt Left: 42.47% $254,009.40
Delta: -7.95% -$62,781.35
Over/Under Est: 30% $217,944.00
Amt Left: 57.91% $346,383.90
Delta: -10.84% -$92,374.50
Over/Under Est: 61.9% $449,740.30
Amt Left: 96.66% $578,180.20
Delta: -24.54% -$231,796.30

Bid Items & Bid Tabulations

63 Total 0 of 63
KAUFMAN  |  FM 3039  |  DALLAS  |  3089-01-013  |  07/01/2026 1:00 PM CDT  |  $726,590.00  |  F 2026(772)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
C & W SOUTHERN LLC
ICOS MANAGEMENT, LLC
TUCAN CONTRACTING, LLC
THK CONSTRUCTION LLC
HIGHWAY 19 CONSTRUCTION LLC
FOUTSCO PAVING COMPANY, LLC
CENTRAL NORTH CONSTRUCTION, LLC
CROSS PLUS CONSTRUCTION, LLC
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 15.000 $1,283.000 $200.000 $1,260.000 $2,200.000 $1,250.000 $5,000.000 $1,000.000 $6,500.000 $1,500.000 $3,500.000
REMOV CONC (MOWSTRIP)
SY 132.000 $18.000 $10.000 $26.250 $4.130 $10.000 $25.000 $21.400 $18.000 $50.000 $40.000
REMOV CONC (RIPRAP)
SY 206.000 $18.000 $15.000 $26.250 $22.000 $10.000 $25.000 $21.600 $16.000 $40.000 $40.000
EXCAV (ROADWAY)
CY 105.000 $75.000 $25.000 $52.500 $33.000 $20.000 $30.000 $42.100 $26.000 $75.000 $80.000
EMBANK (FNL)(OC)(TY C)
CY 659.000 $45.000 $30.000 $42.000 $27.500 $20.000 $50.000 $43.600 $40.000 $50.000 $60.000
COMPOST MANUF TOPSOIL (4")
SY 1,836.000 $3.000 $12.000 $3.150 $6.600 $6.600 $5.000 $9.750 $4.500 $9.000 $1.500
BLOCK SODDING
SY 1,836.000 $8.000 $7.000 $6.300 $7.700 $7.700 $5.000 $4.750 $6.000 $10.000 $6.000
DRILL SEED (TEMP_WARM_COOL)
SY 1,836.000 $0.500 $0.300 $0.600 $2.080 $2.079 $0.100 $0.750 $2.000 $10.000 $0.800
VEGETATIVE WATERING
TGL 546.000 $1.500 $2.000 $5.250 $16.500 $1.000 $10.000 $25.000 $24.000 $100.000 $5.000
TEMPORARY SPL SHORING
SF 503.000 $35.000 $25.000 $5.250 $22.000 $40.000 $55.000 $103.000 $40.000 $80.000 $175.000
CL C CONC (RAIL FOUNDATION)
CY 16.000 $1,000.000 $950.000 $1,050.000 $825.000 $1,000.000 $1,500.000 $855.400 $1,200.000 $450.000 $1,500.000
CL C CONC (MISC)
CY 3.000 $1,800.000 $1,000.000 $1,575.000 $1,155.000 $1,000.000 $2,500.000 $1,093.000 $3,150.000 $500.000 $2,500.000
RIPRAP (MOW STRIP)(4 IN)
CY 14.000 $900.000 $800.000 $735.000 $770.000 $800.000 $550.000 $640.400 $2,800.000 $500.000 $1,700.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 398.000 $155.000 $165.000 $168.000 $198.000 $200.000 $180.000 $164.100 $250.000 $300.000 $275.000
RAIL (TY C221)
LF 103.000 $220.000 $250.000 $475.500 $242.000 $200.000 $250.000 $142.900 $125.000 $450.000 $400.000
RAIL (HANDRAIL)(TY E)
LF 110.000 $225.000 $140.000 $262.500 $220.000 $222.990 $180.000 $166.900 $150.000 $450.000 $200.000
CONC BOX CULV (10 FT X 10 FT)(EXTEND)
LF 20.000 $3,500.000 $2,000.000 $1,575.000 $2,750.000 $1,500.000 $1,800.000 $1,929.000 $2,100.000 $2,300.000 $2,300.000
RC PIPE (CL III)(18 IN)
LF 10.000 $125.000 $80.000 $126.000 $93.500 $100.000 $70.000 $115.000 $100.000 $150.000 $190.000
RC PIPE (CL III)(24 IN)
LF 99.000 $120.000 $90.000 $210.000 $110.000 $120.000 $110.000 $94.700 $120.000 $220.000 $200.000
WINGWALL (SW - 0) (HW=12 FT)
EA 1.000 $55,000.000 $45,000.000 $26,250.000 $22,000.000 $60,000.000 $48,000.000 $24,340.400 $12,000.000 $10,000.000 $65,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 4.000 $1,500.000 $900.000 $1,050.000 $2,750.000 $1,000.000 $800.000 $1,086.200 $5,500.000 $3,500.000 $2,050.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 9.000 $1,300.000 $1,280.000 $1,575.000 $2,310.000 $1,200.000 $1,500.000 $1,985.800 $2,200.000 $4,000.000 $2,950.000
CLEAN EXIST CULVERTS
EA 1.000 $3,000.000 $5,000.000 $5,250.000 $4,400.000 $10,000.000 $5,000.000 $4,896.300 $10,000.000 $1,000.000 $34,000.000
REMOV STR (SET)
EA 2.000 $500.000 $500.000 $525.000 $550.000 $500.000 $1,000.000 $1,257.000 $5,000.000 $500.000 $510.000
REMOV STR (WINGWALL)
EA 1.000 $1,800.000 $2,000.000 $4,200.000 $1,320.000 $2,500.000 $1,000.000 $4,289.700 $1,800.000 $1,200.000 $15,000.000
REMOV STR (BOX CULVERT)
LF 3.000 $70.000 $1,000.000 $840.000 $55.000 $500.000 $100.000 $456.100 $500.000 $10,000.000 $3,100.000
MOBILIZATION
LS 1.000 $66,040.000 $65,000.000 $53,960.000 $55,000.000 $70,000.000 $50,000.000 $78,000.000 $50,000.000 $75,000.000 $106,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $10,000.000 $1,500.000 $1.100 $1,320.000 $1,506.300 $5,000.000 $30,000.000 $6,500.000 $5,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,000.000 $7,500.000 $4,200.000 $11,000.000 $20,000.000 $5,000.000 $10,000.000 $2,500.000 $10.000 $22,000.000
TMA (STATIONARY)
DAY 79.000 $300.000 $275.000 $262.500 $231.000 $300.000 $250.000 $1.000 $350.000 $400.000 $150.000
TMA (MOBILE OPERATION)
DAY 5.000 $400.000 $350.000 $420.000 $385.000 $300.000 $1,000.000 $1.000 $1,500.000 $400.000 $75.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $55.000 $47.000 $10.500 $55.000 $55.000 $60.000 $40.000 $50.000 $10.000 $60.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 60.000 $80.000 $115.000 $10.500 $97.900 $97.900 $110.000 $85.000 $55.000 $10.000 $135.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $15.000 $1.000 $5.250 $13.200 $13.200 $10.000 $14.000 $20.000 $1.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 176.000 $40.000 $15.000 $10.500 $46.200 $46.200 $5.000 $35.500 $45.000 $30.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 176.000 $10.000 $1.000 $5.250 $13.200 $13.200 $1.000 $9.000 $10.000 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 964.000 $3.000 $3.200 $2.100 $5.500 $5.500 $4.000 $3.650 $2.750 $1.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 964.000 $1.000 $1.000 $1.100 $1.100 $1.100 $1.000 $1.000 $1.000 $1.000 $1.250
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,027.000 $5.000 $4.500 $10.500 $7.150 $7.150 $10.000 $5.750 $5.000 $10.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,027.000 $1.000 $1.000 $5.250 $0.550 $0.550 $1.000 $1.200 $1.000 $1.000 $1.250
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 140.000 $70.000 $85.000 $189.000 $165.000 $100.000 $100.000 $80.000 $148.000 $40.000 $55.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $50.000 $69.000 $210.000 $165.000 $100.000 $125.000 $80.000 $174.000 $40.000 $200.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 140.000 $18.000 $40.000 $26.250 $55.000 $25.000 $25.000 $40.000 $30.000 $20.000 $55.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $14.000 $20.000 $26.250 $55.000 $25.000 $25.000 $40.000 $30.000 $20.000 $55.000
CONC SIDEWALKS (4")
SY 324.000 $123.000 $100.000 $84.000 $82.500 $100.000 $85.000 $73.900 $81.000 $139.000 $140.000
CONCRETE SIDEWALK (RETAINING WALL)
CY 47.000 $700.000 $650.000 $525.000 $935.000 $300.000 $1,100.000 $786.000 $750.000 $690.000 $2,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 138.000 $35.000 $25.750 $36.750 $38.500 $32.310 $35.000 $22.500 $26.000 $33.000 $24.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,500.000 $1,700.000 $2,310.000 $2,420.000 $1,870.000 $3,100.000 $1,800.000 $2,500.000 $2,350.000 $3,250.000
REMOVE METAL BEAM GUARD FENCE
LF 307.000 $3.000 $2.500 $4.200 $3.300 $2.750 $5.000 $3.000 $10.000 $20.000 $3.250
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,100.000 $3,150.000 $4,200.000 $3,795.000 $3,465.000 $2,800.000 $2,950.000 $10,000.000 $4,000.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $200.000 $200.000 $525.000 $330.000 $220.000 $250.000 $250.000 $3,300.000 $200.000 $275.000
ALUMINUM SIGNS (TY A)
SF 23.500 $42.000 $40.000 $42.000 $38.500 $38.000 $35.000 $35.000 $35.000 $100.000 $40.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $605.000 $1,000.000 $1,050.000 $753.500 $800.000 $850.000 $685.000 $800.000 $1,000.000 $725.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $30.000 $40.000 $52.500 $30.800 $27.500 $45.000 $25.000 $150.000 $440.000 $27.000
INSTL OM ASSM (OM-2Z)(WFLX)GNDLL(BI)
EA 6.000 $50.000 $45.000 $210.000 $165.000 $100.000 $45.000 $75.000 $275.000 $440.000 $80.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 76.000 $12.000 $26.000 $31.500 $27.500 $27.500 $25.000 $12.000 $18.000 $55.000 $27.000
PAVEMENT SLER 6"
LF 32.000 $2.000 $20.000 $26.250 $11.000 $11.000 $5.000 $1.000 $8.000 $30.000 $22.000
PAVEMENT SLER 24"
LF 76.000 $12.000 $13.000 $26.250 $16.500 $16.500 $5.000 $2.000 $8.000 $30.000 $22.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 16.000 $5.000 $20.000 $26.250 $11.000 $11.000 $20.000 $2.000 $50.000 $20.000 $22.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 16.000 $5.000 $20.000 $26.250 $11.000 $11.000 $20.000 $2.000 $50.000 $30.000 $22.000
ELIM EXT PM & MRKS (12")
LF 87.000 $1.000 $20.000 $26.250 $16.500 $16.500 $5.000 $3.000 $25.000 $20.000 $22.000
FULL - WIDTH MOWING
CYC 2.000 $4,000.000 $500.000 $1,050.000 $1,650.000 $5,000.000 $5,000.000 $5,000.000 $12,000.000 $10,000.000 $8,000.000
SOLAR-POWERED RRFB (ONE-WAY WIRELESS)
EA 2.000 $9,500.000 $10,000.000 $15,750.000 $5,500.000 $20,000.000 $15,000.000 $10,000.000 $8,200.000 $9,000.000 $10,000.000
Totals: $726,590.000 $598,150.100 $640,294.250 $685,106.190 $698,125.474 $754,504.100 $789,378.150 $852,159.500 $944,534.000 $1,176,330.300
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $40,000.00