KAUFMAN US 80 (0095-04-079)

Items: 29

County: KAUFMAN
Length: 0.0590 MILES
Highway: US 80
District: DALLAS
Control Number: 0095-04-079
DBE Goal: 0.0%
Project: F 2026(859)
Guaranty: $22,000.00
Time: 35 WORKING DAYS
Engineer's Estimate: $1,290,272.50
Date: 1:00 PM AUGUST 05, 2026 (in 5 weeks)
Contract Number: 8263038
Type: BRIDGE MAINTENANCE
Project ID: A00217911
Contract Type: Federal
Project Description: STABILIZE ERODED CHANNEL BANKS AND INSTALL STONE RIPRAP WITHIN THE CHANNEL AND AROUND BRIDGE BENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
KAUFMAN US 80 (0095-04-079)
Project Name: N/A
Project: F 2026(859)
Length: 0.0580 MILES
Project Type: CONSTRUCTION
Limits From: AT BIG BRUSHY CREEK
Limits To: .
Project Description: STABILIZE ERODED CHANNEL BANKS AND INSTALL STONE RIPRAP WITHIN THE CHANNEL AND AROUND BRIDGE BENTS
Actions:
Notice Questions HCS Excel Print Print Notice

Bid Items & Bid Tabulations

29 Total 0 of 29
KAUFMAN  |  US 80  |  DALLAS  |  0095-04-079  |  1:00 PM AUGUST 05, 2026  |  $1,290,272.50  |  F 2026(859)  |  BRIDGE MAINT  |  35 WORKING DAYS
Item Code
Description
Unit
Quantity
PREPARING ROW
STA 3.110
REMOV CONC (RIPRAP)
SY 380.000
EXCAV (CHANNEL)
CY 4,695.000
EMBANK (FNL)(OC)(TY C2)
CY 9.000
BLOCK SODDING
SY 1,174.000
VEGETATIVE WATERING
TGL 174.000
FLOWABLE BACKFILL
CY 12.000
RIPRAP (MOW STRIP)(4 IN)
CY 28.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 3,995.000
GABION MATTRESSES (GALV) (24 IN)
SY 68.000
GABIONS (3' X 3')(GALV)
CY 160.000
REMOVING ROCK RIPRAP
CY 620.000
MOBILIZATION
LS 1.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000
TMA (STATIONARY)
DAY 6.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 220.000
ROCK FILTER DAMS (REMOVE)
LF 220.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 440.000
CONSTRUCTION EXITS (REMOVE)
SY 440.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 550.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 550.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 220.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 220.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 4.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1 (BI)
EA 4.000
DEBRIS REMOVAL (SPOT DEBRIS)
MI 0.050
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $30,000.00