HUNT SH 34 (0173-07-062)
Items: 67
County: HUNT
Length: 1.1180 MILES
Highway: SH 34
District: PARIS
Control Number: 0173-07-062
DBE Goal: 4.0%
Project: STP 2025(724)HES
Guaranty: $85,000.00
Time: 144 WORKING DAYS
Engineer's Estimate: $4,309,128.28
Date: 05/02/2025 1:00 PM CDT (1 year ago)
Contract Number: 5253220
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184738
Contract Type: FEDERAL
Project Description: INSTALL CONTINUOUS TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ATKINS
WILLIE BOLDEN
HUNT SH 34 (0173-07-062)
Project Name: N/A
Project: STP 2025(724)HES
Length: 1.1180 MILES
Project Class: CONSTRUCTION
Limits From: TRADERS RD
Limits To: FM 1570
Project Description: INSTALL CONTINUOUS TURN LANE
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,309,128.28 | |||
| $4,125,933.95 |
-4.25%
-$183,194.33
|
|||
| $4,172,220.50 |
-3.18%
-$136,907.78
|
1.12%
$46,286.55
|
||
| $4,290,618.54 |
-0.43%
-$18,509.74
|
3.99%
$164,684.59
|
-2.84%
-$118,398.04
|
|
| $4,446,087.14 |
3.18%
$136,958.86
|
7.76%
$320,153.19
|
-3.62%
-$155,468.60
|
|
| $4,809,978.40 |
11.62%
$500,850.12
|
16.58%
$684,044.45
|
-8.18%
-$363,891.26
|
|
| $7,052,939.24 |
63.67%
$2,743,810.96
|
70.94%
$2,927,005.29
|
-46.63%
-$2,242,960.84
|
E
Engineer's Estimate
$4,309,128.28
1
$4,125,933.95
Over/Under Est:
-4.25%
-$183,194.33
$4,172,220.50
Over/Under Est:
-3.18%
-$136,907.78
Amt Left:
1.12%
$46,286.55
$4,290,618.54
Over/Under Est:
-0.43%
-$18,509.74
Amt Left:
3.99%
$164,684.59
Delta:
-2.84%
-$118,398.04
$4,446,087.14
Over/Under Est:
3.18%
$136,958.86
Amt Left:
7.76%
$320,153.19
Delta:
-3.62%
-$155,468.60
$4,809,978.40
Over/Under Est:
11.62%
$500,850.12
Amt Left:
16.58%
$684,044.45
Delta:
-8.18%
-$363,891.26
$7,052,939.24
Over/Under Est:
63.67%
$2,743,810.96
Amt Left:
70.94%
$2,927,005.29
Delta:
-46.63%
-$2,242,960.84
Bid Items & Bid Tabulations
67
Total
0 of 67
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $42,297.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $84,594.00 |
| Total: | $126,891.00 |