HOUSTON FM 3016 (3110-01-003)
Items: 87
County: HOUSTON
Length: 0.0000 MILES (2.3743 MILES)
Highway: FM 3016
District: LUFKIN
Control Number: 3110-01-003
DBE Goal: 0.0%
Project: STP 2026(746)HES
Guaranty: $92,000.00
Time: 156 WORKING DAYS
Engineer's Estimate: $4,104,552.80
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263015
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206568
Contract Type: FEDERAL
Project Description: SAFETY TREAT FIXED OBJECTS, MILLED EDGELINE RUMBLE STRIPS, REHAB EXISTING AND PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED CENTERLINE RUMBLE STRIPS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESSE SISCO
HOUSTON FM 3016 (3110-01-003)
Project Name: N/A
Project: STP 2026(746)HES
Engineer's Estimate: $4,104,552.80
Length: 0.0000 MILES (2.3743 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: FM 228
Limits To: CR 1685
Project Description: SAFETY TREAT FIXED OBJECTS, MILLED EDGELINE RUMBLE STRIPS, REHAB EXISTING AND PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED CENTERLINE RUMBLE STRIPS
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,104,552.80 | |||
| $3,814,102.44 |
-7.08%
-$290,450.36
|
|||
| $3,853,111.26 |
-6.13%
-$251,441.54
|
1.02%
$39,008.82
|
||
| $3,925,687.78 |
-4.36%
-$178,865.02
|
2.93%
$111,585.34
|
-1.88%
-$72,576.52
|
|
| $4,041,533.51 |
-1.54%
-$63,019.29
|
5.96%
$227,431.07
|
-2.95%
-$115,845.73
|
|
| $4,166,237.01 |
1.5%
$61,684.21
|
9.23%
$352,134.57
|
-3.09%
-$124,703.50
|
E
Engineer's Estimate
$4,104,552.80
$3,814,102.44
Over/Under Est:
-7.08%
-$290,450.36
$3,853,111.26
Over/Under Est:
-6.13%
-$251,441.54
Amt Left:
1.02%
$39,008.82
$3,925,687.78
Over/Under Est:
-4.36%
-$178,865.02
Amt Left:
2.93%
$111,585.34
Delta:
-1.88%
-$72,576.52
$4,041,533.51
Over/Under Est:
-1.54%
-$63,019.29
Amt Left:
5.96%
$227,431.07
Delta:
-2.95%
-$115,845.73
$4,166,237.01
Over/Under Est:
1.5%
$61,684.21
Amt Left:
9.23%
$352,134.57
Delta:
-3.09%
-$124,703.50
Bid Items & Bid Tabulations
87
Total
0 of 87
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| Total: | $4,000.00 |