Job Info for 0901-28-097

County: HOPKINS Highway: CR Date: 05/05/2023 (1 year ago) Engineer's Estimate: $958,568 Control Number: 0901-28-097
Project: BR 2022(357) District: PARIS Time: 128 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $958,568.40
THK CONSTRUCTION LLC   $842,684.36 1
-12.09% | -$115,884.04
HIGHWAY 19 CONSTRUCTION LLC   $948,430.40 2
-1.06% | -$10,138.00
12.55% | $105,746.04
HODGES AND SON CONSTRUCTION COMPANY, INC.   $999,627.90 3
4.28% | $41,059.50
18.62% | $156,943.54
5.40% | $51,197.50

Bid Items

Items: 36, 0 filtered
HOPKINS CR  |  PARIS  |  0901-28-097  |  05/05/2023  |  $958,568  |  BR 2022(357)  |  BRIDGE REPL  |  128 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate THK CONSTRUCTION LLC HIGHWAY 19 CONSTRUCTION LLC HODGES AND SON CONSTRUCTION COMPANY, INC.
100 6002 PREPARING ROW STA 7.260 $2,000.000 $1,500.000 $2,500.000 $4,200.000
110 6001 EXCAVATION (ROADWAY) CY 200.000 $25.000 $18.000 $25.000 $25.000
110 6002 EXCAVATION (CHANNEL) CY 1,732.000 $30.000 $15.000 $25.000 $15.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 732.000 $30.000 $18.000 $30.000 $30.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 818.000 $0.300 $0.010 $1.000 $2.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 818.000 $0.300 $0.010 $1.000 $2.000
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 1,636.000 $2.000 $4.410 $2.000 $3.000
168 6001 VEGETATIVE WATERING MG 20.000 $20.000 $20.000 $100.000 $1.000
247 6064 FL BS (CMP IN PLC)(TY A GR 4) (6") SY 808.000 $32.000 $40.000 $27.000 $50.000
251 6478 REWORK BS MTL (TY B) (9-18") (ORD COMP) SY 472.000 $20.000 $40.000 $11.000 $12.000
400 6005 CEM STABIL BKFL CY 79.000 $200.000 $250.000 $250.000 $250.000
416 6002 DRILL SHAFT (24 IN) LF 276.000 $175.000 $156.000 $157.000 $135.000
416 6004 DRILL SHAFT (36 IN) LF 276.000 $250.000 $202.000 $164.000 $180.000
420 6013 CL C CONC (ABUT) CY 56.800 $1,200.000 $1,000.000 $1,194.000 $1,500.000
422 6001 REINF CONC SLAB SF 1,950.000 $30.000 $25.000 $31.000 $35.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 1,170.000 $25.000 $20.000 $25.000 $26.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 222.110 $260.000 $297.150 $320.000 $290.000
425 6035 PRESTR CONC GIRDER (TX28) LF 298.000 $250.000 $262.570 $301.000 $330.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 896.000 $200.000 $164.000 $180.000 $205.000
450 6019 RAIL (TY T631LS) LF 300.000 $75.000 $78.750 $66.000 $80.000
464 6002 RC PIPE (CL III)(15 IN) LF 20.000 $95.000 $90.000 $50.000 $200.000
467 6341 SET (TY II) (15 IN) (RCP) (6: 1) (P) EA 2.000 $790.000 $1,000.000 $1,000.000 $4,000.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 2.000 $13,000.000 $5,000.000 $10,000.000 $10,000.000
496 6016 REMOV STR (PIPE) EA 1.000 $350.000 $200.000 $500.000 $500.000
500 6001 MOBILIZATION LS 1.000 $87,143.000 $70,000.000 $100,000.000 $85,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $2,000.000 $1,134.000 $1,925.000 $1,200.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 82.000 $35.000 $40.000 $35.000 $1.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 82.000 $10.000 $1.000 $10.000 $1.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 178.000 $20.000 $1.000 $1.000 $1.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 178.000 $6.000 $1.000 $1.000 $1.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,300.000 $5.000 $3.500 $3.000 $1.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,300.000 $2.000 $1.000 $1.000 $1.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 200.000 $30.000 $2.400 $27.000 $30.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $3,100.000 $3,071.250 $3,000.000 $3,000.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 24.000 $30.000 $31.500 $35.000 $30.000
3076 6003 D-GR HMA TY-B PG64-22 (EXEMPT) TON 160.000 $130.000 $246.490 $250.000 $250.000
Totals: $958,568.40 $842,684.37 $948,430.40 $999,627.90