HOPKINS SL 301 (0400-03-015)
Items: 51
County: HOPKINS
Length: N/A
Highway: SL 301
District: PARIS
Control Number: 0400-03-015
DBE Goal: N/A
Project: BR 2022(802)
Guaranty: N/A
Time: 250 WORKING DAYS
Engineer's Estimate: $1,394,680.00
Date: 08/03/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,394,680.00 | |||
| $1,347,538.80 |
-3.38%
-$47,141.20
|
|||
| $1,452,649.38 |
4.16%
$57,969.38
|
7.8%
$105,110.58
|
||
| $1,604,194.60 |
15.02%
$209,514.60
|
19.05%
$256,655.80
|
-10.43%
-$151,545.22
|
|
| $1,711,914.00 |
22.75%
$317,234.00
|
27.04%
$364,375.20
|
-6.71%
-$107,719.40
|
E
Engineer's Estimate
$1,394,680.00
1
Awarded
$1,347,538.80
Over/Under Est:
-3.38%
-$47,141.20
$1,452,649.38
Over/Under Est:
4.16%
$57,969.38
Amt Left:
7.8%
$105,110.58
$1,604,194.60
Over/Under Est:
15.02%
$209,514.60
Amt Left:
19.05%
$256,655.80
Delta:
-10.43%
-$151,545.22
$1,711,914.00
Over/Under Est:
22.75%
$317,234.00
Amt Left:
27.04%
$364,375.20
Delta:
-6.71%
-$107,719.40
| Subcontractor | Percentage | Amount |
|---|---|---|
| SOUTHERN CROSS CONTRACTORS, LLC | 7.49% | $102,797.60 |
| FLEX SUPPLY, LLC | 1.82% | $24,978.86 |
| HERMANOS STEEL, LLC | 0.36% | $4,940.87 |
| A. E. MOORE CONSTRUCTION, INC. | 0.24% | $3,293.92 |
| Total: | 9.91% | $136,011.25 |