Job Info for 0108-03-041

County: HENDERSON Highway: SH 19 Date: 09/06/2024 (2 months ago) Engineer's Estimate: $20,755,210 Control Number: 0108-03-041
Project: C 108-3-41 District: TYLER Time: 300 WORKING DAYS Type: HIGHWAY IMPROVEMENT
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $20,755,210.28
BIG CREEK CONSTRUCTION, LTD.   $13,887,918.16 1
-33.09% | -$6,867,292.12
REYNOLDS & KAY, LTD.   $16,584,648.30 2
-20.09% | -$4,170,561.98
19.42% | $2,696,730.14
A. L. HELMCAMP, INC.   $17,511,205.34 3
-15.63% | -$3,244,004.94
26.09% | $3,623,287.18
5.59% | $926,557.04
TRUE ROADS, LLC   $20,210,735.15 4
-2.62% | -$544,475.13
45.53% | $6,322,816.99
15.42% | $2,699,529.81

Bid Items

Items: 124, 0 filtered
HENDERSON SH 19  |  TYLER  |  0108-03-041  |  09/06/2024  |  $20,755,210  |  C 108-3-41  |  HWY IMPRV  |  300 WORKING DAYS
Alt Item code Description Unit Quantity Engineer's Estimate BIG CREEK CONSTRUCTION, LTD. REYNOLDS & KAY, LTD. A. L. HELMCAMP, INC. TRUE ROADS, LLC
100 7002 PREPARING ROW STA 476.810 $2,000.000 $2,000.000 $2,600.000 $2,500.000 $5,000.000
104 7005 REMOV CONC (MOWSTRIP) LF 3,402.000 $17.140 $15.000 $14.000 $12.000 $10.000
104 7011 REMOV CONC (DRIVEWAYS) SY 150.000 $36.000 $25.000 $28.000 $55.000 $28.500
105 7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV SY 6,938.000 $4.650 $12.000 $6.750 $15.000 $5.000
110 7001 EXCAV (ROADWAY) CY 13,074.000 $35.000 $24.000 $9.750 $40.000 $26.000
132 7006 EMBANK (FNL)(DC)(TY C) CY 4,283.000 $30.000 $24.000 $34.000 $40.000 $32.000
134 7001 BACKFILL (TY A) STA 339.700 $496.500 $275.000 $525.000 $350.000 $450.000
160 7002 FURN & PLACE TOPSOIL (4") SY 88,865.000 $3.500 $1.250 $3.700 $2.200 $5.000
164 7001 BROADCAST SEED (PERM_RURAL_SAND) SY 44,436.000 $0.210 $0.150 $0.120 $0.140 $0.160
164 7074 BONDED FBR MTRX SEED (TEMP)(WARM) SY 44,436.000 $0.600 $0.580 $0.600 $0.560 $0.680
164 7075 BONDED FBR MTRX SEED (TEMP)(COOL) SY 44,436.000 $0.600 $0.580 $0.630 $0.560 $0.680
164 7076 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 88,865.000 $1.200 $0.600 $0.700 $0.580 $0.700
168 7001 VEGETATIVE WATERING TGL 977.500 $332.650 $25.000 $25.000 $20.000 $25.000
247 7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 8,360.000 $43.000 $86.000 $110.000 $135.000 $125.000
260 7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) TON 253.000 $450.000 $350.000 $350.000 $325.000 $450.000
260 7007 LIME TRT (EXIST MATL)(8") SY 12,232.000 $5.000 $7.000 $6.500 $9.000 $10.000
275 7001 CEMENT TON 253.000 $350.000 $275.000 $300.000 $250.000 $335.000
275 7003 CEMENT TRT (EXIST MATL)(8") SY 12,232.000 $5.000 $7.000 $5.750 $9.000 $6.500
314 7010 EMULS ASPH (EROSN CONT)(CSS-1) GAL 2,139.000 $8.160 $6.000 $7.000 $7.500 $9.000
316 7068 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) GAL 112,135.000 $7.000 $3.500 $4.450 $4.250 $7.000
316 7148 AGGR (TY-PD, GR-4)(SAC-A) CY 2,670.000 $200.000 $135.000 $195.000 $150.000 $280.000
344 7001 SP MIXES SP-B PG64-22 TON 1,453.000 $260.000 $135.000 $203.000 $186.000 $210.000
344 7019 SP MIXES SP-C PG70-22 TON 21,032.000 $184.670 $135.000 $186.000 $190.000 $185.000
344 7021 SP MIXES SP-C SAC-B PG70-22 TON 11,624.000 $272.000 $135.000 $171.000 $185.000 $195.000
344 7077 TACK COAT GAL 26,739.000 $4.700 $4.000 $3.050 $4.000 $6.000
351 7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 3,500.000 $85.000 $65.000 $65.000 $88.000 $85.000
351 7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 3,500.000 $163.000 $85.000 $82.000 $110.000 $105.000
354 7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") SY 187,543.000 $4.500 $3.250 $2.950 $2.500 $4.000
401 7001 FLOWABLE BACKFILL CY 33.000 $518.370 $350.000 $600.000 $370.000 $500.000
402 7001 TRENCH EXCAVATION PROTECTION LF 86.000 $50.000 $20.000 $10.000 $22.000 $40.000
429 7007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 111.000 $279.040 $250.000 $175.000 $530.000 $150.000
432 7013 RIPRAP (MOW STRIP)(4 IN) CY 259.000 $747.750 $650.000 $755.000 $1,000.000 $720.000
432 7043 RIPRAP (STONE PROTECTION)(18 IN) CY 346.000 $211.770 $225.000 $400.000 $320.000 $350.000
438 7004 CLEANING AND SEALING EXIST JOINTS (CL3) LF 360.000 $58.000 $60.000 $70.000 $68.000 $65.000
450 7020 RAIL (TY T631) LF 500.000 $99.600 $80.000 $90.000 $90.000 $125.000
462 7056 CONC BOX CULV (3 FT X 2 FT)(EXTEND) LF 8.000 $770.000 $850.000 $1,800.000 $700.000 $2,300.000
462 7057 CONC BOX CULV (3 FT X 3 FT)(EXTEND) LF 19.000 $1,400.000 $1,000.000 $1,600.000 $750.000 $2,400.000
462 7059 CONC BOX CULV (4 FT X 3 FT)(EXTEND) LF 4.000 $1,050.000 $1,050.000 $1,850.000 $800.000 $2,500.000
462 7060 CONC BOX CULV (4 FT X 4 FT)(EXTEND) LF 16.000 $842.000 $1,100.000 $1,400.000 $920.000 $2,500.000
462 7063 CONC BOX CULV (5 FT X 4 FT)(EXTEND) LF 11.000 $990.000 $1,200.000 $2,100.000 $960.000 $2,600.000
462 7067 CONC BOX CULV (6 FT X 4 FT)(EXTEND) LF 15.000 $1,400.000 $1,400.000 $1,800.000 $1,100.000 $2,300.000
462 7069 CONC BOX CULV (6 FT X 6 FT)(EXTEND) LF 3.000 $1,200.000 $1,600.000 $3,300.000 $1,300.000 $4,600.000
462 7073 CONC BOX CULV (7 FT X 6 FT)(EXTEND) LF 10.000 $1,287.000 $1,800.000 $2,200.000 $1,400.000 $3,000.000
466 7174 WINGWALL (PW - 1) (HW=4 FT) EA 1.000 $25,996.290 $15,000.000 $15,000.000 $7,400.000 $17,000.000
466 7175 WINGWALL (PW - 1) (HW=5 FT) EA 5.000 $21,616.030 $20,000.000 $15,000.000 $13,000.000 $17,000.000
466 7176 WINGWALL (PW - 1) (HW=6 FT) EA 5.000 $34,278.690 $25,000.000 $21,500.000 $15,000.000 $21,500.000
466 7177 WINGWALL (PW - 1) (HW=7 FT) EA 1.000 $33,000.000 $30,000.000 $28,000.000 $17,000.000 $29,000.000
466 7179 WINGWALL (PW - 1) (HW=9 FT) EA 1.000 $67,000.000 $50,000.000 $36,000.000 $28,000.000 $32,000.000
467 7004 SET (REPLACE PIPE RUNNER) EA 9.000 $9,583.330 $5,000.000 $100.000 $1,000.000 $6,000.000
467 7041 SET (TY I)(S= 3 FT)(HW= 3 FT)(4:1)(C) EA 2.000 $11,000.000 $10,000.000 $16,000.000 $7,900.000 $13,000.000
467 7044 SET (TY I)(S= 3 FT)(HW= 4 FT)(3:1)(C) EA 2.000 $17,000.000 $12,000.000 $16,000.000 $8,500.000 $14,000.000
467 7045 SET (TY I)(S= 3 FT)(HW= 4 FT)(4:1)(C) EA 1.000 $13,950.000 $15,000.000 $22,000.000 $8,900.000 $18,000.000
467 7104 SET (TY I)(S= 5 FT)(HW= 5 FT)(4:1)(C) EA 1.000 $17,000.000 $17,000.000 $30,000.000 $13,000.000 $18,000.000
467 7108 SET (TY I)(S= 5 FT)(HW= 6 FT)(4:1)(C) EA 1.000 $10,992.310 $20,000.000 $26,000.000 $14,000.000 $19,000.000
467 7166 SET (TY I)(S= 7 FT)(HW= 7 FT)(4:1)(C) EA 1.000 $12,700.000 $30,000.000 $45,000.000 $16,000.000 $42,000.000
467 7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 109.000 $1,750.000 $1,200.000 $1,150.000 $1,000.000 $1,100.000
467 7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 12.000 $2,450.000 $1,600.000 $2,400.000 $2,600.000 $1,800.000
468 7001 THERMOPLASTIC PIPE (PP) (18") LF 2,752.000 $81.000 $0.000 $0.000 $0.000 $0.000
468 7002 THERMOPLASTIC PIPE (PP) (24") LF 239.000 $134.000 $0.000 $0.000 $0.000 $0.000
480 7001 CLEAN EXIST CULVERTS EA 24.000 $3,400.000 $2,000.000 $5,000.000 $2,600.000 $2,700.000
480 7002 CLEAN EXIST CULVERTS CY 1,120.000 $53.000 $35.000 $16.000 $50.000 $110.000
496 7037 REMOV STR (PIPE) EA 54.000 $826.180 $475.000 $850.000 $1,600.000 $500.000
500 7001 MOBILIZATION LS 1.000 $1,752,733.450 $1,300,000.000 $1,185,000.000 $1,450,000.000 $1,500,000.000
502 7001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 20.000 $7,500.000 $7,500.000 $7,500.000 $28,400.000 $15,000.000
503 7002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $18,342.000 $15,000.000 $20,000.000 $25,000.000 $25,000.000
505 7001 TMA (STATIONARY) DAY 50.000 $350.000 $500.000 $200.000 $350.000 $225.000
505 7003 TMA (MOBILE OPERATION) DAY 50.000 $305.000 $550.000 $200.000 $100.000 $225.000
506 7001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 1,600.000 $42.000 $35.000 $35.000 $35.000 $42.000
506 7011 ROCK FILTER DAMS (REMOVE) LF 1,600.000 $12.700 $12.000 $13.000 $12.000 $14.000
506 7029 EARTHWORK (EROSN & SEDMT CONT, IN VEH) CY 1,000.000 $73.000 $35.000 $20.000 $23.000 $45.000
506 7030 BACKHOE WORK (EROSION & SEDMT CONT) HR 150.000 $124.090 $180.000 $55.000 $120.000 $300.000
506 7039 TEMP SEDMT CONT FENCE (INSTALL) LF 3,145.000 $4.750 $5.000 $4.000 $4.300 $5.000
506 7041 TEMP SEDMT CONT FENCE (REMOVE) LF 3,145.000 $2.480 $1.000 $0.750 $0.750 $1.000
530 7002 INTERSECTIONS (ACP) SY 2,054.000 $68.000 $55.000 $75.000 $77.000 $100.000
530 7007 DRIVEWAYS (CONC) (HES) SY 150.000 $145.000 $150.000 $160.000 $260.000 $180.000
530 7010 DRIVEWAYS (ACP) SY 7,688.000 $100.000 $55.000 $75.000 $58.000 $70.000
530 7018 TURNOUTS (ACP) SY 257.000 $100.000 $55.000 $133.000 $77.000 $140.000
533 7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) LF 68,260.000 $0.340 $0.300 $0.350 $0.150 $0.150
533 7003 MILL RUMBLE STRIPS (CONC) (SHLDR) LF 25,623.000 $0.340 $0.500 $0.700 $0.150 $0.650
533 7004 MILL RUMBLE STRIPS (CONC) (CENTERLINE) LF 46,805.000 $0.340 $0.500 $0.750 $0.150 $0.650
540 7002 MTL W-BEAM GD FEN (STEEL POST) LF 2,138.000 $38.790 $35.000 $30.000 $27.000 $35.000
540 7018 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 350.000 $99.600 $80.000 $108.000 $97.000 $120.000
542 7001 REMOVE METAL BEAM GUARD FENCE LF 2,496.000 $4.380 $3.000 $3.000 $2.000 $3.000
544 7001 GUARDRAIL END TREATMENT (INSTALL) EA 32.000 $3,028.570 $3,200.000 $3,300.000 $2,900.000 $3,600.000
544 7003 GUARDRAIL END TREATMENT (REMOVE) EA 18.000 $358.500 $300.000 $225.000 $220.000 $250.000
560 7001 MAILBOX INSTALL-M (TWG-POST) TY 1 EA 12.000 $674.800 $500.000 $735.000 $690.000 $850.000
560 7002 MAILBOX INSTALL-S (TWG-POST) TY 2 EA 55.000 $334.760 $300.000 $360.000 $270.000 $340.000
560 7003 MAILBOX INSTALL-D (TWG-POST) TY 2 EA 6.000 $390.760 $325.000 $410.000 $290.000 $320.000
644 7004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 1.000 $910.000 $800.000 $890.000 $640.000 $1,100.000
644 7007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 3.000 $965.000 $850.000 $1,040.000 $740.000 $1,100.000
644 7028 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 1.000 $1,173.860 $1,100.000 $1,260.000 $950.000 $1,500.000
644 7031 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 4.000 $1,279.900 $950.000 $1,175.000 $900.000 $1,500.000
644 7057 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 74.000 $672.000 $500.000 $475.000 $520.000 $550.000
644 7058 IN SM RD SN SUP&AM TYTWT(1)WS(T) EA 1.000 $663.000 $600.000 $600.000 $520.000 $750.000
644 7073 REMOVE SM RD SN SUP&AM EA 84.000 $147.860 $100.000 $110.000 $110.000 $100.000
658 7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 207.000 $52.430 $30.000 $28.000 $35.000 $34.000
658 7059 INSTL OM ASSM (OM-2Z)(WFLX)GND(BI) EA 62.000 $92.000 $50.000 $80.000 $75.000 $68.000
662 7005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) LF 10,507.000 $1.100 $0.300 $0.350 $0.310 $0.380
662 7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 187,068.000 $1.080 $0.300 $0.350 $0.310 $0.380
662 7017 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 556.000 $7.520 $4.000 $4.500 $4.100 $5.000
662 7036 WK ZN PAV MRK NON-REMOV (Y)6"(BRK) LF 300.000 $1.290 $1.000 $1.150 $1.000 $1.250
662 7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 201,548.000 $4.210 $0.300 $0.350 $0.310 $0.380
662 7068 WK ZN PAV MRK REMOV (W)6"(SLD) LF 4,750.000 $2.280 $1.000 $2.250 $0.400 $1.900
662 7100 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 46,029.000 $2.940 $1.000 $2.250 $0.400 $1.900
662 7112 WK ZN PAV MRK SHT TERM (TAB)TY W EA 1,583.000 $2.500 $1.500 $1.300 $0.750 $1.700
662 7113 WK ZN PAV MRK SHT TERM (TAB)TY Y EA 5,040.000 $2.500 $1.500 $1.300 $0.750 $1.700
666 7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 1,840.000 $2.180 $1.500 $1.450 $1.400 $1.650
666 7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 278.000 $9.210 $6.000 $6.500 $6.500 $7.500
666 7123 REFL PAV MRK TY I (Y)24"(SLD)(100MIL) LF 1,430.000 $9.340 $6.000 $6.500 $6.500 $7.500
666 7172 RE PM TY II (W) 6" (BRK) LF 5,120.000 $1.000 $0.450 $0.450 $0.450 $0.500
666 7173 RE PM TY II (W) 6" (DOT) LF 571.000 $1.780 $1.000 $1.150 $1.100 $1.250
666 7175 RE PM TY II (W) 6" (SLD) LF 93,574.000 $1.250 $0.350 $0.350 $0.350 $0.380
666 7211 RE PM TY II (Y) 6" (BRK) LF 16,140.000 $0.990 $0.450 $0.450 $0.450 $0.500
666 7213 RE PM TY II (Y) 6" (SLD) LF 113,734.000 $1.250 $0.300 $0.450 $0.350 $0.380
668 7023 PREFAB PM TY B (W)(ARROW) EA 4.000 $600.000 $250.000 $275.000 $260.000 $315.000
668 7027 PREFAB PM TY B (W)(U-LT ARROW) EA 8.000 $1,200.000 $400.000 $450.000 $430.000 $500.000
668 7031 PREFAB PM TY B (W)(WORD) EA 8.000 $751.480 $300.000 $330.000 $320.000 $375.000
668 7051 PREFAB PM TY B (Y)(6")(SLD) LF 18.000 $5.500 $10.000 $11.000 $11.000 $12.500
672 7002 REFL PAV MRKR TY I-C EA 94.000 $6.500 $6.000 $6.500 $6.500 $7.500
672 7004 REFL PAV MRKR TY II-A-A EA 1,122.000 $6.800 $6.000 $5.500 $5.300 $6.250
730 7019 FULL - WIDTH MOWING CYC 4.000 $2,500.000 $5,500.000 $9,500.000 $4,500.000 $15,000.000
734 7002 LITTER REMOVAL CYC 6.000 $2,791.000 $6,000.000 $3,500.000 $3,000.000 $3,200.000
1 464 7003 RC PIPE (CL III)(18 IN) LF 2,752.000 $81.000 $65.000 $57.000 $72.000 $85.000
2 464 7005 RC PIPE (CL III)(24 IN) LF 239.000 $134.000 $100.000 $78.000 $180.000 $110.000
Totals: $21,010,148.29 $13,887,918.16 $16,584,648.30 $17,511,205.34 $20,210,735.15