HARRISON IH0020 (6462-19-001)

Items: 15

County: HARRISON
Length: N/A
Highway: IH0020
District: ATLANTA
Control Number: 6462-19-001
DBE Goal: 0.0%
Project: RMC - 646219001
Guaranty: N/A
Time: 612 CALENDAR DAYS
Engineer's Estimate: $510,800.00
Date: 02/02/2024 (2 years ago)
Contract Number: N/A
Type: CABLE BARRIER REPAIR
Mail/Deliver Bids To: N/A
JASON DUPREE
CHARLOTTE ASLIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$510,800.00
$478,435.00
Over/Under Est: -6.34% -$32,365.00
$527,950.00
Over/Under Est: 3.36% $17,150.00
Amt Left: 10.35% $49,515.00
Over/Under Est: 5.72% $29,218.85
Amt Left: 12.87% $61,583.85
Delta: -2.29% -$12,068.85
Over/Under Est: 16.16% $82,550.00
Amt Left: 24.02% $114,915.00
Delta: -9.88% -$53,331.15
Over/Under Est: 17.74% $90,600.00
Amt Left: 25.7% $122,965.00
Delta: -1.36% -$8,050.00
$965,450.00
Over/Under Est: 89.01% $454,650.00
Amt Left: 101.79% $487,015.00
Delta: -60.53% -$364,050.00
Subcontractor Percentage Amount
ELITE CASTLE RESOURCES LLC 90.00% $431,581.50
TIMBERTEX, INC. 2.82% $13,522.89
Total: 92.82% $445,104.39

Bid Items & Bid Tabulations

15 Total 0 of 15
HARRISON  |  IH0020  |  ATLANTA  |  6462-19-001  |  02/02/2024  |  $510,800.00  |  RMC - 646219001  |  CABLE BARRIER REPAIR  |  612 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROSS SA ENTERPRISE LLC
H. V. CAVER, INC.
SCOUT 5 CONSTRUCTION LLC
JCW CONSTRUCTION, LLC
RISE UP CONSTRUCTION LLC
E.V.G. ENTERPRISE
RIPRAP (MOW STRIP)(4 IN)
CY 20.000 $150.000 $500.000 $225.000 $0.010 $200.000 $600.000 $740.000
MOBILIZATION (CALLOUT)
EA 25.000 $200.000 $1.000 $150.000 $0.010 $6,000.000 $1,000.000 $1,000.000
PAVEMENT EDGES, STRUCTURES & FIXTURES
MI 100.000 $250.000 $200.000 $240.000 $300.000 $300.000 $800.000 $1,400.000
REPLACE POSTS (TL-3)
EA 1,500.000 $130.000 $240.000 $145.000 $200.000 $200.000 $200.000 $260.000
REPLACE POSTS (TL-4)
EA 750.000 $240.000 $1.000 $200.000 $200.000 $1.000 $200.000 $260.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 25.000 $240.000 $500.000 $300.000 $0.010 $500.000 $5.000 $10.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 10.000 $330.000 $15.000 $300.000 $0.010 $100.000 $5.000 $10.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 30.000 $150.000 $100.000 $100.000 $0.010 $500.000 $300.000 $20.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 10.000 $100.000 $11.000 $100.000 $0.010 $100.000 $300.000 $20.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 45.000 $900.000 $1,500.000 $900.000 $0.010 $1,500.000 $5.000 $1,200.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 20.000 $1,200.000 $15.000 $1,200.000 $0.010 $500.000 $5.000 $1,200.000
REPLACE CABLE (TL-3)
LF 1,000.000 $1.000 $3.000 $0.800 $0.010 $0.500 $1.000 $1.000
REPLACE CABLE (TL-4)
LF 500.000 $1.000 $1.000 $0.800 $0.010 $1.000 $1.000 $1.000
CHECK / RE-TENSION CABLE
EA 400.000 $5.000 $1.000 $20.000 $150.000 $1.000 $1.000 $200.000
TMA (STATIONARY)
DAY 200.000 $100.000 $1.000 $200.000 $0.010 $1.000 $100.000 $200.000
Totals: $510,800.000 $478,435.000 $527,950.000 $540,018.850 $593,350.000 $601,400.000 $965,450.000