HARRISON SH 43 (0569-04-020)

Items: 92

County: HARRISON
Length: N/A
Highway: SH 43
District: ATLANTA
Control Number: 0569-04-020
DBE Goal: N/A
Project: BR 2020(725)
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $2,433,484.35
Date: 08/06/2020 (5 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$2,433,484.35
$2,545,187.72
Over/Under Est: 4.59% $111,703.37
$2,887,835.39
Over/Under Est: 18.67% $454,351.04
Amt Left: 13.46% $342,647.67
Over/Under Est: 32.21% $783,904.65
Amt Left: 26.41% $672,201.28
Delta: -11.41% -$329,553.61
Over/Under Est: 32.73% $796,407.15
Amt Left: 26.9% $684,703.78
Delta: -0.39% -$12,502.50
Over/Under Est: 39.43% $959,440.93
Amt Left: 33.31% $847,737.56
Delta: -5.05% -$163,033.78
Over/Under Est: 64.1% $1,559,866.26
Amt Left: 56.9% $1,448,162.89
Delta: -17.70% -$600,425.33

Bid Items & Bid Tabulations

92 Total 0 of 92
HARRISON  |  SH 43  |  ATLANTA  |  0569-04-020  |  08/06/2020  |  $2,433,484.35  |  BR 2020(725)  |  REPLACE BRIDGE AND APPROACHES  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
PIERCE R & B LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
HIGHWAY 19 CONSTRUCTION LLC
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 7.700 $4,000.000 $1,475.000 $2,500.000 $6,500.000 $10,000.000 $2,500.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 536.000 $9.000 $16.000 $11.000 $40.000 $25.000 $25.000 $30.000
REMOVING CONCRETE(MOW STRIP)
LF 1,201.000 $7.000 $8.000 $4.000 $10.000 $10.000 $16.000 $10.000
REMOVING STAB BASE AND ASPH PAV (11")
SY 668.000 $6.000 $14.000 $15.000 $20.000 $25.000 $18.000 $15.000
EXCAVATION (ROADWAY)
CY 228.000 $8.000 $10.000 $7.500 $30.000 $100.000 $40.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 4,061.000 $40.000 $10.000 $13.500 $25.000 $17.000 $22.000 $30.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 16.000 $9.000 $100.000 $85.000 $80.000 $180.000 $40.000 $100.000
FURNISHING AND PLACING TOPSOIL (4")
SY 11,476.000 $2.000 $2.250 $2.500 $2.000 $5.000 $2.000 $3.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 11,476.000 $0.800 $0.800 $0.810 $1.000 $1.000 $0.820 $0.830
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 5,738.000 $0.700 $0.800 $0.840 $0.750 $1.000 $0.850 $0.850
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 5,738.000 $0.700 $0.800 $0.790 $0.750 $1.000 $0.800 $0.800
VEGETATIVE WATERING
MG 184.000 $12.000 $25.000 $50.000 $1.000 $10.000 $5.000 $12.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 11,476.000 $1.250 $0.850 $0.840 $1.500 $3.000 $0.860 $0.880
CEMENT
TON 14.000 $163.000 $210.000 $350.000 $200.000 $250.000 $500.000 $250.000
CEMENT TREAT (EXIST MATL) (10")
SY 1,012.000 $3.000 $12.500 $16.000 $25.000 $10.000 $11.000 $10.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 123.000 $7.000 $25.000 $23.000 $10.000 $50.000 $20.000 $20.000
ASPH (TIER I)
GAL 354.000 $4.000 $25.000 $24.000 $20.000 $50.000 $20.000 $20.000
AGGR(TY-D GR-4 SAC-B)
CY 8.000 $130.000 $1,000.000 $550.000 $2,000.000 $1,000.000 $2,000.000 $800.000
PLANE ASPH CONC PAV (2")
SY 7,038.000 $2.000 $3.650 $2.000 $6.000 $6.000 $7.500 $5.000
PAV JT UNDERSEAL (18")
LF 1,118.000 $45.000 $10.000 $9.000 $50.000 $55.000 $60.000 $22.000
CEM STABIL BKFL
CY 352.000 $190.000 $175.000 $210.000 $200.000 $250.000 $290.000 $275.000
TEMPORARY SPL SHORING
SF 2,608.000 $33.000 $29.000 $52.000 $30.000 $65.000 $75.000 $65.000
DRILL SHAFT (36 IN)
LF 438.000 $200.000 $350.000 $370.000 $305.000 $310.000 $500.000 $450.000
CL C CONC (ABUT)(HPC)(EXTEND)
CY 41.000 $1,691.000 $1,100.000 $1,300.000 $1,600.000 $2,500.000 $1,500.000 $2,800.000
CL C CONC (CAP)(HPC)(EXTEND)
CY 22.000 $1,599.000 $1,250.000 $2,300.000 $2,000.000 $2,500.000 $1,500.000 $3,500.000
CL C CONC (COLUMN)(HPC)
CY 21.600 $1,100.000 $1,400.000 $1,900.000 $2,000.000 $1,500.000 $1,500.000 $2,000.000
CL C CONC (CRASHWALL)(HPC)
CY 98.800 $850.000 $795.000 $1,050.000 $1,200.000 $1,000.000 $1,200.000 $1,600.000
REINF CONC SLAB (HPC)
SF 7,000.000 $24.000 $26.000 $23.000 $32.000 $30.000 $38.000 $46.000
APPROACH SLAB (HPC)
CY 163.400 $715.000 $565.000 $625.000 $500.000 $650.000 $520.000 $650.000
PRESTR CONC BOX BEAM (4XB20)
LF 553.280 $220.000 $340.000 $255.000 $325.000 $300.000 $415.000 $350.000
RIPRAP (CONC)(CL B)
CY 11.100 $490.000 $800.000 $900.000 $600.000 $1,000.000 $585.000 $600.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 236.000 $435.000 $425.000 $575.000 $475.000 $650.000 $500.000 $600.000
RIPRAP (MOW STRIP)(4 IN)
CY 32.000 $450.000 $425.000 $650.000 $550.000 $500.000 $520.000 $600.000
STR STEEL (SHEAR CONNECTOR)
LB 1,715.000 $7.000 $9.750 $25.000 $15.000 $25.000 $8.000 $35.000
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 1.000 $190,000.000 $405,000.000 $400,000.000 $400,000.000 $15,000.000 $550,000.000 $450,000.000
RAIL (TY SSTR)(HPC)
LF 328.000 $81.000 $105.000 $100.000 $85.000 $180.000 $90.000 $120.000
RAIL (CLF-RO)
LF 280.000 $20.000 $110.000 $150.000 $250.000 $180.000 $80.000 $100.000
ARMOR JOINT
LF 98.000 $100.000 $85.000 $65.000 $80.000 $150.000 $50.000 $65.000
ARMOR JOINT (SEALED)
LF 104.000 $160.000 $95.000 $85.000 $85.000 $55.000 $70.000 $100.000
WATERPROOFING (TY 10)
SY 75.200 $90.000 $25.000 $350.000 $70.000 $100.000 $330.000 $200.000
REMOV STR (BRIDGE SLAB)
EA 1.000 $68,000.000 $45,000.000 $48,000.000 $150,000.000 $100,000.000 $65,000.000 $100,000.000
REMOV STR (APPROACH SLAB)
EA 2.000 $9,535.000 $10,000.000 $12,000.000 $20,000.000 $10,000.000 $4,500.000 $10,000.000
REMOVE STR (RAIL)
LF 360.000 $50.000 $25.000 $60.000 $10.000 $50.000 $75.000 $150.000
ADJUST STL SHOES
EA 8.000 $5,000.000 $4,000.000 $4,000.000 $7,000.000 $5,000.000 $5,000.000 $10,000.000
MOBILIZATION
LS 1.000 $213,610.000 $200,000.000 $288,000.000 $280,000.000 $300,000.000 $200,000.000 $375,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $8,000.000 $2,200.000 $2,000.000 $8,500.000 $10,000.000 $3,000.000 $8,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 40.000 $39.000 $35.000 $39.000 $5.000 $100.000 $40.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 40.000 $15.000 $12.000 $16.000 $1.000 $10.000 $15.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $29.000 $25.000 $30.000 $1.000 $50.000 $30.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $15.000 $10.000 $14.000 $1.000 $10.000 $14.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,225.000 $2.750 $3.000 $3.000 $2.000 $3.000 $2.850 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,225.000 $1.000 $1.000 $1.500 $1.000 $1.000 $1.350 $1.350
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 6.000 $5,000.000 $3,500.000 $4,100.000 $4,000.000 $10,000.000 $6,500.000 $8,000.000
PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL)
LF 810.000 $65.000 $29.000 $30.000 $35.000 $100.000 $90.000 $125.000
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
LF 810.000 $9.000 $6.000 $7.000 $10.000 $25.000 $6.000 $60.000
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL)
LF 810.000 $11.000 $10.000 $24.000 $6.000 $25.000 $10.000 $15.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 1,523.000 $0.250 $2.750 $2.750 $3.500 $5.000 $3.000 $4.000
MTL W-BEAM GD FEN (TIM POST)
LF 400.000 $22.000 $21.000 $17.500 $20.000 $16.000 $22.000 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,850.000 $1,425.000 $1,350.000 $1,600.000 $1,225.000 $1,485.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 1,000.000 $3.000 $2.000 $2.250 $1.000 $2.000 $2.500 $2.750
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,710.000 $2,500.000 $2,500.000 $2,500.000 $2,500.000 $2,600.000 $2,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $640.000 $200.000 $234.000 $500.000 $200.000 $220.000 $230.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,334.000 $2,000.000 $1,650.000 $2,000.000 $2,000.000 $2,200.000 $2,300.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,342.000 $800.000 $900.000 $2,000.000 $800.000 $900.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $9,300.000 $9,650.000 $10,000.000 $9,000.000 $12,000.000 $11,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 3.000 $550.000 $1,000.000 $670.000 $650.000 $1,000.000 $1,050.000 $700.000
REMOVE SM RD SN SUP&AM
EA 4.000 $90.000 $200.000 $125.000 $50.000 $100.000 $140.000 $120.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $25.000 $45.000 $55.000 $30.000 $25.000 $18.000 $20.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $39.000 $45.000 $31.000 $50.000 $45.000 $33.000 $40.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,869.000 $0.500 $2.200 $2.200 $2.500 $2.000 $2.200 $2.500
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 36.000 $9.000 $11.000 $12.800 $10.000 $10.000 $11.000 $11.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 223.000 $0.500 $5.500 $5.750 $5.000 $5.000 $5.500 $6.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 3,024.000 $0.200 $0.550 $0.600 $0.750 $0.500 $0.550 $0.600
REFL PAV MRK TY II (Y) 4" (SLD)
LF 4,192.000 $0.200 $0.550 $0.600 $0.750 $0.500 $0.550 $0.600
PAVEMENT SEALER 4"
LF 892.000 $0.200 $1.100 $1.200 $1.000 $1.000 $1.100 $1.150
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 253.000 $16.000 $13.500 $13.800 $15.000 $13.000 $13.750 $15.000
REFL PAV MRKR TY II-A-A
EA 86.000 $3.000 $5.500 $6.250 $5.000 $5.000 $5.500 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 6,014.000 $0.500 $0.530 $0.550 $0.500 $0.500 $0.550 $0.550
ELIM EXT PAV MRK & MRKS (24")
LF 222.000 $5.000 $3.300 $3.600 $4.000 $5.000 $3.300 $3.500
PAV SURF PREP FOR MRK (4")
LF 892.000 $0.200 $0.550 $0.650 $0.750 $0.500 $0.550 $0.600
CARBON FIBER REINF POLYMER STRENGTHNING
SF 215.000 $50.000 $85.000 $188.000 $100.000 $150.000 $150.000 $175.000
SP MIXES SP-C SAC-A PG70-22
TON 480.000 $130.000 $165.000 $170.000 $190.000 $180.000 $140.000 $150.000
SP MIXES SP-D SAC-A PG76-22
TON 868.000 $130.000 $165.000 $151.000 $190.000 $180.000 $130.000 $150.000
TACK COAT
GAL 700.000 $4.000 $6.000 $7.000 $6.000 $10.000 $4.000 $7.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $8,500.000 $12,500.000 $8,000.000 $20,000.000 $20,000.000 $25,000.000
PREFB PV MK W/WNTY TY B(W)4"(SLD)CNTST
LF 446.000 $6.000 $8.800 $8.800 $8.000 $8.000 $8.800 $9.000
PREFB PV MK W/WNTY TY B(Y)4"(SLD)CNTST
LF 446.000 $6.000 $8.800 $8.800 $8.000 $8.000 $8.800 $9.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 347.000 $2.750 $7.000 $7.250 $8.000 $6.500 $7.150 $7.000
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 3,024.000 $0.500 $1.100 $1.100 $1.000 $1.000 $1.100 $1.150
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 4,192.000 $0.500 $1.100 $1.100 $1.000 $1.000 $1.100 $1.150
TMA (STATIONARY)
DAY 25.000 $210.000 $145.000 $200.000 $200.000 $1,000.000 $125.000 $300.000
TMA (MOBILE OPERATION)
HR 30.000 $48.000 $85.000 $50.000 $50.000 $50.000 $30.000 $100.000
Totals: $2,433,484.350 $2,545,187.720 $2,887,835.390 $3,217,389.000 $3,229,891.500 $3,392,925.280 $3,993,350.610