Show Job Controls
Bid Cobra

HARRIS IH 10 (0508-01-394)

Items: 32

County: HARRIS
Length: N/A
Highway: IH 10
District: HOUSTON
Control Number: 0508-01-394
DBE Goal: 0.0%
Project: C 508-1-394
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $2,207,938.28
Date: 02/01/2024 (2 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$2,207,938.28
Over/Under Est: -7.44% -$164,256.01
Over/Under Est: 13.63% $301,024.22
Amt Left: 22.77% $465,280.23
Subcontractor Percentage Amount
BLUE SKY RIGHT OF WAY, LLC 9.11% $239,911.51
Total: 9.11% $239,911.51

Bid Items & Bid Tabulations

32 Total 0 of 32
HARRIS  |  IH 10  |  HOUSTON  |  0508-01-394  |  02/01/2024  |  $2,207,938.28  |  C 508-1-394  |  LANDSCAPE DEVELOPMENT  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
APEX LANDSCAPE & IRRIGATION, LLC
PREP ROW (TREE) (2" TO 12" DIA)
EA 114.000 $250.000 $735.710 $120.000
FURNISHING AND PLACING TOPSOIL
CY 12.000 $50.000 $43.011 $50.000
EROSION CONTROL COMPOST
CY 2,169.000 $21.000 $25.283 $28.000
GENERAL USE COMPOST
CY 1,055.000 $25.000 $27.519 $27.000
BLOCK SODDING
SY 45.000 $8.000 $6.631 $12.000
FERTILIZER
AC 0.010 $2,778.000 $1,935.484 $2,800.000
VEGETATIVE WATERING
MG 1.000 $45.000 $35.887 $1.000
PLANT MATERIAL (3-GAL)
EA 2,261.000 $20.000 $39.235 $26.000
PLANT MATERIAL (15 GAL) (TREE)
EA 238.000 $128.000 $135.538 $140.000
PLANT MATERIAL (1 GAL) (SHRUB)
EA 492.000 $15.000 $9.835 $10.000
PLANT BED PREP (TYPE III)
SY 19,780.000 $0.500 $0.310 $3.000
PLANT MAINTENANCE
MO 19.000 $12,000.000 $3,820.034 $30,000.000
PLANT MAINTENANCE
CYC 6.000 $30,000.000 $78,780.621 $75,000.000
MOBILIZATION
LS 1.000 $197,450.000 $129,032.258 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $4,500.000 $161.290 $15,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,048.000 $4.000 $4.155 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,048.000 $1.000 $0.277 $1.000
FULL - WIDTH MOWING
CYC 6.000 $7,260.000 $7,795.699 $5,000.000
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 19,780.000 $0.150 $0.147 $0.350
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 19,780.000 $0.200 $0.130 $0.300
LANDSCAPE SOIL AMENDMENT (TYPE III)
SY 2,499.000 $1.000 $0.904 $1.500
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 12,495.000 $0.300 $0.284 $0.700
LANDSCAPE SOIL AMENDMENT (TYPE V)
SY 2,991.000 $2.000 $2.157 $1.500
LANDSCAPE TREATMENT(TY 3)
EA 1.000 $127,000.000 $222,580.645 $85,000.000
LANDSCAPE TREATMENT(TY 4)
EA 2.000 $40,000.000 $54,032.258 $75,000.000
LANDSCAPE TREATMENT (TY 5)
EA 1.000 $60,000.000 $91,935.484 $90,000.000
LANDSCAPE TREATMENT (TY 6)
EA 1.000 $75,000.000 $135,483.871 $125,000.000
LANDSCAPE TREATMENT (TY 7)
EA 1.000 $835,000.000 $238,709.677 $110,000.000
LANDSCAPE TREATMENT (TY 8)
EA 1.000 $25,000.000 $45,161.290 $50,000.000
LANDSCAPE TREATMENT (TY 10)
EA 1.000 $50,000.000 $87,096.774 $150,000.000
TMA (STATIONARY)
DAY 45.000 $225.000 $681.004 $300.000
TMA (MOBILE OPERATION)
DAY 60.000 $700.000 $645.161 $350.000
Totals: $2,207,938.280 $2,043,682.380 $2,508,962.500