Job Info for 0508-01-394

County: HARRIS Highway: IH 10 Date: 02/01/2024 (9 months ago) Engineer's Estimate: $2,207,938 Control Number: 0508-01-394
Project: C 508-1-394 District: HOUSTON Time: 120 WORKING DAYS Type: LANDSCAPE DEVELOPMENT
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,207,938.28
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $2,043,682.27 1
-7.44% | -$164,256.01
APEX LANDSCAPE & IRRIGATION, LLC   $2,508,962.50 2
13.63% | $301,024.22
22.77% | $465,280.23
Subcontractor Percentage Amount
BLUE SKY RIGHT OF WAY, LLC 11.74% $239,928.31
Total: 11.74% $239,928.31

Bid Items

Items: 32, 0 filtered
HARRIS IH 10  |  HOUSTON  |  0508-01-394  |  02/01/2024  |  $2,207,938  |  C 508-1-394  |  LANDSCAPE DEVELOPMENT  |  120 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate YELLOWSTONE LANDSCAPE - CENTRAL, INC. APEX LANDSCAPE & IRRIGATION, LLC
100 6013 PREP ROW (TREE) (2" TO 12" DIA) EA 114.000 $250.000 $735.710 $120.000
160 6005 FURNISHING AND PLACING TOPSOIL CY 12.000 $50.000 $43.011 $50.000
161 6009 EROSION CONTROL COMPOST CY 2,169.000 $21.000 $25.283 $28.000
161 6012 GENERAL USE COMPOST CY 1,055.000 $25.000 $27.519 $27.000
162 6002 BLOCK SODDING SY 45.000 $8.000 $6.631 $12.000
166 6001 FERTILIZER AC 0.010 $2,778.000 $1,935.484 $2,800.000
168 6001 VEGETATIVE WATERING MG 1.000 $45.000 $35.887 $1.000
192 6003 PLANT MATERIAL (3-GAL) EA 2,261.000 $20.000 $39.235 $26.000
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA 238.000 $128.000 $135.538 $140.000
192 6028 PLANT MATERIAL (1 GAL) (SHRUB) EA 492.000 $15.000 $9.835 $10.000
192 6065 PLANT BED PREP (TYPE III) SY 19,780.000 $0.500 $0.310 $3.000
193 6001 PLANT MAINTENANCE MO 19.000 $12,000.000 $3,820.034 $30,000.000
193 6002 PLANT MAINTENANCE CYC 6.000 $30,000.000 $78,780.621 $75,000.000
500 6001 MOBILIZATION LS 1.000 $197,450.000 $129,032.258 $250,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $4,500.000 $161.290 $15,000.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 1,048.000 $4.000 $4.155 $3.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,048.000 $1.000 $0.277 $1.000
730 6107 FULL - WIDTH MOWING CYC 6.000 $7,260.000 $7,795.699 $5,000.000
1006 6001 LANDSCAPE SOIL AMENDMENT (TYPE I) SY 19,780.000 $0.150 $0.147 $0.350
1006 6002 LANDSCAPE SOIL AMENDMENT (TYPE II) SY 19,780.000 $0.200 $0.130 $0.300
1006 6003 LANDSCAPE SOIL AMENDMENT (TYPE III) SY 2,499.000 $1.000 $0.904 $1.500
1006 6004 LANDSCAPE SOIL AMENDMENT (TYPE IV) SY 12,495.000 $0.300 $0.284 $0.700
1006 6005 LANDSCAPE SOIL AMENDMENT (TYPE V) SY 2,991.000 $2.000 $2.157 $1.500
1022 6003 LANDSCAPE TREATMENT(TY 3) EA 1.000 $127,000.000 $222,580.645 $85,000.000
1022 6004 LANDSCAPE TREATMENT(TY 4) EA 2.000 $40,000.000 $54,032.258 $75,000.000
1022 6005 LANDSCAPE TREATMENT (TY 5) EA 1.000 $60,000.000 $91,935.484 $90,000.000
1022 6006 LANDSCAPE TREATMENT (TY 6) EA 1.000 $75,000.000 $135,483.871 $125,000.000
1022 6007 LANDSCAPE TREATMENT (TY 7) EA 1.000 $835,000.000 $238,709.677 $110,000.000
1022 6008 LANDSCAPE TREATMENT (TY 8) EA 1.000 $25,000.000 $45,161.290 $50,000.000
1022 6010 LANDSCAPE TREATMENT (TY 10) EA 1.000 $50,000.000 $87,096.774 $150,000.000
6185 6002 TMA (STATIONARY) DAY 45.000 $225.000 $681.004 $300.000
6185 6005 TMA (MOBILE OPERATION) DAY 60.000 $700.000 $645.161 $350.000
Totals: $2,207,938.28 $2,043,682.38 $2,508,962.50