GRAYSON CR (0901-19-181)

Items: 39

County: GRAYSON
Length: N/A
Highway: CR
District: PARIS
Control Number: 0901-19-181
DBE Goal: N/A
Project: BR 2016(435)
Guaranty: N/A
Time: 173 WORKING DAYS
Engineer's Estimate: $1,199,764.56
Date: 06/06/2018 (7 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,199,764.56
$1,074,079.50
Over/Under Est: -10.48% -$125,685.06
Over/Under Est: -9.4% -$112,812.46
Amt Left: 1.2% $12,872.60
Over/Under Est: -2.44% -$29,316.56
Amt Left: 8.97% $96,368.50
Delta: -7.68% -$83,495.90
$1,197,999.79
Over/Under Est: -0.15% -$1,764.77
Amt Left: 11.54% $123,920.29
Delta: -2.35% -$27,551.79
Over/Under Est: 5.81% $69,714.20
Amt Left: 18.19% $195,399.26
Delta: -5.97% -$71,478.97
$1,534,497.35
Over/Under Est: 27.9% $334,732.79
Amt Left: 42.87% $460,417.85
Delta: -20.88% -$265,018.59
Over/Under Est: 57.78% $693,235.44
Amt Left: 76.24% $818,920.50
Delta: -23.36% -$358,502.65

Bid Items & Bid Tabulations

39 Total 0 of 39
GRAYSON  |  CR  |  PARIS  |  0901-19-181  |  06/06/2018  |  $1,199,764.56  |  BR 2016(435)  |  BRIDGE REPL  |  173 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
HIGHWAY 19 CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
PIERCE R & B LLC
COPPELL CONSTRUCTION CO., INC.
FNH CONSTRUCTION, LLC
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 15.060 $2,000.000 $2,000.000 $1,000.000 $4,000.000 $2,100.000 $1,740.000 $12,000.000 $10,000.000
EXCAVATION (ROADWAY)
CY 609.000 $13.710 $10.000 $15.000 $20.000 $12.000 $33.000 $30.000 $40.000
EXCAVATION (CHANNEL)
CY 832.000 $32.750 $10.000 $10.000 $15.000 $16.500 $40.000 $25.000 $40.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 341.000 $32.100 $12.000 $30.000 $30.000 $32.000 $55.000 $35.000 $40.000
BROADCAST SEED (TEMP) (WARM)
SY 1,758.000 $0.120 $1.100 $1.000 $0.700 $2.900 $0.680 $1.000 $0.010
BROADCAST SEED (TEMP) (COOL)
SY 1,758.000 $0.100 $1.100 $1.000 $0.700 $1.090 $0.680 $1.000 $0.010
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 3,514.000 $0.500 $1.100 $1.000 $2.000 $1.070 $1.480 $1.000 $10.000
VEGETATIVE WATERING
MG 60.000 $14.040 $5.000 $10.000 $1.000 $25.000 $56.000 $80.000 $330.000
FL BS (RDWY DEL) (TY D GR 4)
TON 597.000 $37.500 $50.000 $72.000 $55.000 $51.400 $51.000 $50.000 $47.000
D-GR HMA(SQ) TY-B PG64-22
TON 176.000 $100.000 $165.000 $139.000 $140.000 $146.000 $139.000 $140.000 $140.000
CEM STABIL BKFL
CY 166.000 $200.210 $225.000 $200.000 $200.000 $194.000 $331.000 $200.000 $250.000
DRILL SHAFT (24 IN)
LF 435.000 $107.570 $125.000 $107.000 $110.000 $153.000 $133.000 $180.000 $150.000
DRILL SHAFT (30 IN)
LF 114.000 $119.670 $200.000 $197.000 $160.000 $190.000 $212.000 $200.000 $200.000
DRILL SHAFT (36 IN)
LF 186.000 $175.000 $280.000 $183.000 $200.000 $279.000 $287.000 $450.000 $250.000
CL C CONC (ABUT)
CY 106.800 $1,000.000 $800.000 $718.000 $950.000 $1,025.000 $1,147.000 $900.000 $2,000.000
REINF CONC SLAB
SF 1,950.000 $16.000 $23.000 $21.000 $20.000 $20.000 $31.000 $20.000 $50.000
REINF CONC SLAB (BOX BEAM)
SF 1,701.000 $19.520 $16.000 $13.000 $18.000 $17.000 $25.300 $20.000 $50.000
REINF CONC SLAB (SLAB BEAM)
SF 2,600.000 $17.860 $16.000 $13.000 $18.000 $18.000 $29.000 $20.000 $50.000
SHEAR KEY
CY 8.600 $554.470 $450.000 $350.000 $600.000 $455.000 $530.000 $450.000 $1,000.000
PRESTR CONC BOX BEAM (4B20)
LF 258.000 $180.450 $200.000 $230.000 $220.000 $200.000 $217.000 $123.000 $300.000
PRESTR CONC BOX BEAM (5B20)
LF 129.000 $180.450 $200.000 $230.000 $220.000 $238.000 $227.000 $125.000 $300.000
PRESTR CONC SLAB BEAM (5SB15)
LF 495.000 $168.600 $200.000 $230.000 $220.000 $176.000 $202.000 $125.000 $300.000
PRESTR CONC GIRDER (TX28)
LF 297.690 $200.000 $200.000 $230.000 $220.000 $194.000 $239.000 $165.000 $300.000
RIPRAP (CONC)(5 IN)
CY 26.800 $455.000 $425.000 $500.000 $500.000 $470.000 $552.000 $450.000 $800.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 881.000 $180.000 $120.000 $140.000 $115.000 $177.000 $125.000 $125.000 $165.000
RAIL (TY T631LS)
LF 600.000 $100.000 $60.000 $55.000 $70.000 $63.000 $55.000 $65.000 $60.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 4.000 $27,321.700 $8,500.000 $10,000.000 $12,000.000 $8,500.000 $16,500.000 $50,000.000 $10,000.000
MOBILIZATION
LS 1.000 $86,204.780 $95,000.000 $100,000.000 $105,000.000 $119,000.000 $64,000.000 $100,000.000 $160,961.090
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $3,000.000 $1,250.000 $1,000.000 $2,200.000 $2,251.000 $1,300.000 $8,500.000 $4,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 160.000 $34.650 $40.000 $40.000 $10.000 $42.000 $40.000 $35.000 $26.000
ROCK FILTER DAMS (REMOVE)
LF 160.000 $9.610 $5.000 $10.000 $10.000 $12.000 $3.000 $10.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,893.000 $2.860 $3.000 $3.000 $2.000 $3.250 $3.950 $4.500 $1.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,893.000 $1.380 $0.500 $1.000 $1.000 $1.080 $1.000 $2.000 $0.250
MTL W-BEAM GD FEN (STEEL POST)
LF 400.000 $25.000 $26.000 $23.500 $30.000 $21.150 $20.000 $35.000 $22.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,341.480 $1,200.000 $1,075.000 $1,200.000 $848.000 $800.000 $1,300.000 $900.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,271.390 $2,500.000 $2,300.000 $2,500.000 $2,212.000 $2,100.000 $3,000.000 $2,250.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 3.000 $404.310 $400.000 $3,500.000 $400.000 $250.000 $150.000 $500.000 $500.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 8.000 $52.130 $50.000 $45.000 $60.000 $65.000 $55.000 $100.000 $160.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $31.820 $20.000 $18.000 $40.000 $32.960 $30.000 $50.000 $40.000
Totals: $1,199,764.562 $1,074,079.500 $1,086,952.100 $1,170,448.000 $1,197,999.790 $1,269,478.760 $1,534,497.350 $1,893,000.000