Job Info for 0901-19-181

County: GRAYSON Highway: CR Date: 06/06/2018 (6 years ago) Engineer's Estimate: $1,199,765 Control Number: 0901-19-181
Project: BR 2016(435) District: PARIS Time: 173 WORKING DAYS Type: BRIDGE REPLACEMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,199,764.56
EAST TEXAS BRIDGE, INC.   $1,074,079.50 1
-10.48% | -$125,685.06
HIGHWAY 19 CONSTRUCTION LLC   $1,086,952.10 2
-9.4% | -$112,812.46
1.2% | $12,872.60
HODGES AND SON CONSTRUCTION COMPANY, INC.   $1,170,448.00 3
-2.44% | -$29,316.56
8.97% | $96,368.50
7.68% | $83,495.90
PIERCE R & B LLC   $1,197,999.79 4
-0.15% | -$1,764.77
11.54% | $123,920.29
2.35% | $27,551.79
COPPELL CONSTRUCTION CO., INC.   $1,269,478.76 5
5.81% | $69,714.20
18.19% | $195,399.26
5.97% | $71,478.97
FNH CONSTRUCTION, LLC   $1,534,497.35 6
27.9% | $334,732.79
42.87% | $460,417.85
20.88% | $265,018.59
ED BELL CONSTRUCTION COMPANY   $1,893,000.00 7
57.78% | $693,235.44
76.24% | $818,920.50
23.36% | $358,502.65

Bid Items

Items: 39, 0 filtered
GRAYSON CR  |  PARIS  |  0901-19-181  |  06/06/2018  |  $1,199,765  |  BR 2016(435)  |  BRIDGE REPL  |  173 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate EAST TEXAS BRIDGE, INC. HIGHWAY 19 CONSTRUCTION LLC HODGES AND SON CONSTRUCTION COMPANY, INC. PIERCE R & B LLC COPPELL CONSTRUCTION CO., INC. FNH CONSTRUCTION, LLC ED BELL CONSTRUCTION COMPANY
100 6002 PREPARING ROW STA 15.060 $2,000.000 $2,000.000 $1,000.000 $4,000.000 $2,100.000 $1,740.000 $12,000.000 $10,000.000
110 6001 EXCAVATION (ROADWAY) CY 609.000 $13.710 $10.000 $15.000 $20.000 $12.000 $33.000 $30.000 $40.000
110 6002 EXCAVATION (CHANNEL) CY 832.000 $32.750 $10.000 $10.000 $15.000 $16.500 $40.000 $25.000 $40.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 341.000 $32.100 $12.000 $30.000 $30.000 $32.000 $55.000 $35.000 $40.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 1,758.000 $0.120 $1.100 $1.000 $0.700 $2.900 $0.680 $1.000 $0.010
164 6011 BROADCAST SEED (TEMP) (COOL) SY 1,758.000 $0.100 $1.100 $1.000 $0.700 $1.090 $0.680 $1.000 $0.010
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 3,514.000 $0.500 $1.100 $1.000 $2.000 $1.070 $1.480 $1.000 $10.000
168 6001 VEGETATIVE WATERING MG 60.000 $14.040 $5.000 $10.000 $1.000 $25.000 $56.000 $80.000 $330.000
247 6136 FL BS (RDWY DEL) (TY D GR 4) TON 597.000 $37.500 $50.000 $72.000 $55.000 $51.400 $51.000 $50.000 $47.000
340 6011 D-GR HMA(SQ) TY-B PG64-22 TON 176.000 $100.000 $165.000 $139.000 $140.000 $146.000 $139.000 $140.000 $140.000
400 6005 CEM STABIL BKFL CY 166.000 $200.210 $225.000 $200.000 $200.000 $194.000 $331.000 $200.000 $250.000
416 6002 DRILL SHAFT (24 IN) LF 435.000 $107.570 $125.000 $107.000 $110.000 $153.000 $133.000 $180.000 $150.000
416 6003 DRILL SHAFT (30 IN) LF 114.000 $119.670 $200.000 $197.000 $160.000 $190.000 $212.000 $200.000 $200.000
416 6004 DRILL SHAFT (36 IN) LF 186.000 $175.000 $280.000 $183.000 $200.000 $279.000 $287.000 $450.000 $250.000
420 6013 CL C CONC (ABUT) CY 106.800 $1,000.000 $800.000 $718.000 $950.000 $1,025.000 $1,147.000 $900.000 $2,000.000
422 6001 REINF CONC SLAB SF 1,950.000 $16.000 $23.000 $21.000 $20.000 $20.000 $31.000 $20.000 $50.000
422 6005 REINF CONC SLAB (BOX BEAM) SF 1,701.000 $19.520 $16.000 $13.000 $18.000 $17.000 $25.300 $20.000 $50.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 2,600.000 $17.860 $16.000 $13.000 $18.000 $18.000 $29.000 $20.000 $50.000
422 6023 SHEAR KEY CY 8.600 $554.470 $450.000 $350.000 $600.000 $455.000 $530.000 $450.000 $1,000.000
425 6001 PRESTR CONC BOX BEAM (4B20) LF 258.000 $180.450 $200.000 $230.000 $220.000 $200.000 $217.000 $123.000 $300.000
425 6002 PRESTR CONC BOX BEAM (5B20) LF 129.000 $180.450 $200.000 $230.000 $220.000 $238.000 $227.000 $125.000 $300.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 495.000 $168.600 $200.000 $230.000 $220.000 $176.000 $202.000 $125.000 $300.000
425 6035 PRESTR CONC GIRDER (TX28) LF 297.690 $200.000 $200.000 $230.000 $220.000 $194.000 $239.000 $165.000 $300.000
432 6002 RIPRAP (CONC)(5 IN) CY 26.800 $455.000 $425.000 $500.000 $500.000 $470.000 $552.000 $450.000 $800.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 881.000 $180.000 $120.000 $140.000 $115.000 $177.000 $125.000 $125.000 $165.000
450 6019 RAIL (TY T631LS) LF 600.000 $100.000 $60.000 $55.000 $70.000 $63.000 $55.000 $65.000 $60.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 4.000 $27,321.700 $8,500.000 $10,000.000 $12,000.000 $8,500.000 $16,500.000 $50,000.000 $10,000.000
500 6001 MOBILIZATION LS 1.000 $86,204.780 $95,000.000 $100,000.000 $105,000.000 $119,000.000 $64,000.000 $100,000.000 $160,961.090
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $3,000.000 $1,250.000 $1,000.000 $2,200.000 $2,251.000 $1,300.000 $8,500.000 $4,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 160.000 $34.650 $40.000 $40.000 $10.000 $42.000 $40.000 $35.000 $26.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 160.000 $9.610 $5.000 $10.000 $10.000 $12.000 $3.000 $10.000 $11.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,893.000 $2.860 $3.000 $3.000 $2.000 $3.250 $3.950 $4.500 $1.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,893.000 $1.380 $0.500 $1.000 $1.000 $1.080 $1.000 $2.000 $0.250
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 400.000 $25.000 $26.000 $23.500 $30.000 $21.150 $20.000 $35.000 $22.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 8.000 $1,341.480 $1,200.000 $1,075.000 $1,200.000 $848.000 $800.000 $1,300.000 $900.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $2,271.390 $2,500.000 $2,300.000 $2,500.000 $2,212.000 $2,100.000 $3,000.000 $2,250.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 3.000 $404.310 $400.000 $3,500.000 $400.000 $250.000 $150.000 $500.000 $500.000
658 6046 INSTL OM ASSM (OM-2X)(WC)GND EA 8.000 $52.130 $50.000 $45.000 $60.000 $65.000 $55.000 $100.000 $160.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 24.000 $31.820 $20.000 $18.000 $40.000 $32.960 $30.000 $50.000 $40.000
Totals: $1,199,764.56 $1,074,079.50 $1,086,952.10 $1,170,448.00 $1,197,999.79 $1,269,478.76 $1,534,497.35 $1,893,000.00