PREPARING ROW
|
STA
|
567.000
|
$800.000
|
$375.000
|
$275.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
10.000
|
$23.000
|
$20.000
|
$100.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
600.000
|
$6.800
|
$15.000
|
$10.000
|
|
|
REMOVING CONC (SAWCUT)
|
LF
|
25.000
|
$120.000
|
$100.000
|
$100.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
224.000
|
$23.000
|
$35.000
|
$25.000
|
|
|
EXCAVATION (SPECIAL)
|
CY
|
30.000
|
$19.390
|
$35.000
|
$50.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
530.000
|
$250.000
|
$200.000
|
$250.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
618.000
|
$1.000
|
$35.000
|
$30.000
|
|
|
BACKFILL (TY A)
|
STA
|
35.000
|
$220.000
|
$550.000
|
$1,000.000
|
|
|
BACKFILL (TY B)
|
STA
|
530.000
|
$200.000
|
$210.000
|
$250.000
|
|
|
ROAD GRADER WORK (ORD COMP)
|
STA
|
530.000
|
$250.000
|
$265.000
|
$250.000
|
|
|
BULLDOZER WORK
|
HR
|
16.000
|
$112.000
|
$75.000
|
$100.000
|
|
|
SPEC EXCAV WORK (HYD EXCAVATOR)
|
HR
|
16.000
|
$137.000
|
$75.000
|
$100.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
125,866.000
|
$0.750
|
$0.090
|
$0.100
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
125,866.000
|
$0.900
|
$0.090
|
$0.100
|
|
|
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
251,730.000
|
$0.250
|
$0.260
|
$0.250
|
|
|
VEGETATIVE WATERING
|
MG
|
1,512.000
|
$35.000
|
$25.000
|
$10.000
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY E)
|
SY
|
850.000
|
$1.660
|
$2.000
|
$3.500
|
|
|
FL BS (CMP IN PL)(TY D GR 4)(8")
|
SY
|
155,126.000
|
$20.250
|
$23.250
|
$20.000
|
|
|
REWRKING BS MATL (TY C)(10")(ORD COMP)
|
SY
|
143,626.000
|
$2.750
|
$2.050
|
$2.530
|
|
|
CEMENT
|
TON
|
941.000
|
$250.000
|
$245.000
|
$210.000
|
|
|
CEMENT TREAT (NEW BASE) (6")
|
SY
|
155,126.000
|
$2.500
|
$2.850
|
$1.820
|
|
|
ASPH (RC-250)
|
GAL
|
43,434.000
|
$5.800
|
$5.980
|
$5.400
|
|
|
AGGR (TY-B GR-5 OR TY-L GR-5)
|
CY
|
1,110.000
|
$135.000
|
$146.000
|
$175.000
|
|
|
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
|
CY
|
1,293.000
|
$175.000
|
$176.000
|
$211.000
|
|
|
ASPH (AC-20-5TR OR AC-20XP)
|
GAL
|
127,202.000
|
$5.100
|
$5.370
|
$4.460
|
|
|
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
|
CY
|
1,478.000
|
$150.000
|
$176.000
|
$144.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
|
SY
|
250.000
|
$93.000
|
$245.000
|
$350.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 3")
|
SY
|
9,315.000
|
$2.500
|
$4.350
|
$2.500
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
338.000
|
$120.000
|
$100.000
|
$350.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
276.000
|
$350.000
|
$250.000
|
$250.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
787.000
|
$10.000
|
$15.000
|
$10.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
886.000
|
$40.000
|
$65.000
|
$35.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
62.000
|
$198.000
|
$200.000
|
$350.000
|
|
|
CONC STR REPR(REMOV AND REPL WINGWALL)
|
CY
|
3.000
|
$8,000.000
|
$2,500.000
|
$5,000.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
99.000
|
$200.000
|
$195.000
|
$180.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
103.000
|
$147.000
|
$215.000
|
$180.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
122.000
|
$511.180
|
$525.000
|
$500.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)
|
LF
|
70.000
|
$392.000
|
$500.000
|
$350.000
|
|
|
CONC BOX CULV (6 FT X 5 FT)
|
LF
|
61.000
|
$700.000
|
$1,000.000
|
$750.000
|
|
|
RC PIPE (CL III)(12 IN)
|
LF
|
836.000
|
$50.000
|
$48.000
|
$46.000
|
|
|
RC PIPE (CL III)(15 IN)
|
LF
|
465.000
|
$60.000
|
$50.000
|
$46.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
3,063.000
|
$70.000
|
$54.000
|
$53.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
846.000
|
$100.000
|
$90.000
|
$76.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
290.000
|
$150.000
|
$150.000
|
$110.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
368.000
|
$170.000
|
$165.000
|
$150.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
55.000
|
$225.000
|
$215.000
|
$215.000
|
|
|
RC PIPE (CL III)(60 IN)
|
LF
|
6.000
|
$275.000
|
$450.000
|
$420.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 30 IN)
|
EA
|
1.000
|
$3,833.000
|
$8,000.000
|
$6,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
2.000
|
$7,500.000
|
$10,000.000
|
$6,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 42 IN)
|
EA
|
1.000
|
$8,700.000
|
$12,000.000
|
$12,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 30 IN)
|
EA
|
2.000
|
$7,500.000
|
$16,000.000
|
$8,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 36 IN)
|
EA
|
1.000
|
$10,800.000
|
$11,000.000
|
$8,500.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 54 IN)
|
EA
|
2.000
|
$9,500.000
|
$14,000.000
|
$16,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 60 IN)
|
EA
|
4.000
|
$11,000.000
|
$18,000.000
|
$18,000.000
|
|
|
WINGWALL (PW - 2) (HW=7 FT)
|
EA
|
2.000
|
$13,000.000
|
$25,000.000
|
$18,000.000
|
|
|
WINGWALL (PW - 2) (HW=8 FT)
|
EA
|
2.000
|
$13,000.000
|
$30,000.000
|
$26,000.000
|
|
|
SET (TY II) (12 IN) (RCP) (6: 1) (P)
|
EA
|
80.000
|
$952.000
|
$550.000
|
$520.000
|
|
|
SET (TY II) (15 IN) (RCP) (6: 1) (P)
|
EA
|
48.000
|
$750.000
|
$550.000
|
$520.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
8.000
|
$1,177.000
|
$650.000
|
$250.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
200.000
|
$825.000
|
$750.000
|
$725.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
16.000
|
$1,050.000
|
$1,000.000
|
$886.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
48.000
|
$1,050.000
|
$1,200.000
|
$1,300.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$2,300.000
|
$1,600.000
|
$1,300.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
9.000
|
$600.000
|
$2,000.000
|
$1,500.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$4,500.000
|
$2,500.000
|
$2,378.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
7.000
|
$3,600.000
|
$4,500.000
|
$2,905.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
3.000
|
$4,800.000
|
$7,000.000
|
$5,301.000
|
|
|
SET (TY II) (42 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$4,600.000
|
$7,500.000
|
$7,933.000
|
|
|
REMOV & RE - LAY PIPE (24 IN)
|
LF
|
8.000
|
$145.000
|
$45.000
|
$100.000
|
|
|
REMOV & RE - LAY PIPE (30 IN)
|
LF
|
4.000
|
$366.000
|
$55.000
|
$100.000
|
|
|
REMOV & RE - LAY PIPE (54 IN)
|
LF
|
12.000
|
$110.000
|
$80.000
|
$100.000
|
|
|
REMOV STR (PIPE)
|
LF
|
3,919.000
|
$30.000
|
$12.000
|
$20.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
72.000
|
$79.000
|
$100.000
|
$100.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$997,156.840
|
$332,500.000
|
$1,139,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
30.000
|
$6,000.000
|
$2,883.080
|
$1,727.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,400.000
|
$35.000
|
$33.000
|
$35.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,400.000
|
$12.000
|
$11.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,430.000
|
$5.000
|
$3.100
|
$3.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,430.000
|
$1.500
|
$0.900
|
$1.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
62.000
|
$140.000
|
$115.000
|
$180.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,970.000
|
$60.000
|
$63.400
|
$75.000
|
|
|
TURNOUTS (ACP)
|
SY
|
2,340.000
|
$30.000
|
$105.500
|
$85.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
5,519.000
|
$35.000
|
$32.000
|
$35.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,100.000
|
$35.000
|
$25.750
|
$25.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,433.000
|
$2,410.000
|
$2,845.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,100.000
|
$3.150
|
$5.000
|
$1.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
12.000
|
$3,338.000
|
$2,625.000
|
$2,825.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
8.000
|
$278.500
|
$300.000
|
$175.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
7.000
|
$1,500.000
|
$600.000
|
$590.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
78.000
|
$240.000
|
$160.000
|
$169.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
14.000
|
$275.000
|
$220.000
|
$179.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
121.000
|
$825.000
|
$775.000
|
$569.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
42.000
|
$1,000.000
|
$810.000
|
$629.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$1,050.000
|
$1,200.000
|
$916.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
2.000
|
$1,750.000
|
$1,195.000
|
$937.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
3.000
|
$1,500.000
|
$1,450.000
|
$1,096.000
|
|
|
RELOCATE SM RD SN SUP&AM(HIST MRKR)
|
EA
|
1.000
|
$100.000
|
$3,000.000
|
$1,000.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
168.000
|
$87.000
|
$60.000
|
$85.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
12.000
|
$30.370
|
$25.500
|
$15.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
84.000
|
$77.000
|
$100.000
|
$69.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
24.000
|
$38.000
|
$25.000
|
$20.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
133,226.000
|
$0.500
|
$0.330
|
$0.330
|
|
|
WK ZN PAV MRK NON-REMOV (W)(RR XING)
|
EA
|
1.000
|
$250.000
|
$320.000
|
$500.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
|
LF
|
8,720.000
|
$0.750
|
$0.400
|
$0.400
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
94,819.000
|
$0.500
|
$0.330
|
$0.330
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
16,185.000
|
$1.250
|
$0.900
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
446.000
|
$7.000
|
$6.770
|
$6.200
|
|
REFL PAV MRK TY I (W)(RR XING)(100MIL)
|
EA
|
2.000
|
$660.000
|
$876.000
|
$650.000
|
|
REFL PAV MRK TY II (W) 24" (SLD)
|
LF
|
446.000
|
$4.200
|
$4.000
|
$3.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
380.000
|
$0.220
|
$1.000
|
$1.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
772.000
|
$0.190
|
$1.000
|
$1.000
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
133,226.000
|
$0.750
|
$1.130
|
$1.050
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
|
LF
|
9,390.000
|
$1.500
|
$1.200
|
$1.200
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
94,819.000
|
$1.800
|
$1.130
|
$1.050
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,666.000
|
$5.000
|
$4.750
|
$4.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
772.000
|
$0.460
|
$1.000
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
1,544.000
|
$0.150
|
$0.750
|
$1.000
|
|
|
D-GR HMA TY-C SAC-A PG64-22
|
TON
|
1,025.000
|
$145.000
|
$153.400
|
$155.000
|
|
|
BONDING COURSE
|
GAL
|
2,236.000
|
$5.100
|
$5.000
|
$3.600
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
155,125.000
|
$1.550
|
$1.320
|
$1.840
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$13,000.000
|
$17,000.000
|
$20,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
360.000
|
$250.000
|
$180.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
240.000
|
$24.250
|
$75.000
|
$50.000
|
|
|
REML & DISPL DRIFTWOOD & DEBRIS
|
LS
|
1.000
|
$7,000.000
|
$5,000.000
|
$15,000.000
|
|
Totals: |
$11,394,325.240
|
$10,767,205.410
|
$10,777,511.720
|