Show Job Controls
Bid Cobra

GRAYSON SH 289 (0202-08-063)

Items: 28

County: GRAYSON
Length: N/A
Highway: SH 289
District: PARIS
Control Number: 0202-08-063
DBE Goal: N/A
Project: STP 2018(609)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $244,279.85
Date: 03/06/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE CULVERTS AND IMPROVE DRAINAGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$244,279.85
$201,885.96
Over/Under Est: -17.35% -$42,393.89
Over/Under Est: 5.99% $14,630.15
Amt Left: 28.25% $57,024.04
Over/Under Est: 9.16% $22,378.65
Amt Left: 32.08% $64,772.54
Delta: -2.99% -$7,748.50
Over/Under Est: 11.33% $27,682.15
Amt Left: 34.71% $70,076.04
Delta: -1.99% -$5,303.50
Over/Under Est: 13.23% $32,330.15
Amt Left: 37.01% $74,724.04
Delta: -1.71% -$4,648.00
Over/Under Est: 13.82% $33,765.55
Amt Left: 37.72% $76,159.44
Delta: -0.52% -$1,435.40
Over/Under Est: 19.42% $47,450.15
Amt Left: 44.5% $89,844.04
Delta: -4.92% -$13,684.60
Over/Under Est: 21.56% $52,654.99
Amt Left: 47.08% $95,048.88
Delta: -1.78% -$5,204.84
Over/Under Est: 72.12% $176,171.65
Amt Left: 108.26% $218,565.54
Delta: -41.60% -$123,516.66
Over/Under Est: 76.54% $186,965.15
Amt Left: 113.61% $229,359.04
Delta: -2.57% -$10,793.50

Bid Items & Bid Tabulations

28 Total 0 of 28
GRAYSON  |  SH 289  |  PARIS  |  0202-08-063  |  03/06/2018  |  $244,279.85  |  STP 2018(609)  |  REPLACE CULVERTS AND IMPROVE DRAINAG...  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
TALBRAN ENTERPRISES LLC
ED BELL CONSTRUCTION COMPANY
BECK-REIT & SONS, LTD.
FNH CONSTRUCTION, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
EARTH BUILDERS, L.P.
TCB CONSTRUCTION, INC
COPPELL CONSTRUCTION CO., INC.
GHB EQUIPMENT COMPANY, L.L.C.
PREPARING ROW
STA 1.000 $1,000.000 $2,500.000 $10,000.000 $3,150.000 $3,500.000 $25,000.000 $6,000.000 $10,000.000 $15,600.000 $31,000.000 $40,000.000
REMOVING CONCRETE(MOW STRIP)
LF 175.000 $20.000 $5.000 $20.000 $13.650 $30.000 $20.000 $18.000 $15.000 $18.000 $29.000 $50.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 41.000 $75.000 $30.000 $100.000 $63.000 $35.000 $35.000 $50.000 $100.000 $35.000 $100.000 $300.000
BLOCK SODDING
SY 378.000 $10.000 $5.000 $6.500 $7.350 $15.000 $6.500 $15.000 $12.000 $4.500 $16.000 $15.000
BROADCAST SEED (TEMP) (WARM)
SY 378.000 $0.500 $1.320 $0.750 $0.250 $1.500 $2.000 $8.000 $8.000 $2.000 $5.500 $5.000
VEGETATIVE WATERING
MG 6.400 $20.000 $10.000 $75.000 $84.000 $100.000 $550.000 $1.000 $200.000 $100.000 $360.000 $300.000
CUT & RESTORE ASPH PAVING
SY 140.000 $170.000 $180.000 $120.000 $63.000 $265.000 $185.000 $100.000 $240.000 $70.500 $215.000 $100.000
FLOWABLE BACKFILL
CY 84.000 $350.000 $180.000 $220.000 $385.000 $255.000 $350.000 $200.000 $150.000 $122.000 $270.000 $300.000
TRENCH EXCAVATION PROTECTION
LF 62.000 $14.000 $25.000 $3.500 $21.000 $40.000 $3.500 $200.000 $20.000 $15.000 $122.000 $300.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 24.000 $275.000 $180.000 $185.000 $315.000 $255.000 $185.000 $200.000 $240.000 $285.000 $346.000 $300.000
CONC BOX CULV (10 FT X 6 FT)
LF 64.000 $800.000 $1,117.000 $1,000.000 $1,365.000 $1,200.000 $1,000.000 $1,100.000 $1,550.000 $1,877.810 $2,200.000 $2,000.000
WINGWALL (PW - 2) (HW=7 FT)
EA 2.000 $20,000.000 $11,800.000 $18,500.000 $16,400.000 $15,000.000 $18,500.000 $20,000.000 $18,000.000 $22,500.000 $22,000.000 $21,000.000
REMOV STR (PIPE)
LF 116.000 $50.000 $50.000 $50.000 $12.600 $110.000 $30.000 $200.000 $100.000 $25.000 $53.000 $300.000
MOBILIZATION
LS 1.000 $21,116.350 $20,000.000 $50,000.000 $22,250.000 $25,000.000 $25,000.000 $25,000.000 $28,000.000 $30,000.000 $41,000.000 $43,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $4,000.000 $2,500.000 $5,500.000 $11,550.000 $3,500.000 $8,500.000 $8,000.000 $4,000.000 $4,500.000 $4,000.000 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $60.000 $30.000 $35.000 $33.000 $35.000 $30.000 $40.000 $65.000 $40.000 $166.000 $200.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $18.000 $10.000 $15.000 $16.500 $10.000 $15.000 $20.000 $20.000 $10.000 $47.000 $40.000
REMOVE METAL BEAM GUARD FENCE
LF 125.000 $10.000 $2.000 $3.000 $4.200 $20.000 $3.000 $5.000 $5.000 $5.000 $44.000 $40.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $500.000 $500.000 $500.000 $525.000 $2,500.000 $500.000 $300.000 $250.000 $150.000 $380.000 $500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $500.000 $500.000 $950.000 $630.000 $3,500.000 $1,500.000 $300.000 $500.000 $350.000 $380.000 $500.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 4.000 $100.000 $35.000 $45.000 $157.500 $75.000 $100.000 $100.000 $120.000 $60.000 $127.000 $150.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3.000 $2.500 $50.000 $25.000 $5.250 $500.000 $5.000 $10.000 $50.000 $5.000 $63.000 $30.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 90.000 $0.800 $22.000 $25.000 $25.000 $15.000 $20.000 $60.000 $22.000 $15.000 $28.000 $15.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 10.000 $0.800 $22.000 $25.000 $25.000 $30.000 $20.000 $60.000 $22.000 $13.000 $28.000 $15.000
REFL PAV MRKR TY II-A-A
EA 1.000 $6.000 $10.000 $62.500 $60.000 $250.000 $15.000 $60.000 $10.000 $10.000 $12.500 $25.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $5,000.000 $5,000.000 $4,113.500 $4,500.000 $6,000.000 $6,000.000 $5,000.000 $9,800.000 $6,000.000 $3,000.000
TMA (STATIONARY)
DAY 31.000 $400.000 $100.000 $210.000 $315.000 $220.000 $150.000 $130.000 $200.000 $265.000 $700.000 $300.000
TMA (MOBILE OPERATION)
HR 10.000 $200.000 $100.000 $70.000 $73.500 $200.000 $85.000 $20.000 $65.000 $50.000 $100.000 $100.000
Totals: $244,279.850 $201,885.960 $258,910.000 $266,658.500 $271,962.000 $276,610.000 $278,045.400 $291,730.000 $296,934.840 $420,451.500 $431,245.000