Show Job Controls
Bid Cobra

EL PASO IH0010 (6457-81-001)

Items: 16

County: EL PASO
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6457-81-001
DBE Goal: 0.0%
Project: RMC - 645781001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,096,690.00
Date: 02/01/2024 (2 years ago)
Contract Number: N/A
Type: FLEXIBLE PAVEMENT STRUCTURE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,096,690.00
$1,140,752.80
Over/Under Est: 4.02% $44,062.80
Over/Under Est: 9.24% $101,360.00
Amt Left: 5.02% $57,297.20
Over/Under Est: 11.68% $128,075.00
Amt Left: 7.36% $84,012.20
Delta: -2.23% -$26,715.00
$1,386,470.00
Over/Under Est: 26.42% $289,780.00
Amt Left: 21.54% $245,717.20
Delta: -13.20% -$161,705.00

Bid Items & Bid Tabulations

16 Total 0 of 16
EL PASO  |  IH0010  |  EL PASO  |  6457-81-001  |  02/01/2024  |  $1,096,690.00  |  RMC - 645781001  |  FLEXIBLE PAVMT STRUCT REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN CONCRETE, LLC
DEL MAR CONTRACTING, INC.
DOUBLE H CONTRACTING INC.
HAWK CONSTRUCTION
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 150.000 $270.000 $310.000 $167.000 $275.000 $230.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 300.000 $280.000 $225.000 $191.000 $275.000 $270.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 150.000 $235.000 $112.000 $126.000 $250.000 $170.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 150.000 $260.000 $225.000 $144.000 $250.000 $190.000
MOBILIZATION
LS 1.000 $50,000.000 $132,042.000 $7,500.000 $60,000.000 $90,000.000
MOBILIZATION (CALLOUT 1)
EA 8.000 $6,000.000 $14,500.000 $11,000.000 $10,000.000 $8,000.000
PREFAB PAV MRK TY B (W)(6")(BRK)
LF 600.000 $15.000 $13.340 $14.000 $10.000 $10.000
PREFAB PAV MRK TY B (W)(6")(SLD)
LF 5,580.000 $15.000 $4.960 $10.000 $10.000 $10.000
PREFAB PAV MRK TY B (Y)(6")(SLD)
LF 660.000 $15.000 $11.000 $14.000 $10.000 $10.000
REFL PAV MRKR TY I-C
EA 10.000 $25.000 $120.000 $72.000 $25.000 $16.000
REFL PAV MRKR TY II-A-A
EA 10.000 $25.000 $120.000 $72.000 $25.000 $16.000
REFL PAV MRKR TY II-C-R
EA 10.000 $25.000 $120.000 $72.000 $25.000 $16.000
PAV SURF PREP FOR MRK (6")
LF 6,840.000 $1.000 $5.000 $2.500 $1.000 $1.000
POTHOLE REPAIR (SAW - CUT)
TON 2,500.000 $270.000 $250.000 $347.000 $320.000 $384.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 5.000 $150.000 $884.000 $700.000 $5.000 $250.000
TMA (STATIONARY)
DAY 40.000 $350.000 $450.000 $400.000 $250.000 $650.000
Totals: $1,096,690.000 $1,140,752.800 $1,198,050.000 $1,224,765.000 $1,386,470.000