EL PASO US 54 (0167-01-120)
Items: 45
County: EL PASO
Length: N/A
Highway: US 54
District: EL PASO
Control Number: 0167-01-120
DBE Goal: N/A
Project: NH 2020(874)
Guaranty: N/A
Time: 25 WORKING DAYS
Engineer's Estimate: $993,342.60
Date: 04/09/2020 (6 years ago)
Contract Number: N/A
Type: MILL AND INLAY (FRONTAGE ROAD)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$993,342.60 | |||
| $719,532.16 |
-27.56%
-$273,810.44
|
|||
| $760,714.02 |
-23.42%
-$232,628.58
|
5.72%
$41,181.86
|
||
| $840,362.36 |
-15.4%
-$152,980.24
|
16.79%
$120,830.20
|
-10.47%
-$79,648.34
|
|
| $926,653.15 |
-6.71%
-$66,689.45
|
28.79%
$207,120.99
|
-10.27%
-$86,290.79
|
|
| $1,016,093.40 |
2.29%
$22,750.80
|
41.22%
$296,561.24
|
-9.65%
-$89,440.25
|
|
| $1,026,698.52 |
3.36%
$33,355.92
|
42.69%
$307,166.36
|
-1.04%
-$10,605.12
|
E
Engineer's Estimate
$993,342.60
1
Awarded
$719,532.16
Over/Under Est:
-27.56%
-$273,810.44
$760,714.02
Over/Under Est:
-23.42%
-$232,628.58
Amt Left:
5.72%
$41,181.86
$840,362.36
Over/Under Est:
-15.4%
-$152,980.24
Amt Left:
16.79%
$120,830.20
Delta:
-10.47%
-$79,648.34
$926,653.15
Over/Under Est:
-6.71%
-$66,689.45
Amt Left:
28.79%
$207,120.99
Delta:
-10.27%
-$86,290.79
$1,016,093.40
Over/Under Est:
2.29%
$22,750.80
Amt Left:
41.22%
$296,561.24
Delta:
-9.65%
-$89,440.25
$1,026,698.52
Over/Under Est:
3.36%
$33,355.92
Amt Left:
42.69%
$307,166.36
Delta:
-1.04%
-$10,605.12
Bid Items & Bid Tabulations
45
Total
0 of 45