COMANCHE SH 6 (0257-05-046)

Items: 131

County: COMANCHE
Length: N/A
Highway: SH 6
District: BROWNWOOD
Control Number: 0257-05-046
DBE Goal: N/A
Project: NH 2020(457)
Guaranty: N/A
Time: 368 WORKING DAYS
Engineer's Estimate: $15,485,237.27
Date: 04/09/2020 (6 years ago)
Contract Number: N/A
Type: CONSTRUCT SUPER 2 HIGHWAY AND SURFACING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$15,485,237.27
$13,793,112.53
Over/Under Est: -10.93% -$1,692,124.74
Over/Under Est: -8.38% -$1,297,668.94
Amt Left: 2.86% $394,455.80
Over/Under Est: -7.23% -$1,119,852.71
Amt Left: 4.15% $572,272.03
Delta: -1.25% -$177,816.23
$15,086,755.32
Over/Under Est: -2.57% -$398,481.95
Amt Left: 9.38% $1,293,642.79
Delta: -5.02% -$721,370.76
$15,972,315.16
Over/Under Est: 3.15% $487,077.89
Amt Left: 15.8% $2,179,202.63
Delta: -5.87% -$885,559.84
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 4.33% $783,709.72
DIIBS SPECIALISTS, LLC 1.98% $358,370.73
BEAR CREEK CONSTRUCTION, LLC 1.86% $336,651.29
D. I. J. CONSTRUCTION, INC. 1.86% $336,651.29
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 1.81% $327,601.52
DALLAS LITE AND BARRICADE, INC. 1.11% $200,904.80
BROCK CONSTRUCTION, LLC 1.01% $182,805.27
GIBSON & ASSOCIATES, INC. 0.66% $119,456.91
BECK-REIT & SONS, LTD. 0.65% $117,646.96
WILKO INDUSTRIAL, L.L.C. 0.50% $90,497.66
SOUTHERN CROSS CONTRACTORS, LLC 0.46% $83,257.85
CONTRACTORS SERVICE COMPANY 0.29% $52,488.64
WEST TEXAS ROCK RESOURCES, LLC 0.24% $43,438.88
AREA WIDE PROTECTIVE, INC. 0.03% $5,429.86
Total: 16.79% $3,038,911.38

Bid Items & Bid Tabulations

131 Total 0 of 131
COMANCHE  |  SH 6  |  BROWNWOOD  |  0257-05-046  |  04/09/2020  |  $15,485,237.27  |  NH 2020(457)  |  CONSTRUCT SUPER 2 HWY AND SURF  |  368 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
JAY MILLS CONTRACTING, INCORPORATED
SMITH & COMPANY
A. L. HELMCAMP, INC.
PREPARING ROW
STA 770.000 $1,000.000 $400.000 $1,000.000 $350.000 $300.000 $361.000
REMOVING CONC (RIPRAP)
SY 171.000 $10.000 $20.000 $20.000 $14.000 $22.000 $41.000
REMOVING CONCRETE(MOW STRIP)
LF 200.000 $6.900 $10.000 $12.000 $12.000 $18.000 $15.000
EXCAVATION (ROADWAY)
CY 17,223.000 $20.000 $12.000 $14.000 $14.000 $24.000 $15.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 9,207.000 $11.000 $9.000 $14.000 $8.000 $20.000 $12.000
BLADING
HR 400.000 $160.000 $120.000 $100.000 $145.000 $120.000 $145.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 604,014.000 $0.220 $0.080 $0.090 $0.090 $0.180 $0.080
DRILL SEEDING (TEMP) (COOL)
SY 604,014.000 $0.110 $0.070 $0.080 $0.080 $0.150 $0.070
PROOF ROLLING
HR 152.000 $85.000 $65.000 $70.000 $85.000 $120.000 $95.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 50,082.000 $45.000 $39.750 $40.000 $38.250 $34.000 $55.000
REWORK BS MTL (TY C)(10")(DENS CONT)
SY 86,318.000 $2.000 $1.000 $1.500 $2.000 $3.000 $3.100
REWRK BS MATL (TY B)(10")(DENS CONT)
SY 35,695.000 $3.000 $1.250 $5.000 $3.000 $10.000 $4.500
PRIME COAT (RC-250)
GAL 40,645.000 $4.000 $3.320 $3.400 $4.350 $4.000 $4.000
ASPH (AC-20-5TR)
GAL 249,968.000 $4.000 $3.140 $3.000 $3.450 $4.000 $3.600
AGGR(TY-B GR-5 SAC-B)
CY 1,478.000 $75.000 $115.000 $85.000 $90.000 $140.000 $130.000
AGGR(TY-PB GR-4 SAC-B)
CY 4,960.000 $110.000 $125.000 $105.000 $100.000 $140.000 $120.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 4,421.000 $100.000 $60.000 $60.000 $69.000 $65.000 $78.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 3,577.000 $25.000 $27.000 $15.000 $27.000 $28.000 $24.000
PLAN & TEXT ASPH CONC PAV(0" TO 1")
SY 2,860.000 $2.000 $5.000 $3.500 $4.000 $4.000 $4.000
PLANE ASPH CONC PAV (2")
SY 105,793.000 $1.150 $1.000 $1.000 $1.450 $1.750 $2.000
CEM STABIL BKFL
CY 721.000 $150.000 $210.000 $150.000 $145.000 $175.000 $210.000
CUT & RESTORING PAV
SY 456.000 $145.000 $125.000 $50.000 $65.000 $50.000 $47.000
TRENCH EXCAVATION PROTECTION
LF 527.000 $5.000 $15.500 $15.000 $3.000 $10.000 $16.000
TEMPORARY SPL SHORING
SF 468.000 $55.000 $45.000 $50.000 $44.000 $10.000 $47.000
EPOXY WATERPROOF FINISH
SF 11,063.000 $20.000 $8.000 $15.000 $10.150 $11.000 $10.000
RIPRAP (CONC)(5 IN)
CY 6.000 $535.000 $600.000 $600.000 $950.000 $850.000 $600.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 42.000 $250.000 $250.000 $125.000 $150.000 $180.000 $220.000
RIPRAP (STONE PROTECTION) (36 IN)
CY 232.000 $150.000 $150.000 $150.000 $150.000 $170.000 $160.000
RIPRAP (MOW STRIP)(4 IN)
CY 675.000 $435.000 $520.000 $475.000 $577.500 $540.000 $520.000
RETROFIT RAIL (TY T631)
LF 550.000 $150.000 $102.000 $125.000 $75.900 $96.000 $85.000
GABION MATTRESSES (GALV)(12 IN)
SY 195.000 $180.000 $159.000 $125.000 $120.000 $125.000 $125.000
GABIONS (3' X 3')(GALV)
CY 236.900 $250.000 $265.000 $450.000 $410.000 $375.000 $270.000
CONC BOX CULV (4 FT X 2 FT)
LF 348.000 $325.000 $425.000 $250.000 $334.000 $340.000 $420.000
CONC BOX CULV (4 FT X 3 FT)
LF 90.000 $350.000 $450.000 $300.000 $372.000 $380.000 $450.000
RC PIPE (CL III)(18 IN)
LF 112.000 $60.000 $95.000 $50.000 $58.000 $52.000 $58.000
RC PIPE (CL III)(24 IN)
LF 168.000 $95.000 $106.000 $70.000 $74.000 $65.000 $110.000
RC PIPE (CL III)(30 IN)
LF 628.000 $135.000 $154.000 $110.000 $101.000 $90.000 $150.000
RC PIPE (CL III)(36 IN)
LF 80.000 $170.000 $218.000 $160.000 $146.000 $135.000 $215.000
RC PIPE (CL III)(60 IN)
LF 90.000 $300.000 $441.000 $300.000 $362.000 $320.000 $435.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $7,700.000 $5,100.000 $4,200.000 $6,160.000 $5,600.000 $5,100.000
HEADWALL (CH - PW - 0) (DIA= 60 IN)
EA 1.000 $13,000.000 $16,500.000 $11,700.000 $19,800.000 $18,000.000 $16,000.000
WINGWALL (PW - 1) (HW=3 FT)
EA 3.000 $7,700.000 $6,250.000 $6,400.000 $6,160.000 $5,500.000 $6,200.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C)
EA 4.000 $6,000.000 $3,700.000 $3,000.000 $3,520.000 $3,200.000 $3,700.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(3:1) (C)
EA 3.000 $6,500.000 $4,800.000 $3,700.000 $4,070.000 $3,700.000 $4,700.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 1.000 $7,100.000 $5,800.000 $5,700.000 $6,050.000 $5,500.000 $5,700.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $8,000.000 $5,300.000 $5,400.000 $8,250.000 $7,500.000 $5,300.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C)
EA 1.000 $8,500.000 $6,900.000 $7,200.000 $5,500.000 $5,000.000 $6,900.000
SET (TY I)(S= 8 FT)(HW= 5 FT)(3:1) (C)
EA 2.000 $13,000.000 $13,300.000 $14,000.000 $11,880.000 $10,800.000 $13,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 6.000 $900.000 $1,000.000 $800.000 $950.000 $900.000 $950.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $1,150.000 $1,200.000 $1,200.000 $1,100.000 $1,100.000 $1,100.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 15.000 $2,400.000 $1,500.000 $1,200.000 $1,300.000 $2,800.000 $1,100.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 2.000 $2,900.000 $2,250.000 $3,000.000 $2,200.000 $4,300.000 $2,100.000
SET (TY II) (60 IN) (RCP) (3: 1) (C)
EA 1.000 $4,800.000 $7,000.000 $8,000.000 $12,650.000 $11,500.000 $6,900.000
REMOV STR (PIPE)
LF 1,234.000 $15.000 $10.500 $10.000 $16.000 $8.000 $11.000
REMOV STR (BOX CULVERT)
LF 87.000 $48.000 $58.000 $60.000 $80.000 $90.000 $58.000
REMOV STR (PIPE)
EA 6.000 $400.000 $160.000 $400.000 $315.000 $1,200.000 $158.000
MOBILIZATION
LS 1.000 $1,150,000.000 $1,300,000.000 $1,400,000.000 $1,200,000.000 $1,300,000.000 $1,500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $7,500.000 $12,000.000 $4,000.000 $5,750.000 $9,000.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 3,248.000 $30.000 $26.000 $28.000 $27.500 $28.000 $26.000
ROCK FILTER DAMS (REMOVE)
LF 3,248.000 $8.150 $7.760 $3.000 $8.550 $10.000 $8.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 828.000 $25.000 $22.500 $10.000 $24.750 $25.000 $24.000
CONSTRUCTION EXITS (REMOVE)
SY 828.000 $7.000 $8.290 $3.000 $9.150 $10.000 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 49,911.000 $3.150 $2.750 $2.750 $2.150 $2.750 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 49,911.000 $1.000 $0.360 $0.500 $0.400 $1.000 $0.400
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 2,433.000 $4.000 $7.500 $7.000 $6.400 $7.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,433.000 $1.200 $0.570 $1.000 $0.650 $1.500 $0.600
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 390.000 $45.000 $107.000 $35.000 $85.000 $100.000 $102.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,050.000 $6.900 $26.500 $20.000 $10.000 $30.000 $36.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 390.000 $9.250 $26.000 $30.000 $15.000 $32.000 $33.000
INTERSECTIONS (ACP)
SY 3,317.000 $35.000 $38.000 $30.000 $40.000 $15.000 $24.000
DRIVEWAYS (ACP)
SY 1,008.000 $35.000 $30.000 $25.000 $32.250 $25.000 $24.000
DRIVEWAYS (SURF TREAT)
SY 3,301.000 $25.000 $35.000 $20.000 $21.000 $22.000 $23.000
TURNOUTS (SURF TREAT)
SY 220.000 $25.000 $50.000 $20.000 $20.000 $38.000 $23.000
RUMBLE STRIPS (SHOULDER)
LF 153,329.000 $0.180 $0.170 $0.180 $0.090 $0.150 $0.140
RUMBLE STRIPS (CENTERLINE)
LF 77,421.000 $0.190 $0.180 $0.180 $0.090 $0.150 $0.140
MTL W-BEAM GD FEN (STEEL POST)
LF 6,000.000 $32.000 $25.540 $28.000 $24.750 $24.000 $20.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,975.000 $2,360.000 $2,000.000 $1,850.000 $1,725.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 2,275.000 $2.500 $4.260 $5.000 $1.950 $4.000 $2.200
REMOVE TERMINAL ANCHOR SECTION
EA 14.000 $250.000 $133.000 $150.000 $165.000 $125.000 $260.000
GUARDRAIL END TREATMENT (INSTALL)
EA 66.000 $3,000.000 $2,660.000 $3,000.000 $2,706.000 $2,500.000 $2,400.000
GUARDRAIL END TREATMENT (REMOVE)
EA 14.000 $360.000 $266.000 $300.000 $220.000 $250.000 $260.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $2,000.000 $1,488.000 $1,500.000 $2,200.000 $4,500.000 $1,100.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $1,200.000 $1,000.000 $1,600.000 $1,500.000 $1,100.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $11,500.000 $11,000.000 $7,500.000 $6,950.000 $11,000.000 $12,000.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 22.000 $215.000 $200.000 $225.000 $159.500 $310.000 $210.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 2.000 $265.000 $210.000 $250.000 $170.500 $330.000 $240.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 58.000 $500.000 $499.000 $525.000 $490.000 $650.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 47.000 $600.000 $626.000 $625.000 $626.000 $750.000 $620.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $750.000 $784.000 $800.000 $800.000 $800.000 $770.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $680.000 $750.000 $800.000 $778.000 $900.000 $870.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 9.000 $770.000 $880.000 $900.000 $910.000 $1,300.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 2.000 $870.000 $944.000 $1,000.000 $940.000 $1,500.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 1.000 $1,000.000 $977.000 $1,000.000 $1,015.000 $1,600.000 $860.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 3.000 $400.000 $488.000 $500.000 $425.000 $1,400.000 $370.000
REMOVE SM RD SN SUP&AM
EA 101.000 $150.000 $73.000 $90.000 $62.000 $150.000 $95.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 63.000 $22.000 $30.000 $35.000 $22.000 $28.000 $26.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 36.000 $69.000 $65.000 $70.000 $59.400 $125.000 $65.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 255.000 $30.000 $48.000 $50.000 $24.200 $25.000 $36.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 52,686.000 $0.250 $0.390 $0.400 $0.410 $0.400 $0.380
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 52,686.000 $0.250 $0.390 $0.400 $0.410 $0.400 $0.380
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 9,903.000 $3.500 $1.490 $2.000 $1.540 $1.400 $1.500
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 32,544.000 $0.650 $0.620 $0.650 $0.640 $0.600 $0.600
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 60,288.000 $0.650 $0.660 $0.700 $0.680 $0.600 $0.650
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 2,046.000 $1.000 $0.850 $1.000 $0.880 $0.800 $0.850
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,500.000 $1.000 $1.060 $2.000 $1.100 $1.000 $1.100
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 125.000 $10.000 $9.580 $10.000 $9.900 $9.000 $10.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 716.000 $5.950 $5.320 $6.000 $5.500 $5.000 $5.500
REF PROF PAV MRK TY I(W)4"(SLD)(060MIL)
LF 97,380.000 $0.540 $0.550 $0.600 $0.570 $0.500 $0.550
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 28,651.000 $0.540 $0.710 $0.700 $0.740 $0.700 $0.700
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 10,950.000 $0.540 $0.760 $0.750 $0.780 $0.700 $0.750
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 11,680.000 $0.250 $0.370 $0.400 $0.390 $0.350 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 154,310.000 $0.250 $0.340 $0.400 $0.350 $0.350 $0.350
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 420.000 $0.400 $0.640 $1.000 $0.660 $0.600 $0.650
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 159,570.000 $0.250 $0.350 $0.400 $0.360 $0.350 $0.350
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $200.000 $271.320 $300.000 $280.500 $255.000 $270.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 12.000 $800.000 $654.360 $750.000 $676.500 $615.000 $650.000
PREFAB PAV MRK TY C (W) (WORD)
EA 4.000 $280.000 $319.200 $400.000 $330.000 $300.000 $320.000
REFL PAV MRKR TY I-C
EA 649.000 $4.000 $3.620 $4.000 $3.740 $3.500 $4.000
REFL PAV MRKR TY II-A-A
EA 2,098.000 $3.500 $3.620 $4.000 $3.740 $3.500 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 48,816.000 $0.550 $0.800 $0.500 $0.440 $1.000 $1.000
D-GR HMA TY-B PG64-22
TON 5,730.000 $65.000 $80.000 $85.000 $100.000 $90.000 $91.000
D-GR HMA TY-C PG76-22 (LEVEL-UP)
TON 2,000.000 $120.000 $99.000 $90.000 $111.000 $105.000 $113.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 1,776.000 $120.000 $94.000 $95.000 $111.000 $95.000 $103.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 1,500.000 $120.000 $97.000 $100.000 $111.000 $100.000 $107.000
SP MIXES SP-D SAC-B PG76-22
TON 35,672.000 $95.000 $86.000 $87.000 $108.000 $95.000 $99.000
TACK COAT
GAL 42,120.000 $4.000 $0.010 $3.500 $0.010 $4.000 $3.300
DEWATERING BAGS
EA 6.000 $2,000.000 $500.000 $750.000 $150.000 $500.000 $2,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 120.000 $100.000 $150.000 $100.000 $95.000 $50.000 $200.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 5,475.000 $4.000 $3.190 $5.000 $3.300 $3.000 $3.200
TMA (STATIONARY)
DAY 60.000 $200.000 $500.000 $150.000 $200.000 $300.000 $350.000
TMA (MOBILE OPERATION)
DAY 66.000 $150.000 $665.000 $300.000 $100.000 $125.000 $90.000
Totals: $15,485,237.270 $13,793,112.530 $14,187,568.330 $14,365,384.560 $15,086,755.320 $15,972,315.160