CLAY SS0510 (6318-92-001)

Items: 29

County: CLAY
Length: N/A
Highway: SS0510
District: WICHITA FALLS
Control Number: 6318-92-001
DBE Goal: N/A
Project: RMC - 631892001
Guaranty: N/A
Time: 52 W
Engineer's Estimate: $221,890.40
Date: 10/04/2017 (8 years ago)
Contract Number: N/A
Type: DRAINAGE IMPORVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$221,890.40
$227,990.00
Over/Under Est: 2.75% $6,099.60
Over/Under Est: 3.01% $6,689.60
Amt Left: 0.26% $590.00
Over/Under Est: 24.48% $54,314.60
Amt Left: 21.15% $48,215.00
Delta: -20.84% -$47,625.00
Over/Under Est: 24.48% $54,320.10
Amt Left: 21.15% $48,220.50
Delta: 0.00% -$5.50
Over/Under Est: 65.64% $145,646.60
Amt Left: 61.21% $139,547.00
Delta: -33.06% -$91,326.50

Bid Items & Bid Tabulations

29 Total 0 of 29
CLAY  |  SS0510  |  WICHITA FALLS  |  6318-92-001  |  10/04/2017  |  $221,890.40  |  RMC - 631892001  |  DRAINAGE IMPORVEMENT  |  52 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
EARTH BUILDERS, L.P.
HIGHWAY 19 CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
O. TREVINO CONSTRUCTION, LLC
REMOVING CONC (CURB AND GUTTER)
LF 72.000 $10.000 $25.000 $5.000 $20.000 $20.000 $21.500
REMOVING CONCRETE(MOW STRIP)
LF 556.000 $10.000 $10.000 $5.000 $10.000 $20.000 $16.500
EXCAVATION (CHANNEL)
CY 460.000 $15.000 $20.000 $25.000 $30.000 $30.000 $37.500
FURNISHING AND PLACING TOPSOIL (4")
SY 3,050.000 $3.000 $3.500 $4.000 $5.000 $5.000 $9.500
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 3,050.000 $1.000 $0.500 $0.500 $1.000 $2.000 $1.750
VEGETATIVE WATERING
MG 26.000 $20.000 $20.000 $100.000 $10.000 $150.000 $400.000
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 3,050.000 $3.000 $3.000 $5.000 $10.000 $6.250 $13.250
D-GR HMA(SQ) TY-D SAC-B PG64-22
TON 198.000 $150.000 $155.000 $150.000 $250.000 $200.000 $222.000
PLANE ASPH CONC PAV(0" TO 4")
SY 2,400.000 $5.000 $5.000 $8.000 $10.000 $15.000 $3.000
TRENCH EXCAVATION PROTECTION
LF 158.000 $3.000 $10.000 $10.000 $10.000 $3.500 $35.500
TEMPORARY SPL SHORING
SF 20.000 $100.000 $75.000 $150.000 $100.000 $50.000 $120.000
RIPRAP (MOW STRIP)(4 IN)
CY 14.800 $500.000 $1,000.000 $650.000 $550.000 $650.000 $900.000
RC PIPE (CL III)(30 IN)
LF 180.000 $100.000 $170.000 $150.000 $180.000 $105.000 $200.000
INLET(COMPL)(CURB)(SPL)
EA 2.000 $15,000.000 $5,500.000 $4,500.000 $5,000.000 $5,000.000 $10,000.000
HEADWALL (CH - FW - 0) (DIA= 30 IN)
EA 1.000 $8,500.000 $11,000.000 $3,500.000 $5,000.000 $5,000.000 $13,850.000
REMOV STR (INLET)
EA 2.000 $400.000 $1,500.000 $1,500.000 $1,000.000 $2,500.000 $2,825.000
REMOV STR (PIPE)
LF 180.000 $40.000 $22.000 $10.000 $50.000 $30.000 $35.000
MOBILIZATION
LS 1.000 $20,076.400 $22,000.000 $20,000.000 $25,000.000 $20,000.000 $36,750.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,000.000 $5,000.000 $3,000.000 $5,000.000 $8,500.000 $8,850.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 110.000 $10.000 $7.000 $12.000 $6.000 $12.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 110.000 $5.000 $3.000 $2.000 $2.000 $8.000 $8.000
CONC CURB & GUTTER (TY II)
LF 40.000 $50.000 $110.000 $100.000 $50.000 $55.000 $75.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 325.000 $25.000 $13.000 $30.000 $15.000 $20.000 $30.000
TRANSITION ADJUSTMENT
EA 4.000 $700.000 $450.000 $1,500.000 $500.000 $1,500.000 $1,300.000
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $5.000 $7.000 $5.000 $10.000 $3.000 $7.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 4.000 $2,500.000 $2,000.000 $2,500.000 $1,000.000 $1,250.000 $2,650.000
WIRE FENCE (TY C)
LF 100.000 $25.000 $25.000 $20.000 $17.000 $20.000 $30.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 300.000 $4.000 $8.000 $25.000 $10.000 $4.000 $1.500
ELIM EXT PAV MRK & MRKS (4")
LF 760.000 $4.000 $8.000 $5.000 $2.000 $4.000 $1.250
Totals: $221,890.400 $227,990.000 $228,580.000 $276,205.000 $276,210.500 $367,537.000